Effluent Treatment System Draft Statement of Work.pdf
PDF 267 KB Posted
- Attached to
- Effluent Treatment System
- Solicitation number
- OFPM_TEAM_SS26-03
About this file
This Statement of Work (SOW) details the comprehensive renovation of the Effluent Treatment System located at the National Institute of Standards and Technology (NIST) in Gaithersburg, Maryland. The project requires a complete rebuild of the system's internal components, including demolition and replacement of the wet tank's floor, support members, safety blowers, heaters, stir/agitation motor, PH monitoring probes, electrical wiring, and conduit. The contractor must have specialized equipment and experience to handle environmental issues associated with raw effluent.
Key project specifications include a 200-day performance period, work conducted between 6 AM and 6 PM on Federal work days, and strict safety and badging requirements. The contractor must provide a detailed safety plan, weekly project updates, and ensure all personnel have appropriate NIST Green Badges. Payment will be made monthly, with invoices subject to review and approval by the Contracting Officer's Representative (COR). The project emphasizes workmanship and requires leaving a fully functional effluent treatment system that meets current regulatory requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| EFFLUENT TANK SSN.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 | P a g e
Statement of Work
Site - Effluent Treatment System
Operations Engineering Group, OFPM, NIST
Gaithersburg, MD
1. Background Information
2. Purpose
3. Place of Performance
4. Regular business Hours
5. Period of Performance
6. Specific Requirements / Tasks
TASK 1: General TASK 2: Demolition TASK 3: Installation TASK 4: Work General Requirements
7. Safety TASK 1: Safety Related Requirements Task 2: Safety Related Training
8. Homeland Security Presidential Directive (HSPD)-12
9. General Requirements
10. Badging
11. Issuance Of Building Keys
12. Government Furnished Material
13. Inspection & Acceptance
14. Payment Schedule
2 | P a g e
1. BACKGROUND INFORMATION
The Gaithersburg Site Effluent Treatment System is located on the south end of campus at the “E” Gate intersection at Center Drive. Built in the mid-1990’s, the system was designed to comply with Washington Sanitary Sewer Commission (WSSC) effluent discharge requirements.
The system is centered around a large concrete tank (wet tank) that provides primary effluent treatment with a stir / chop agitator system PH monitoring and treatment.
Currently, the interior wet tank operational, structural, and life safety systems have rendered this system inoperable. Inspection has found the primary floor support has detached along the south side of the wet tank. This has caused for the aluminum grating to sag, and no longer safe for personnel entry. More, there are areas of the aluminum grate that have literally rotted away.
Further inspection revealed even more issues.
Internal blowers to address the confined space ventilation requirements are inoperable and heavily corroded.
The system internal heater is inoperable and heavily corroded.
The motor and stir mechanism is seized. Additionally, the motor is electrically inoperable.
The explosion proof electrical wiring and conduit is in very poor condition.
In general, the entire wet tank and systems needs to be renovated and brought back to operable condition. This requires a complete replacement of all tank components. This includes an entire new floor surface and all support members, safety blowers and heaters, new stir / agitation motor and shaft system, PH monitoring probes and data signaling, epoxy lining of the wet tank, lighting, electrical outlets, and demolition and replacement of all the explosion proof electrical wiring and conduit. Other work as required to conform to current regulatory requirements, as required.
All the work above complicated by environmental factors and the presence of site raw effluent.
The contractor doing this remediation and repair will need to have specialized equipment and experience to deal with the multitude of environmental issues and trained qualified staff to complete this work.
2. PURPOSE
The Site Effluent Treatment System requires a complete rebuild of all internal components to fulfill operational, regulatory, and life safety requires.
3. PLACE OF PERFORMANCE
Work is located near Gate E, NIST, Gaithersburg, Maryland.
4. REGULAR BUSINESS HOURS
Regular business hours are Monday through Friday, 6 AM to 6 PM Eastern Time, excluding Federal holidays and NIST closures.
3 | P a g e
5. PERIOD OF PERFORMANCE
The period of performance for this project is 200 days from signing Notice to Proceed.
Any extension of period of performance shall be made via Email to COR and CO and be at no additional cost to government.
6. SPECIFIC REQUIREMENTS
TASK 1: General
1. The contractor will provide all supervision, labor, materials, tools and equipment to complete the work
2. The contractor will be solely responsible for all subcontractor activity not limited to work schedule and quality.
3. The contractor will provide drawings/datasheets (to include cut sheets for equipment and material) of new equipment/materials to be installed no later than 20 days from signed Notice to Proceed.
4. Contractor shall enforce pre-approved PPE requirements for staff and subcontractors exposed to raw sewage.
TASK 2: Wet Tank Work
1. NIST personnel will operate all wet tank diversion valves and direct flow away from/around the wet well to facilitate work within the wet well.
The contractor Will:
1. Refer “NIST Site Effluent Treatment System dwg – Combined” and utilize original specification therein to determine replacement material and other repair / renovation specification.
a. Contractor will notify NIST of any required change or upgrade for equipment and or regulatory requirements.
