Sheet1
| U.S. Participation in the Program for International Student Assessment (PISA) 2015 |
| (IESNE120015) |
| Schedule of Deliverables | ||||||
| Tasks | Deliverable no. | Activity | Type of task | Due Date | Quantity/Format | Date Received |
| Task 1: Contract Administration | FP | ||||
| 1.1 | Project initiation and planning | ||||
| 1.1.1 | Post-award meeting material | within 2 weeks of contract award | 1 electronic copy | ||
| 1.1.2.1 | Revised master schedule for field test | within 2 weeks of contract award | 1 electronic copy | ||
| 1.1.2.2 | Revised master schedule for main study | no later than 7 months prior to contacting schools for recruiting | 1 electronic copy | ||
| 1.1.3.1 | Draft project management plan | within 3 weeks of contract award | 1 electronic copy | ||
| 1.1.3.2 | Final project management plan | Within 3 weeks of COR comments | 1 electronic copy | ||
| 1.1.4.1 | Draft staffing plan | within 3 weeks of contract award | 1 electronic copy | ||
| 1.1.4.2 | Final staffing plan | Within 3 weeks of COR comments | 1 electronic copy | ||
| 1.1.5.1 | Draft data security plan | within 3 weeks of contract award | 1 electronic copy | ||
| 1.1.5.2 | Final data security plan | Within 3 weeks of COR comments | 1 electronic copy | ||
| 1.1.6 | List of all personnel with signed Affidavits of Nondisclosure | within 4 weeks of contract award; update upon any staffing changes | 1 electronic copy | ||
| 1.1.7 | Test of transfer/retrieval system(s) | within 4 weeks of contract award | 1 electronic delivery and retrieval of each deliverable format | ||
| 1.1.8.1 | Draft informational brochure | within 6 weeks of contract award | 1 electronic copy | ||
| 1.1.8.2 | Final informational brochure | within 3 weeks of full NCES review | 1 electronic copy for posting on the web; 50 color printed copies for NCES + sufficient copies for participants | ||
| 1.2 | Contract management | ||||
| 1.2.1 | Regular project meetings materials including master schedule | Project meeting weekly, bi-weekly or monthly throughout the contract. Meeting agenda and materials are due a day before the meeting | meetings by phone, in person, or other means; materials: electronic and hard copies for face-to-face meetings | ||
| 1.2.2 | NPM meeting trip reports | within 3 business days after the meeting/training ends | 1 represetative per meeting | ||
| 1.2.3 | Monthly study progress and financial reports | 1 month from the start of contract, on the 15th day of each month | 1 electronic copy | ||
| 1.2.4 | Project portal for housing electronic copies of proejct materials | within 1 month of contract award | 1 project portal | ||
| 1.3 | Obtain OMB clearance for field test data collection | ||||
| 1.3.1 | Draft OMB field test clearance package | no later than August 1, 2013 | 1 electronic copy | ||
| 1.3.2 | Revised OMB field test clearance package | within 5 business days of COR and NCES comments | 1 electronic copy | ||
| 1.3.3 | Revised package based on RIMS comments | within 5 business days of receipt of comments | 1 electronic copy | ||
| 1.3.4 | Responses to OMB questions on package | within 5 business days of receipt of comments | 1 electronic copy | ||
| 1.3.5 | Revised final field test clearance package for OMB approval | within 3 business days of final comments | 1 electronic copy | ||
| 1.3.6 | OMB clearance for field test | no less than 3 weeks prior to start of data collection | Confirmation of OMB clearance (OMB number assigned) | ||
| 1.4 | Obtain OMB clearance for the main study data collection | ||||
| 1.4.1 | Draft OMB main study memo or clearance package | no less than 7 months prior to start of data collection | 1 electronic copy | ||
| 1.4.2 | Revised OMB main study memo or clearance package | within 5 business days of COR and NCES comments | 1 electronic copy | ||
| 1.4.3 | Revised memo or package based on RIMS comments | within 5 business days of receipt of comments | 1 electronic copy | ||
| 1.4.4 | Responses to OMB questions on memo or package | within 5 business days of receipt of comments | 1 electronic copy | ||
| 1.4.5 | Revised final main study memo or clearance package for OMB approval | within 3 days of final comments | 1 electronic copy | ||
| 1.4.6 | OMB clearance for main study | no less than 4 months prior to start of data collection | Confirmation of OMB clearance (OMB number assigned) | ||
| 1.5 | Briefings and descriptive materials | ||||
| 1.5.1 | Project briefing materials (up to 5) | within 2 weeks of COR request | 1 electronic copy | ||
| 1.5.2 | Presentations on PISA project (up to 10) | within 2 weeks of COR request | 1 electronic copy |
| Task 2: Study Design and Instruments | FP | ||||
| 2.1 | Field test sampling plan and sample | ||||
| 2.1.1 | Revised U.S. sampling plan for field test | 9 months before the field test (June, 2013) | 1 electronic copy | ||
