Schedule of Deliverables

View the file

Other files

File Type Posted
P15_-_SOD_041212.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

U.S. Participation in the Program for International Student Assessment (PISA) 2015
(IESNE120015)
Schedule of Deliverables
TasksDeliverable no.ActivityType of taskDue DateQuantity/FormatDate Received
Task 1: Contract AdministrationFP
1.1Project initiation and planning
1.1.1Post-award meeting materialwithin 2 weeks of contract award1 electronic copy
1.1.2.1Revised master schedule for field testwithin 2 weeks of contract award1 electronic copy
1.1.2.2Revised master schedule for main studyno later than 7 months prior to contacting schools for recruiting1 electronic copy
1.1.3.1Draft project management planwithin 3 weeks of contract award1 electronic copy
1.1.3.2Final project management planWithin 3 weeks of COR comments1 electronic copy
1.1.4.1Draft staffing planwithin 3 weeks of contract award1 electronic copy
1.1.4.2Final staffing planWithin 3 weeks of COR comments1 electronic copy
1.1.5.1Draft data security planwithin 3 weeks of contract award1 electronic copy
1.1.5.2Final data security planWithin 3 weeks of COR comments1 electronic copy
1.1.6List of all personnel with signed Affidavits of Nondisclosurewithin 4 weeks of contract award; update upon any staffing changes1 electronic copy
1.1.7Test of transfer/retrieval system(s)within 4 weeks of contract award1 electronic delivery and retrieval of each deliverable format
1.1.8.1Draft informational brochurewithin 6 weeks of contract award1 electronic copy
1.1.8.2Final informational brochurewithin 3 weeks of full NCES review1 electronic copy for posting on the web; 50 color printed copies for NCES + sufficient copies for participants
1.2Contract management
1.2.1Regular project meetings materials including master scheduleProject meeting weekly, bi-weekly or monthly throughout the contract. Meeting agenda and materials are due a day before the meetingmeetings by phone, in person, or other means; materials: electronic and hard copies for face-to-face meetings
1.2.2NPM meeting trip reportswithin 3 business days after the meeting/training ends1 represetative per meeting
1.2.3Monthly study progress and financial reports1 month from the start of contract, on the 15th day of each month1 electronic copy
1.2.4Project portal for housing electronic copies of proejct materialswithin 1 month of contract award1 project portal
1.3Obtain OMB clearance for field test data collection
1.3.1Draft OMB field test clearance packageno later than August 1, 20131 electronic copy
1.3.2Revised OMB field test clearance packagewithin 5 business days of COR and NCES comments1 electronic copy
1.3.3Revised package based on RIMS commentswithin 5 business days of receipt of comments1 electronic copy
1.3.4Responses to OMB questions on packagewithin 5 business days of receipt of comments1 electronic copy
1.3.5Revised final field test clearance package for OMB approvalwithin 3 business days of final comments1 electronic copy
1.3.6OMB clearance for field testno less than 3 weeks prior to start of data collectionConfirmation of OMB clearance (OMB number assigned)
1.4Obtain OMB clearance for the main study data collection
1.4.1Draft OMB main study memo or clearance packageno less than 7 months prior to start of data collection1 electronic copy
1.4.2Revised OMB main study memo or clearance packagewithin 5 business days of COR and NCES comments1 electronic copy
1.4.3Revised memo or package based on RIMS commentswithin 5 business days of receipt of comments1 electronic copy
1.4.4Responses to OMB questions on memo or packagewithin 5 business days of receipt of comments1 electronic copy
1.4.5Revised final main study memo or clearance package for OMB approvalwithin 3 days of final comments1 electronic copy
1.4.6OMB clearance for main studyno less than 4 months prior to start of data collectionConfirmation of OMB clearance (OMB number assigned)
1.5Briefings and descriptive materials
1.5.1Project briefing materials (up to 5)within 2 weeks of COR request1 electronic copy
1.5.2Presentations on PISA project (up to 10)within 2 weeks of COR request1 electronic copy
Task 2: Study Design and InstrumentsFP
2.1Field test sampling plan and sample
2.1.1Revised U.S. sampling plan for field test9 months before the field test (June, 2013)1 electronic copy
2.1.2U.S. sampling frame, forms and required data and documentation for submission to international contractor for filed testby established international delivery due date1 electronic copy