TASK 3: Demolition
2. Demolish and remove all structural, operational, and electrical components in the wet tank.
a. Remove both exterior hatches.
b. Remove agitation motor, mounting base, and chopper shaft and blade.
c. Remove/ exhaust fan.
d. Remove unit heater.
4 | P a g e
e. Remove pH sensor and associated junction box.
f. Remove existing interior lights and control circuits.
g. Remove existing explosion proof conduit and related electrical components.
h. Remove floor supports and grating entirely (to walls).
i. Remove both wet well ladders.
3. Clean base of wet tank to meet manufactures requirements to install epoxy coating in wet well.
TASK 3: Installation
The contractor will:
1. Epoxy coating wet tank:
a. The entire wet tank will be epoxy coated – top to bottom.
b. Two (2) coats of Tnemec Series 435 (or similar) @ 15-20 mils per coat DFT.
2. Install new wet well ladders with 2 FRP ladders.
a. Ladders to meet ANSI standard.
b. Install new anti-rusting / anti-corrosion climbing posts
3. Install new exterior hatches to match existing, or similar.
4. Install new floor and supports (including wall attachment brackets or supports) utilizing FRP supports and grating.
a. FRP grating will be of non-slip design.
b. Floor rating design will be for 150 PSF.
5. Contractor will provide detail for wall anchors utilized for flooring, ladders, and equipment.
a. Contractor will utilize wall anchors and material generally that will withstand the damp interior conditions of the wet well.
6. Replace explosion proof agitation motor and agitation / chopping shaft and blade assembly per specification - minimum.
a. Replace agitation motor support / base utilizing FRP material.
b. Replace and provide detail on
i. Mixer construction and assembly support.
7. Replace interior lights and control circuits.
a. Install 1 4 gang 100V electrical outlet on interior wall.
8. Replace the explosion proof exhaust fan per the specification.
9. Replace the explosion proof unit heater.
10. Replace the PH sensor and associated junction box.
11. Replace the explosion proof conduit and associated components.
TASK 4: Work General Requirements
1. The contractor shall:
a. Independently verify all conditions.
b. Provide all special PPE, hazard plans within 10 days of award. This is separate from the safety plan.
5 | P a g e
2. All electrical work will only be conducted by a National Electric Code trained and qualified electrician.
3. Material submittals shall be submitted within 10 days of notice to proceed.
4. Contractor will be the primary NIST approved escort for all elements of this project.
5. Contractor will coordinate all trades and staff and propose a work progression timeline to be approved.
6. Contractor shall develop and enforce specific PPE requirements for staff and subcontractors addressing the specific hazards of this contract.
a. Specific plans will need to be approved for this requirement.
7. Contractor shall provide labor, material, rigging equipment and supplies, and other material as required to complete this project.
8. The contractor shall conduct work during duty hours unless specifically authorized out of hours is approved by COR.
9. Contractor will source and obtain properly pipe sized ANSI self-adhesive pipe markers – SANITARY DRAIN and STORM WATER (Green & White).
a. On sanitary and storm piping, labels will be placed to be visible from floor level at an interval of 10’ between labels.
10. Contractor will obtain any other pipe label damaged or removed from other piping and replace with same size and coloration.
11. All waste and debris will be removed to the contractor’s lawful disposal site.
7. SAFETY
NIST is committed to maintaining a work environment that safeguards the public and the environment, as well as personnel and property.
1. Within 5 days of contract award, the contractor shall provide COR with an OSHA compliant safety plan for contract activity.
a. The Safety Plan shall specify how the company’s policies and practices will comply with each of the applicable standards, laws, and codes.
2. The contracting officer will approve or provide written comments regarding the plan to the contractor within seven (10) days of receipt.
a. Contractor will submit a revised safety plan within seven (7) days with required information for the contracting officer to review.
b. This cycle may be repeated, if necessary, until the contracting officer determines the safety plan to be acceptable.
TASK 1: SAFETY RELATED EQUIPMENT
The Contractor shall:
a. Provide all safety-related equipment required to perform the work under this award, including personal protective equipment (PPE) and other
6 | P a g e equipment that is required or appropriate to protect contractor personnel and other personnel on the NIST campus.
b. Contractor-provided personal protective equipment shall include, at a minimum, hard hats, safety shoes, safety glasses (prescription or standard), respiratory protection (powered air purifying respirator or full-face mask respirator), high visibility clothing and gloves that meet applicable OSHA standards for PPE.
TASK 2: SAFETY RELATED TRAINING
The Contractor shall:
a. Provide safety-related training required by applicable OSHA, state and local regulations or standards to affected contractor personnel (including subcontractor personnel) that perform work under this award.
i. Such training may include, for example, training for proper use of PPE, respirator use, fall protection, crane operation, forklift operation; electrical safety, or other safety-related topics.
b. Maintain records of safety training provided to contractor personnel (including subcontractor personnel) that perform work on this award.
c. The contractor shall make those records available to the contracting officer, contracting officer’s representative for the award, or other authorized personnel within 3 business days of receipt of their written request, and annually thereafter or upon request.
