REBID
TURTLE CREEK ROAD BRIDGE
REINFORCED CONCRETE BRIDGE DECK SYSTEM WITH BARRIER CURB
EAST BUFFALO TOWNSHIP
UNION COUNTY, PENNSYLVANIA
GENERAL CONDITIONS AND INSTRUCTIONS TO BIDDERS
TO MS-944
PLEASE READ CAREFULLY
These bidding documents are supplementary to the conditions set forth in the attached PennDOT MS-944 forms.
Sealed bids will be received online via PennBID on behalf of East Buffalo Township, Union County, until 1:00 p.m. (prevailing time) on Monday, September 8, 2025, via PennBid, for the construction of an 8” reinforced concrete bridge deck and associated barrier curb for the Township’s Turtle Creek Road bridge replacement project.
Bids will be publicly opened and read at 1:01 p.m. (prevailing time) on Monday, September 8, 2025, at the East Buffalo Township Municipal Building, 589 Fairground Road, Lewisburg, PA 17837, by the Township Staff.
Award for the Contract may be made by the Board of Supervisors to the lowest responsible bidder, as determined by the Board, at their regularly scheduled meeting, Monday, September 8, 2025, at 5:30 p.m., held at the East Buffalo Township Municipal Building.
Bidders are advised that this Project is considered to be “construction” as defined by the Pennsylvania Prevailing Wage Law, Act 442 of 1961, as amended, and is subject to Pennsylvania Prevailing Wage.
Bids will remain subject to acceptance for the period of 90 days, but the Township may, in its sole discretion, release any bid and return the bid security prior to the end of this period.
East Buffalo Township reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids.
Bidders shall be aware of the following General Criteria:
1. East Buffalo Township, Union County, Pennsylvania, (Township) is exempt from all excise taxes and sales tax. No tax shall be included in the bid price.
2. The Township does not discriminate on the basis of race, color, national origin, sex, religion, age, disability, or familial status in employment or the provision of services.
ADDITIONAL CONDITIONS AND INSTRUCTIONS TO BIDDERS TO MS-944
REBID Turtle Creek Road Bridge Concrete Deck with Barrier Curb
3. The Township is an Equal Opportunity/Affirmative Action Employer.
4. The successful bidder(s) must ensure that employees and applicants for employment are not discriminated against because of their race, color, religion, sex, national origin, or disability.
5. All Bidders and/or their subcontractors are required be PennDOT prequalified for the work described herein:
PennDOT prequalification IS REQUIRED; bidders shall be prequalified for Cement Concrete Structures – Code ‘S’. CONTRACTOR MUST PROVIDE COPY OF PENNDOT PRE-QUALIFICATION as part of bid submittal.
6. All materials, products, equipment and/or suppliers shall be included in the following
Commonwealth of Pennsylvania Department of Transportation bulletins, unless otherwise indicated in the bidding documents:
Commonwealth of Pennsylvania Department of Transportation, Bulletin 15, Qualified Products List for Construction, Publication 35
7. All work and materials shall conform to the following standards and specifications, unless otherwise approved in advance by the Township:
a. Pennsylvania Statute, Title 73, Chapter 25, Steel Products Procurement Act, of 1978, as amended,
b. Commonwealth of Pennsylvania, Department of Transportation, Design Manual Part 4 - Structures, Publication 15M, dated April 2015, as amended;
c. Commonwealth of Pennsylvania, Department of Transportation, Road Construction Standards, Publication 72M, dated June 2010, as amended;
d. Commonwealth of Pennsylvania Department of Transportation, Temporary Traffic Control Guidelines, Publication 213, dated June 2014, as amended;
e. Commonwealth of Pennsylvania, Department of Transportation, Bridge Standards for Bridge Design, Publication 218M, dated September 2010, as amended;
f. Commonwealth of Pennsylvania Department of Transportation, Specifications, Publication 408/2016, as amended;
g. AASHTO/AWS Bridge Welding Code D1.5M/D1.5, 2008;
h. AASHTO/AWS Bridge Welding Code D1.1/D1.1M:2008 for welding not covered in
D1.5M/D1.5, 2008;
i. Attached US Bridge Design Drawings;
j. Attached HRG Turtle Creek Road Drawings;
k. And these additional conditions.
8. This Project is considered to be “construction” as defined by the Pennsylvania Prevailing Wage Act 442 of 1961, and is subject to prevailing wage; the successful bidder(s) shall pay no less than the prevailing wage rates as set forth in Determination 25-06939, attached.