| 2.1.2 | U.S. sampling frame, forms and required data and documentation for submission to international contractor for filed test | by established international delivery due date | 1 electronic copy | ||
| 2.1.3 | U.S. field test sample | upon approval of sampling plan | 1 electronic copy of school sample list | ||
| 2.2 | Main study sampling plan and sample | ||||
| 2.2.1 | U.S. sampling plan for main study | 7 months before contacting state/district/school | 1 electronic copy | ||
| 2.2.2 | U.S. sampling frame, forms and required data and documentation for submission to international contractor for main study | by established international delivery due date | 1 electronic copy | ||
| 2.2.3 | U.S. main study sample | upon approval of sampling plan | 1 electronic copy | ||
| 2.3 | Adapt, prepare, and produce field test instruments | ||||
| 2.3.1 | International adaptation forms submitted for International review and approval | by established international delivery due date; submit to NCES for review at least 2 weeks before submitting to international contractor | 1 electronic copy of each international adaptation form | ||
| 2.3.2 | Adapted field test items/instruments and student instructions submitted for international verification; | by established international delivery due date | 1 electronic copy of each adapted field test instrument and completed layout forms | ||
| 2.3.3 | Final proofs of field test instruments for NCES final review and approval | within 1 week of receipt from the printer for paper-pencil instruments, and upon the final approval by international contractor/NCES for electronic instruments | for paper-based 1 electronic copy and 1 hard copy of each survey instrument; for computer-based 1 electronic version of each instrument | ||
| 2.3.4 | Final field test instruments | 3 weeks before the field test data collection start date | for paper-based 1 electronic copy and 1 hard copy of each survey instrument; for computer-based 1 electronic version of each instrument | ||
| 2.4 | Adapt, prepare, and produce main study instruments | ||||
| 2.4.1 | International adaptation forms submitted for International review and approval | by established international delivery due date; submit to NCES for review at least 2 weeks before submitting to international contractor | 1 electronic copy of each international adaptation form | ||
| 2.4.2 | Adapted main study items/instruments and student instructions submitted for international verification; | by established international delivery due date | 1 electronic copy of each adapted main assessment instrument and completed layout forms | ||
| 2.4.3 | Final proofs of main study instruments for NCES final review and approval for distribution | within 1 week of receipt from the printer for paper-pencil instruments, and upon the final approval by international contractor/NCES for electronic instruments | for paper-based 1 electronic copy and 1 hard copy of each survey instrument; for computer-based 1 electronic version of each instrument | ||
| 2.4.4 | Final main study instruments | 1 month before the main study data collection start date | for paper-based 1 electronic copy and 1 hard copy of each survey instrument; for computer-based 1 electronic version of each instrument |
| Task 3: Data Collection | CR | ||||
| 3.1 | Recruit Schools and Students for Field Test | ||||
| 3.1.1 | Draft U.S. school and student recruitment plan for field test | 3 months after contract start date | 1 electronic copy | ||
| 3.1.2 | Final U.S. school and student recruitment plan for field test | within 2 weeks of comments submitted on draft | 1 electronic copy | ||
| 3.1.3 | Draft U.S. national recruiting materials | submitted at same time as draft OMB field test package (task 1.3) | 1 electronic copy | ||
| 3.1.4 | Draft field test parent permission letters | submitted at same time as draft OMB field test package (task 1.3) | 1 electronic copy | ||
| 3.1.5 | Draft field test recruitment information packets | submitted at same time as draft OMB field test package (task 1.3) | 1 electronic copy | ||
| 3.1.6 | Final U.S. national recruiting materials | within 1 month of receipt of NCES and OMB approvals | 1 electronic copy; 50 printed copies | ||
| 3.1.7 | Final field test parent permission letters | within 1 month of receipt of NCES and OMB approvals | 1 electronic copy | ||
| 3.1.8 | Final field test recruitment information packets | within 1 month of receipt of NCES and OMB approvals | 1 electronic copy | ||
| 3.1.9 | Weekly recruitment status report for field test | 1 week after start of recruitment effort, and every Monday thereafter until recruitment is completed | 1 electronic copy of each weekly progress report | ||
| 3.2 | Recruit Schools and Students for Main Assessment | ||||