2.1.3U.S. field test sampleupon approval of sampling plan1 electronic copy of school sample list
2.2Main study sampling plan and sample
2.2.1U.S. sampling plan for main study7 months before contacting state/district/school1 electronic copy
2.2.2U.S. sampling frame, forms and required data and documentation for submission to international contractor for main studyby established international delivery due date1 electronic copy
2.2.3U.S. main study sampleupon approval of sampling plan1 electronic copy
2.3Adapt, prepare, and produce field test instruments
2.3.1International adaptation forms submitted for International review and approvalby established international delivery due date; submit to NCES for review at least 2 weeks before submitting to international contractor1 electronic copy of each international adaptation form
2.3.2Adapted field test items/instruments and student instructions submitted for international verification;by established international delivery due date1 electronic copy of each adapted field test instrument and completed layout forms
2.3.3Final proofs of field test instruments for NCES final review and approvalwithin 1 week of receipt from the printer for paper-pencil instruments, and upon the final approval by international contractor/NCES for electronic instrumentsfor paper-based 1 electronic copy and 1 hard copy of each survey instrument; for computer-based 1 electronic version of each instrument
2.3.4Final field test instruments3 weeks before the field test data collection start datefor paper-based 1 electronic copy and 1 hard copy of each survey instrument; for computer-based 1 electronic version of each instrument
2.4Adapt, prepare, and produce main study instruments
2.4.1International adaptation forms submitted for International review and approvalby established international delivery due date; submit to NCES for review at least 2 weeks before submitting to international contractor1 electronic copy of each international adaptation form
2.4.2Adapted main study items/instruments and student instructions submitted for international verification;by established international delivery due date1 electronic copy of each adapted main assessment instrument and completed layout forms
2.4.3Final proofs of main study instruments for NCES final review and approval for distributionwithin 1 week of receipt from the printer for paper-pencil instruments, and upon the final approval by international contractor/NCES for electronic instrumentsfor paper-based 1 electronic copy and 1 hard copy of each survey instrument; for computer-based 1 electronic version of each instrument
2.4.4Final main study instruments1 month before the main study data collection start datefor paper-based 1 electronic copy and 1 hard copy of each survey instrument; for computer-based 1 electronic version of each instrument
Task 3: Data CollectionCR
3.1Recruit Schools and Students for Field Test
3.1.1Draft U.S. school and student recruitment plan for field test3 months after contract start date1 electronic copy
3.1.2Final U.S. school and student recruitment plan for field testwithin 2 weeks of comments submitted on draft1 electronic copy
3.1.3Draft U.S. national recruiting materialssubmitted at same time as draft OMB field test package (task 1.3)1 electronic copy
3.1.4Draft field test parent permission letterssubmitted at same time as draft OMB field test package (task 1.3)1 electronic copy
3.1.5Draft field test recruitment information packetssubmitted at same time as draft OMB field test package (task 1.3)1 electronic copy
3.1.6Final U.S. national recruiting materialswithin 1 month of receipt of NCES and OMB approvals1 electronic copy; 50 printed copies
3.1.7Final field test parent permission letterswithin 1 month of receipt of NCES and OMB approvals1 electronic copy
3.1.8Final field test recruitment information packetswithin 1 month of receipt of NCES and OMB approvals1 electronic copy
3.1.9Weekly recruitment status report for field test1 week after start of recruitment effort, and every Monday thereafter until recruitment is completed1 electronic copy of each weekly progress report
3.2Recruit Schools and Students for Main Assessment
3.2.1Draft U.S. school and student recruitment plan for main assessmentwithin 1 month after field test recruitment ends1 electronic copy
3.2.2PISA main study on sampled states' state assessment calendarsby end of school year preceding main study data collectionemail confirmation