Two (2) copies of the Weekly Payroll Certification forms shall accompany the successful bidders Request for Payment.
9. Commonwealth of Pennsylvania, Department of Transportation Form CS-4171, Certificate of Compliance, is required for all materials. Certificates shall be supplied on a daily basis. No payment will be made without receipt of all load slips (copies accepted) and of all original compliance certificates. Copies of all certifications and load slips shall be (re)submitted with the invoice.
10. Bidder warrants that the prices in this bid are neither directly or indirectly the result of any agreement with any other bidder. Completion of the attached non-collusion affidavit is required.
11. All materials, equipment and/or supplies must conform to the regulations of the
Commonwealth of Pennsylvania Department of Transportation or any other Departments having established standards.
12. PennDOT bidding documents must be used, as provided by the Township. All appropriate blank spaces must be filled in, either typed or written in ink. Each bidder must submit a unit price from which the total extension amounts must be computed.
Altering and/or changing any part of this proposal will be sufficient reason for rejection.
13. It is the Township’s intent to award a single contract for this project. This project is
Lump Sum, any quantities provided are for information only. Low bid shall be based on the cost of the Lump Sum item or items.
14. All bids must be signed by an authorized signatory on behalf of the legal entity making the bid. Each proposal must be accompanied by a Bid Bond in favor of East Buffalo Township in a dollar amount not less than ten (10%) percent of the bid as security against the failure of the successful bidder shall so fail to enter into a contract, the bidder(s) or the principal(s) on the Bid Bond(s) shall pay to the Township the difference, not to exceed the penal amount of the bond(s) between the amount specified in the successful bidder’s bid(s) and such greater amount for which the Township may, in good faith, contract with another party to perform the work in said bid(s).
15. The Township reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. The Township reserves the right to waive informalities and irregularities in the bid submission and the unqualified right to reject any and all bids.
16. The successful bidder is required to provide surety (see item 17) and satisfactory evidence of insurance coverage (see items 18, 19, 20, and 21), as necessary depending on the scope of the bid, within twenty (20) days after notice of acceptance of bid.
Failure to do so will be sufficient reason for the Township to cancel the bid award.
Certificates of Insurance acceptable to the Township shall be filed with the Township prior to the commencement of the work. Said Certificates shall evidence that the Contractor has all the insurance coverages required under this Contract and shall contain the provision that the coverage afforded under the policies will not be cancelled until at least thirty (30) days prior written notice has been submitted to the Township and the Township has been designated as an additional insured for all insurance coverages other than Workers’ Compensation and Employers’ Liability.
17. The successful bidder will be required to furnish the following within twenty (20) days of notice of award:
A performance bond at 100% of the contract price conditioned upon faithful performance of the contract in accordance with the specifications and conditions of the contract;
A payment bond at 100% of the amount of the contract price conditioned for prompt payment of all material furnished or labor supplied or performed in completion of the work.
A maintenance/warranty bond at 10% of the amount of the contract price warrantying any defects which occur within one year of the contract completion.
Bonds shall be executed by one or more surety companies legally authorized to do business in the Commonwealth of Pennsylvania. Such bonds shall be payable to East Buffalo Township, Union County, Pennsylvania.
18. The successful bidder shall purchase and maintain during the life of this Contract such Commercial General Liability (CGL) Insurance including product and completed operations liability insurance covering all claims which may arise from the successful bidder’s performance of the work and the successful bidders other obligations under the Contract, whether such performance is by the successful bidder or by a subcontractor, by anyone directly or indirectly employed by any of them, or by anyone for whose acts any of them may be liable. Proof of insurance shall be submitted to the Township. Insurance coverage shall be statutory unless otherwise noted below.
$2,000,000 Commercial General Liability Aggregate Per Project $2,000,000 Products/Completed Operations Aggregate $1,000,000 Commercial General Liability Each Occurrence $1,000,000 Contractual Liability
Successful bidder shall also purchase and maintain during the life of the Contract, Excess Liability/Umbrella insurance coverage in the amount not less than $1,000,000.
19. The successful bidder shall purchase and maintain during the life of this Contract such
Comprehensive Automobile Liability Insurance including Employer’s Non-Ownership Liability and Hired Car Liability Insurance to protect themselves and any subcontractors performing the work covered by this Contract from claims for damages, whether such operations be by them or any subcontractor or by anyone directly or indirectly employed by either of them. Proof of insurance shall be submitted to the Township.