8. Homeland Security Presidential Directive (HSPD)-12
1. The Contractor (and/or any subcontractor) and its employees who require physical access to NIST facilities or logical access to NIST IT networks or systems must comply with Homeland Security Presidential Directive (HSPD)-12, Policy for a Common Identification Standard for Federal Employees and Contractors; OMB M-05-24; OMB M-19-17; FIPS 201, Personal Identity Verification (PIV) of Federal Employees and Contractors; NIST HSPD-12 policy; and Executive Order 13467, Part 1 §1.2.
1. THIS SECTION APPLIES TO THIS CONTRACT WITH REGARD TO BADGING – SEE
SECTION BELOW
2. Position Sensitivity Designations Requirement
a. The following position sensitivity designation levels apply to this solicitation/contact:
Low / None
7 | P a g e
9. GENERAL REQUIREMENTS
1. A notice to proceed / kick-off meeting cannot be held until the safety plan is approved.
2. Within 10 days of Notice to Proceed provide submittals for contract materials.
3. Within 7 days of notice to proceed, provide a schedule for contracted work.
4. Contractor shall provide COR a weekly update (**) on all project activity via email with the following information due on the Tuesday after the week being reported on:
a. Adherence to projected schedule (on time or other)
b. Daily employee list and hours
c. Major work activity
d. Task completion percentages
e. Problems encountered
f. Changes to scope or methodology
g. Change orders (Pending, presented, and completion on project (%)
h. Other items that affect timely completion of contracted work or project conditions.
i. Due Thursday by 2Pm during the term of contract.
(**) During periods of inactivity the contractor shall submit an abbreviated report.
5. The Contractor(s) shall be on the NIST grounds only between the hours of 6:00 a.m. and 5:30 p.m. (normal work hours) on normal Federal work-days.
a. Should the Contractor(s) desire to work at times other than those specified above, the dates and hours must be scheduled in advance and approved by the NIST Security Office through the Contracting Officer.
b. After hours work will require a government approved escort 100% of the time.
6. Contractor personnel are required to wear identification badges at all times on the NIST grounds.
7. The Gate “F” at the National Institute of Standards and Technology site shall be used for material supply and personnel by the Contractor and subcontractors unless otherwise directed by the COR or during out of hours access.
8. See “GUIDELINES FOR OFPM CONTRACTORS AND A/E FIRMS PERFORMING SITE INVESTIGATIONS AND FIELDWORK (including construction) AT THE NATIONAL
INSTITUTE OF STANDARDS AND TECHNOLOGY GAITHERSBURG, MD”.
12. BADGING
1. All personal entering the NIST Campus, including paper pass visitors and delivery drivers, from any entity, are required to havfe REAL ID.
a. NO EXCEPTIONS.
2. Contractor shall have one supervisory person with a NIST Green Badge prior to starting work.
8 | P a g e
a. Contractor will have at least one person with current NIST Escort Training and badge for the duration of this contract.
b. Requires obtaining a NIST Green Badge before receiving the escort endorsement.
3. All other contractor personnel shall submit completed NIST badge applications to obtain a Green PIV badge to COR within 10 days of contract award for any individuals who will be working on this project but are not already issued a NIST site badge.
a. The COR will provide application forms as required.
b. Contractor will provide a list of all personnel to be badged with full name (first, middle, last, name) company employed with and position description.
c. It is essential that contractor personnel utilize a personal, actively monitored email address, or a central work email monitored daily by others, to ensure proper communication during the badging process.
4. White visitor badge usage is very limited and restricted.
a. A person can only utilize a white paper badge a total of 14 days over the preceding 365 days, not a calendar year
b. The government strongly recommends all required contractor and sub-contractor staff planning to enter the NIST Campus become Green Badged. This includes delivery drivers, supervisors, and others in staff supervision or contractual relationship warrant.
c. Any person requesting a white badge / paper pass must provide first, middle, and last name and country of citizenship.
d. If a non-US citizen, a form 1260 will be required with personal documents to confirm identity / citizenship.
5. Contractor is solely responsible for obtaining all required badging documentation and assumes all coordination responsibility between the COR and staff / sub-contractors.
11. ISSUANCE OF BUILDING KEYS
Does not apply to this contract.
12. GOVERNMENT FURNISHED MATERIAL
1. The Government not providing any property, material, or equipment for this project.
13. INSPECTION & ACCEPTANCE
1. The contractor shall complete all work tasks in a workmanship manner, complete and leaving a fully functional system.
9 | P a g e
14. PAYMENT SCHEDULE
1. Contractor will invoice only once per month.
a. Contractor will submit a “paper copy” of the invoice for review and approval by
COR prior to submitting to the government for payment.
b. Certified payroll will be submitted to COR prior to submitting invoice to the government for payment.
c. Final payment, is allowed in the same month a previous payment has been made, providing all closure documents (release of claims, completed punch lists, final certified payroll, and other required documentation) has been submitted and approved.
Statement of Work