3.2.3Final U.S. school and student main assessment plan for recruitment and improving response rateswithin 2 weeks after receipt of comments on deliverable 3.2.11 electronic copy
3.2.4Revise U.S. national recruiting materials for main assessmentsubmitted with draft OMB main study clearance package (task 1.4)1 electronic copy
3.2.5Draft main assessment parent permission letterssubmitted with draft OMB main study clearance package (task 1.4)1 electronic copy
3.2.6Draft main assessment recruitment information packetssubmitted with draft OMB main study clearance package (task 1.4)1 electronic copy
3.2.7Final U.S. national recruiting materials for main assessmentwithin 1 month of receipt of NCES and OMB approvals1 electronic copy
3.2.8Final main assessment parent permission letterswithin 1 month of receipt of NCES and OMB approvals1 electronic copy
3.2.9Final main assessment recruitment information packetswithin 1 month of receipt of NCES and OMB approvals1 electronic copy; 1 hard copy of the final recruitment package
3.2.10Weekly recruitment status report for main assessment1 week after start of recruitment effort, and every Monday thereafter until recruitment is completed1 electronic copy of each weekly progress report
3.3Recruit and Train Data Collectors for Field Test
3.3.1Draft plan for field test data collector recruitment and trainingat least 3 months prior to start of recruitment and training program1 electronic copy
3.3.2Final plan for field test data collector recruitment and trainingwithin 3 weeks of COR comments1 electronic copy
3.3.3Draft field test data collector training materialsat least 4 weeks prior to training1 electronic copy
3.3.4Final field test data collector training materialsat least 5 business days before training begins1 electronic copy
3.4Recruit and Train Data Collectors for Main Study
3.4.1Draft plan for main study data collector recruitment and trainingat least 3 months prior to start of recruitment and training program1 electronic copy
3.4.2Final plan for main study data collector recruitment and trainingwithin 3 weeks of COR comments1 electronic copy
3.4.3Draft main study data collector training materialsat least 4 weeks prior to training1 electronic copy
3.4.4Final main study data collector training materialsat least 5 business days before training begins1 electronic copy
3.5Collect Data for Field Test
3.5.1Approved field test data collection manuals1 month before field test data collector training1 electronic copy
3.5.2Draft field test data collection/quality assurance plan3 months prior to start of field test data collection1 electronic copy
3.5.3Final field test data collection/quality assurance plan2 weeks after receipt of comments on deliverable 3.5.21 electronic copy
3.5.4Weekly data collection status reportby COB Monday during data collection1 electronic copy of each weekly progress report
3.5.5Draft field test data collection summary with recommendations for main studywithin 1 month of completion of field trial1 electronic copy
3.5.6Final field test data collection summary with recommendations for main studywithin 2 weeks after COR's comments1 electronic copy
3.6Collect Data for Main Assessment
3.6.1Approved main study data collection manuals1 month before main study data collector training
3.6.2Draft main study data collection/quality assurance plan3 months prior to start of main assessment data collection1 electronic copy
3.6.3Final main study data collection/quality assurance plan2 weeks after receipt of comments on deliverable 3.6.21 electronic copy
3.6.4Recommend quality monitors to international contractorby established international timeline1 electronic copy
3.6.5Weekly data collection status reportafter first week of data collection, and every Monday until end of data collection1 electronic copy
3.7Final report on data collection for improvement on main study
3.7.1Draft plan for field test data entry per OECD specifications2 months prior to create dataset1 electronic copy
3.7.2Final plan for field test data entry per OECD specificationswithin 2 weeks of receipt of comments on deliverable 3.7.11 electronic copy
3.7.3Produce and deliver field test datasetbased on the deadline of international contractor1 electronic copy
3.8Produce main assessment dataset
3.8.1Draft plan for main assessment data entry per international contractor's specifications2 months prior to create dataset1 electronic copy
3.8.2Final plan for main study data entrywithin 2 weeks of receipt of comments on deliverable 3.8.11 electronic copy