Insurance coverage shall be statutory unless otherwise noted below.
$1,000,000 Bodily Injury; Each Person; and $1,000,000 Bodily Injury; Each Accident; and $1,000,000 Property Damage Each Accident; or $1,000,000 Property Damage Combined Single Limit
20. The successful bidder shall purchase and maintain during the life of this Contract such standard Worker’s Compensation Insurance including employer’s liability coverage (Coverage B). Proof of insurance shall be submitted to the Township. Insurance coverage shall be statutory unless otherwise noted below.
21. The successful bidder shall purchase and maintain during the life of this Contract such Contractor’s Pollution Liability. Proof of insurance shall be submitted to the Township.
Insurance coverage shall be statutory unless otherwise noted below.
$500,000 Each Occurrence $500,000 General Aggregate
22. At the request of the Township, the Contractor shall provide documentation verifying participation in DOT approved drug and alcohol testing program for CDL drivers.
23. The bidder hereby agrees to hold harmless and fully indemnify the Township and all of its officers, employees or agents from all damages, costs or expenses that may at any time be imposed or claimed on this contract.
24. No award shall be made to any bidder who, in the opinion of the Township, is in default of any bid proposal, purchase order, or contract with the Commonwealth of Pennsylvania or political subdivision therein, or is currently debarred by Commonwealth of Pennsylvania, Department of Labor and Industry, prior to the date of the bid proposal under consideration.
25. Inspection of materials will be made by the Township or its Designated Representative.
Any article that is defective or fails in any way to meet the terms of the contract or purchase order will be rejected. The decision of the Township shall be final and the rejected material will be replaced by and at the expense of the Contractor.
26. Working hours shall be defined as 7:30 AM to 8:00 PM Monday through Saturday.
27. Bidders shall provide a list of all subcontractors associated with this project who will be working within the limits of East Buffalo Township and/or providing materials for the project. Including but not limited to the following examples:
28. Requests for substitution of specified materials shall be made in writing to the Township, along with all appropriate submittals. Substitutions shall provide equal or greater physical properties and be Commonwealth of Pennsylvania Department of Transportation, Bulletin 15, approved (see item 2).
29. Questions regarding these bidding document shall be submitted in writing via Pennbid only; verbal requests will not be accepted.
30. Since damages for delay in completion of the work are impossible for determination, the Contractor and its surety shall be liable for and shall pay the Township the sum of $500 per day as fixed and liquidated damages for each calendar day of delay from the date fixed for the completion of the work until the work is completed.
Summary of Work
The successful bidder shall furnish all labor, equipment and materials to construct the project as described in the Contract and shown on the attached drawings. The BID for the project is lump sum and the Township envisions a complete project which includes, but is not limited to, the following:
Furnish all material, labor, and equipment to install a new reinforced concrete deck and associate curb as shown on the attached US Bridge Plans.
Furnish and install bridge barrier bolt pattern, provided by Township.
Furnish and install all necessary and required erosion and sedimentation control measures to protect the environment and the Creek, including but not limited to concrete washout, silt sock, etc.
Furnish all material, labor, and equipment to install the epoxy overlay.
This is a general scope of work. Refer to the contract documents and drawings to determine the exact limits of work. Any quantities shown herein are for reference only and are the responsibility of all bidders to verify.
The abutments and superstructure of the Turtle Creek Road bridge is currently under construction by East Buffalo Township. It is the Township’s intent to have the superstructure ready for deck installation on or before, October 31, 2025. Contractor should be prepared to begin deck construction on November 1, 2025. Deck construction is anticipated to be completed prior to cold weather. The contract for the deck construction will expire on January 1, 2026, except as noted below. Liquidated damages shall not apply due to cold weather.
The deck system is intended to be constructed without the need for cool or cold weather concrete construction materials and methods. In the event that the Township causes a delay in construction which requires cold weather construction an extension will be issued to the successful bidder to allow for construction during Spring 2026.
The successful bidder may request to delay the epoxy overlay until Spring 2026; the Township will grant a time extension for the epoxy overlay until June 1, 2026, to ensure the epoxy’s bonding integrity. This may require additional cleaning/prep of the deck surface and bidders should consider this cost in their bid. Bridge closure/ traffic control will be the responsibility of the Township.
Estimated Quantities
No quantities have been estimated, except as noted.
Additional Specifications
Bidders are advised that all general items listed below shall include all necessary and required labor, equipment, and material to complete this project. Unspecified items defer to Publication 408, 72M, and the BD Standards.