3.8.3Draft Disclosure Analysis Plan (DAP);3 months prior to submit data to international contractor1 electronic copy
3.8.4Final disclosure analysis planwithin 1 week after receiving comments1 electronic copy
3.8.5Draft data matching and swapping reportwithin 1 week after the approval of DAP1 electronic copy
3.8.6Final data matching and swapping reportwithin 1 week after receiving comments1 electronic copy
3.8.7Main study datasetafter the approval by DAP and based on the negotiated deadline with the international contractor1 electronic copy
3.9Score field test assessment and code questionnaire data
3.9.1Draft plan for field test scoring and coding recruitment, and for scoring/training programat least 2 months prior to anticipated start of data coding/scoring1 electronic copy
3.9.2Final plan for field test scoring and coding recruitment, and for scoring/training programwithin 1 week of receipt of comments on deliverable 3.9.11 electronic copy
3.9.3Field test scoring/coding training materialswithin 5 working dates prior to distributing to trainees1 electronic copy
3.9.4End of training report on inter-rater reliability for field testat the end of scoring training1 electronic copy
3.9.5Mid-point inter-rater reliability for field testat the mid-point of scoring activities1 electronic copy
3.9.6End-point inter-rater reliability for field testat the end of scoring activities1 electronic copy
3.9.7Report on scoring/coding training and plan for improvements during main assessment1 month after completion of scoring1 electronic copy
3.10Score main study assessment and code questionnaire data
3.10.1Draft plan for main study scoring and coding recruitment, and for scoring/training programat least 2 months prior to anticipated start of data coding/scoring1 electronic copy
3.10.2Final plan for main study scoring and coding recruitment, and for scoring/training programwithin 1 week of receipt of comments on deliverable 3.10.11 electronic copy
3.10.3Main assessment scoring/coding training materialswithin 5 working dates prior to distributing to trainees1 electronic copy
3.10.4End of training report on inter-rater reliability for main assessmentat the end of scoring training1 electronic copy
3.10.5Mid-point inter-rater reliability for main assessmentat the mid-point of scoring activities1 electronic copy
3.10.6End-point inter-rater reliability for main assessmentat the end of scoring activities1 electronic copy
3.10.7Report on scoring/coding training and suggestions for improvement for next administration1 month after completion of scoring1 electronic copy
Task 4: Prepare and Disseminate ResultsFP
4.1Prepare technical reports
4.1.1.1Draft field test item review memono later than 3 weeks prior to NPM meeting on Field test results1 electronic copy
4.1.1.2Final field test item review memo1 week after comments on deliverable 4.1.1.11 electronic copy
4.1.2.1Outline for survey operations/technical reportwithin 6 weeks after submitting main study dataset to international contractor1 electronic copy
4.1.2.2Draft survey operation/technical reportwithin 4 months prior to release of national and international reports1 electronic copy
4.1.2.3Final survey operations/technical reportwithin 2 months of the release of the national and international reports1 electronic copy
4.1.3.1Outline for non-response bias analysis1 month prior to main study data collection1 electronic copy
4.1.3.2Preliminary non-response bias analysis reportwithin 2 months of completion of data collection (submitted along with data to international contractor)1 electronic copy
4.1.3.3Draft non-response bias analysis report10 months prior to release of national report1 electronic copy
4.1.3.4Final Non-response bias analysis report6 months prior to release of national report1 electronic copy
4.2Develop and Produce PISA U.S. national report
4.2.1.1Draft national report analysis planno later than 18 months prior to release of national report1 electronic copy
4.2.1.2Final national report analysis planwithin 2 weeks after comments from COR1 electronic copy
4.2.1.3Draft table/figure shells and technical appendix10 months prior to release of national report; revised versions due within 2 weeks after comments from COR1 electronic copy
4.2.1.4Draft analyses to populate table/figure shells6 months prior to international data release1 electronic copy
4.2.2.1Draft national report and factbook (Word/ Excel version)5 months prior to release of national report1 electronic copy