Construction Engineer & Foreman (NOT IN CONTRACT; NIC)
1. The Township will provide access to the Township’s Construction Engineer and/or Foreman throughout the project.
2. Construction Engineer & Foreman will be available at the preconstruction conference to discuss the construction process, material requirements, general construction time frames, and Township expectations. Preconstruction conference will be scheduled with the Contractor prior to start of work.
3. The Construction Engineer or Foreman will be on site daily.
Construction Surveying
1. Contractor shall be responsible for any necessary construction stakeout.
2. Horizontal and vertical stakeout control points will be provided to the Contractor by the
Township, as well as elevations noted below.
Erosion & Sedimentation Control
1. The Township is responsible to install all necessary and required erosion and sedimentation control measures necessary to prevent environmental damage; however, this does not include installation of approved DEP concrete washout location(s).
Contractor shall be responsible for concrete washout.
2. Turtle Creek Road itself as well as the designated staging area on the either side of Turtle Creek Road bridge may be used as staging.
3. Contractor is responsible for any environmental damage, fishkills, and/or fines, including any portion thereof assessed to the Township, as a result of Contractor’s negligence which is part of this project.
Staging Area
1. The Township has arranged for two “Staging Areas”.
2. Contractor may utilize the Township’s staging areas on adjoining property to the either side of the Turtle Creek Road bridge. Contractors shall document and sign off on the condition of the Staging Area. Any separate agreement between the contractor and individual property owner shall be documented in writing and provided to the Township prior to the start of work. In lieu of utilizing staging area, the low bidder shall provide their own staging area.
3. Staging areas are not specifically addressed in the approved plans.
4. Staging Area shall be returned to equal or better condition, or as agreed upon with the property owner, upon completion of the project.
5. Access to neighboring properties shall not be restricted. Contractor will be responsible to document the condition of the Township’s right-of-way and adjoining properties prior to occupying site and for any damages to the roadway surface or adjoining right-of-way.
6. Maintain areas free of waste materials, debris, and rubbish.
7. The project site shall be maintained in good condition.
8. Stockpiles shall be maintained in neat and orderly condition.
9. Construction materials shall be stored in accordance with the manufacturers specifications and maintained in new and undamaged condition.
10. Equipment shall be parked and secured during non-working hours.
11. Site shall be secured during non-working hours.
12. Turtle Creek Road shall be kept in good condition, Contractor will be responsible for gauging, marking, and other damage resulting from equipment during construction, including deliveries.
13. Contractor shall sweep/broom Turtle Creek Road daily, as required.
14. Some construction materials are highly flammable. Dispose of all combustibles, debris, and garbage, daily.
Maintenance & Protection of Traffic
1. Turtle Creek Road is currently closed to “through traffic” by the Township. East Buffalo
Township shall be responsible for the continued maintenance of the existing signs. In the event that construction is delayed due to cold weather, the Township will continue to maintain or erect the MPT in Spring 2026.
2. Site access shall be maintained by the Contractor at all times. The site shall be secured during non-working hours. Fencing may be utilized, as necessary, to secure the site.
Placement of signs warning the public not to trespass or enter into the site may be posted to be visible from not only the road but both up- and down-stream. Contractor assumes the liability of public entering into the site during non-working hours.
3. No material or equipment shall be stored or staged in the Township’s rights-of-way during either working or non-working hours (outside the limits of the “Road Closure”).
The Township has provided two staging areas located adjacent to the site.
4. All adjoining residences and/or businesses shall be provided notice a minimum of forty-eight (48) hours advance notice of road closures and/or restriction (ie material delivery and placement) that further restrict access. Notice shall be given in writing and may be given through the placement of signs, door hangars, mailings, etc.
5. Materials are recommended to be delivered to the north side of the bridge adjacent to the Township’s staging area.
6. Contractors and suppliers are strongly cautioned to determine the delivery route to the site due to weight limitations of local roads and bridges, severe roadway geometry in the immediate area, and are responsible to manage the route of all delivery vehicles.
Concrete Bridge Deck System
1. Contractor shall provide all necessary equipment, labor, and materials to install the Turtle
Creek Road concrete bridge deck and associated barrier curb in accordance with the attached plans. The concrete bridge deck system shall be constructed by the Contractor.
2. PennDOT prequalification IS REQUIRED; bidders shall be prequalified for Cement Concrete Structures – Code ‘S’. CONTRACTOR MUST PROVIDE COPY OF PENNDOT PRE- QUALIFICATION as part of bid submittal.
3. The Township approves the use of an escalator clause for the cost of rebar and concrete.
Contractor shall be responsible for any price change up to and including 10%. Likewise, any reduction in price over 10% shall benefit the Township.
a. The Township will reimburse the Contractor for changes in cost for rebar between the bid date and date of award.
b. The Township will reimburse the Contractor for changes in the cost of concrete between the bid date and the cost at time of placement.
c. Contractor shall supply written and dated documentation from supplier(s), if requesting escalator, showing proof of material cost, as part of their bid. Any requests for escalator which do not submit written proof as part of the bid documents shall be denied.
4. Drawings for the concrete deck system with reinforcing steel materials and strengths has been provided by the Township and is attached to these bidding documents. Refer to the HRG plans sheet 3 for reinforcing.
5. Deck grades will be provided to the awarded contractor in no less than 10’ intervals, if requested.
6. All concrete shall be provided by the Contractor as part of this contract. All concrete shall be PennDOT Class AAA, unless otherwise specified. Use of AAA in lieu of AAAP has been approved as a substitution by the Department of Transportation.
7. All concrete shall be formed, mixed, placed, consolidated, finished and cured in accordance with PennDOT Publication 408.
8. All rebar shall be provided by the Contractor as part of this contract. All rebar shall be epoxy coated and as noted on the plans. Galvanized rebar may be substituted.
9. All rebar shall be fabricated and placed in accordance with PennDOT Publication 408.
10. Elimination of the mechanical connections for the rebar and anchor bolts, as shown on the curb detail section shown on HRG plans (see also BD standards), allowing for a single bar or bolt. Mechanical splicing may be eliminated if a bar is substituted with equivalent strength and has been approved by the Department of Transportation.
11. Contractor is responsible to provide fabricated guiderail anchor bolts, and associated hardware, as shown on HRG drawings.
12. BD-609 is attached for reference.
13. Structure mounted barrier curb shall be installed, including all necessary reinforcing, in accordance with BD-609.
14. Concrete shall not be placed until the forms and reinforcing steel have been inspected by the Township.
15. Concrete bridge deck system shall be mechanically placed and finished as a composite concrete slab, in accordance with Publication 408, Section 1001. Hand placing and finishing will not be accepted.
16. The crown of the deck shall be 3% (3/8” per ft.) cross slope, as noted on the plans.
17. The superstructure for this bridge (NIC) is currently being fabricated:
a. Steel superstructure shall be installed by the Township.
b. Shear studs are provided as part of the superstructure.
c. Structure mounted guiderail barrier and mounting plates areas provided as part of the superstructure; bridge deck contractor shall provide and install the guiderail bolt system as part of the barrier curb.
d. Township shall install the structure mounted guiderail.
e. The Stay-in-Place (SIP) corrugated metal decking forms and edge forms are provide as part of the superstructure and have a minimum depth of 2”, Type 8.5P, as supplied by L.B. Foster.
f. Deck contractor is responsible to install all SIP forms as part of the deck construction, in accordance with the plans.
g. Deck contractor may, at their discretion, tack weld the SIP angle bracket to the top flange of the beam, as approved by the Department of Transportation;
Contractor is responsible for completing galvanized field repair at no additional cost.
18. Safely secure the deck from access to vehicle traffic until the end of the 28-day cure.
19. The skid resistant finish shall be cut into the deck in accordance with Publication 408. Use of a tined finish in lieu of a micro-grooved finish on the deck surface has been approved as a substitution by the Department of Transportation.
20. An epoxy overlay shall be installed on the bridge deck in accordance with Publication 408 Section 1046.
a. The epoxy overlay shall include not only the travel lanes of the deck surface but also the horizontal surface (top) of the barrier curb and vertical surface of the (inside) barrier curb facing toward the travel lanes and perpendicular to the travel lanes, as approved by the Department of Transportation.
b. A quality control plan shall be submitted to the Township for review and approval prior to installation of the epoxy overlay.
c. The successful bidder may request to delay the epoxy overlay until Spring 2026;
the Township will grant a time extension for the epoxy overlay until June 1, 2026, to ensure the epoxy’s bonding integrity. This may require additional cleaning/prep of the deck surface and bidders should consider this cost in their bid. Bridge closure/ traffic control will be the responsibility of the Township.
21. The award will be based on the bid which is in the Township’s best interest to construct.
File details come from the government source that posted it. Updated .