4.2.2.2Final national report and factbook (Word/Excel version)at least 7 working days prior to scheduled release date1 electronic copy
4.2.2.3Final national report (PDF version)at least 7 working days prior to scheduled release date1 electronic copy
4.2.2.4Final national report (HTML version)at least 7 working days prior to scheduled release date1 electronic copy
4.2.2.5Final national report (eBook version)at least 7 working days prior to scheduled release date1 electronic copy
4.2.2.6Final national report (GPO printing files of package)within 2 weeks after release of national report1 electronic copy and 1 hard copy for GPO duplication
4.2.2.7Color, hard copies of report (up to 50), and 1 electronic and hard-bound copy of factbookat least 7 working days prior to scheduled release date1 electronic copy and 50 colored hard copies
4.3PISA school-level reports
4.3.1Draft school report plan with prototypesat least 2 years before expected date of release of PISA 2015 data1 electronic copy
4.3.2Final school report plan with prototypeswithin 2 weeks of receiving comments from NCES1 electronic copy
4.3.3Preliminary results web tool and reports for eligible PISA schoolswithin 1 month of availability of required data from international contractorwebsite access to get the school report
4.3.4Final results web tool and reports for eligible PISA schoolson or within 1 month of national or international report releasewebsite access to get the school report
4.4Produce main study electronic public-use datafiles and user's guide
4.4.1Draft public-use datafilewithin 2 months after release of national report1 electronic copy
4.4.2Final public-use datafile;within 7 months after the release of national report1 electronic copy
4.4.3Draft restricted-use datafilewithin 2 months after release of national report1 electronic copy
4.4.4Final public-use datafilewithin 7 months after the release of national report1 electronic copy
4.4.5Draft user's guide for public-use datafilewithin 2 months after release of national report1 electronic copy
4.4.6Final user's guide for public-use datafilewithin 7 months after the release of national report1 electronic copy
4.4.7Draft user's guide for restricted-use datafilewithin 2 months after release of national report1 electronic copy
4.4.8Final user's guide for restricted-use datafilewithin 7 months after the release of national report1 electronic copy
Task 5: Use Expert HelpCR
5.1Scope of work for expert(s)at least 2 weeks and up to 3 months prior to the activity/event1 electronic copy
5.2Materials to support activityat least 3 weeks prior to the activity/event1 electronic copy, and hard copies as needed
5.3Summary report of activitywithin 2 weeks of the expert panel meeting or the conclusion of the task/activity1 electronic copy
Task 6: PISA Validation Study (TBD)CR
OptionsTBD
Task 7 (Optional): Manage subnational participation in PISACR
7.1Memorandum detailing state participation planswithin 3 weeks of COR request1 electronic copy
7.2Draft brochurewithin 2 weeks of COR request1 electronic copy
7.3Final brochurewithin 2 weeks of COR comments1 electronic copy
Task 8 (Optional): Conference for PISA 2015 SchoolsCR
8.1Conference agenda6 months prior to the conference1 electronic copy
8.2Conference materials6 weeks prior to the conference1 electronic copy
8.3Conference summary reportwithin 2 weeks after the conference1 electronic copy
Task 9 (Optional): Additional Subject-Matter AssessmentsCR
9.1Memorandum with plans for integrating additional subject matter assessments into data collectionwithin 3 weeks of COR request1 electronic copy
Task 10 (Optional): Disseminate ResultsFP
10.1Draft plan for dissemination of study results4 months prior to national report release1 electronic copy
10.2Final plan for dissemination of study resultswithin 2 weeks after comments received on deliverable1 electronic copy
10.3Prepare and deliver national report release materialsat least 5 days prior to national report release1 electronic copy, and hard copies
10.4Press briefingday of national report release1 electronic copy, and hard copies
10.5Study release announcementsno later than 5 days prior to national release date1 electronic copy
Task 11 (Optional): Item DevelopmentFP
11.1Draft items for review by CORat least 3 weeks prior to international deadline for submission1 electronic copy
11.2Final items for submission to international contractorin accordance with international schedule1 electronic copy