| 3.2.1 | Draft U.S. school and student recruitment plan for main assessment | within 1 month after field test recruitment ends | 1 electronic copy | ||
| 3.2.2 | PISA main study on sampled states' state assessment calendars | by end of school year preceding main study data collection | email confirmation | ||
| 3.2.3 | Final U.S. school and student main assessment plan for recruitment and improving response rates | within 2 weeks after receipt of comments on deliverable 3.2.1 | 1 electronic copy | ||
| 3.2.4 | Revise U.S. national recruiting materials for main assessment | submitted with draft OMB main study clearance package (task 1.4) | 1 electronic copy | ||
| 3.2.5 | Draft main assessment parent permission letters | submitted with draft OMB main study clearance package (task 1.4) | 1 electronic copy | ||
| 3.2.6 | Draft main assessment recruitment information packets | submitted with draft OMB main study clearance package (task 1.4) | 1 electronic copy | ||
| 3.2.7 | Final U.S. national recruiting materials for main assessment | within 1 month of receipt of NCES and OMB approvals | 1 electronic copy | ||
| 3.2.8 | Final main assessment parent permission letters | within 1 month of receipt of NCES and OMB approvals | 1 electronic copy | ||
| 3.2.9 | Final main assessment recruitment information packets | within 1 month of receipt of NCES and OMB approvals | 1 electronic copy; 1 hard copy of the final recruitment package | ||
| 3.2.10 | Weekly recruitment status report for main assessment | 1 week after start of recruitment effort, and every Monday thereafter until recruitment is completed | 1 electronic copy of each weekly progress report | ||
| 3.3 | Recruit and Train Data Collectors for Field Test | ||||
| 3.3.1 | Draft plan for field test data collector recruitment and training | at least 3 months prior to start of recruitment and training program | 1 electronic copy | ||
| 3.3.2 | Final plan for field test data collector recruitment and training | within 3 weeks of COR comments | 1 electronic copy | ||
| 3.3.3 | Draft field test data collector training materials | at least 4 weeks prior to training | 1 electronic copy | ||
| 3.3.4 | Final field test data collector training materials | at least 5 business days before training begins | 1 electronic copy | ||
| 3.4 | Recruit and Train Data Collectors for Main Study | ||||
| 3.4.1 | Draft plan for main study data collector recruitment and training | at least 3 months prior to start of recruitment and training program | 1 electronic copy | ||
| 3.4.2 | Final plan for main study data collector recruitment and training | within 3 weeks of COR comments | 1 electronic copy | ||
| 3.4.3 | Draft main study data collector training materials | at least 4 weeks prior to training | 1 electronic copy | ||
| 3.4.4 | Final main study data collector training materials | at least 5 business days before training begins | 1 electronic copy | ||
| 3.5 | Collect Data for Field Test | ||||
| 3.5.1 | Approved field test data collection manuals | 1 month before field test data collector training | 1 electronic copy | ||
| 3.5.2 | Draft field test data collection/quality assurance plan | 3 months prior to start of field test data collection | 1 electronic copy | ||
| 3.5.3 | Final field test data collection/quality assurance plan | 2 weeks after receipt of comments on deliverable 3.5.2 | 1 electronic copy | ||
| 3.5.4 | Weekly data collection status report | by COB Monday during data collection | 1 electronic copy of each weekly progress report | ||
| 3.5.5 | Draft field test data collection summary with recommendations for main study | within 1 month of completion of field trial | 1 electronic copy | ||
| 3.5.6 | Final field test data collection summary with recommendations for main study | within 2 weeks after COR's comments | 1 electronic copy | ||
| 3.6 | Collect Data for Main Assessment | ||||
| 3.6.1 | Approved main study data collection manuals | 1 month before main study data collector training | |||
| 3.6.2 | Draft main study data collection/quality assurance plan | 3 months prior to start of main assessment data collection | 1 electronic copy | ||
| 3.6.3 | Final main study data collection/quality assurance plan | 2 weeks after receipt of comments on deliverable 3.6.2 | 1 electronic copy | ||
| 3.6.4 | Recommend quality monitors to international contractor | by established international timeline | 1 electronic copy | ||
| 3.6.5 | Weekly data collection status report | after first week of data collection, and every Monday until end of data collection | 1 electronic copy | ||
| 3.7 | Final report on data collection for improvement on main study | ||||
| 3.7.1 | Draft plan for field test data entry per OECD specifications | 2 months prior to create dataset | 1 electronic copy | ||
| 3.7.2 | Final plan for field test data entry per OECD specifications | within 2 weeks of receipt of comments on deliverable 3.7.1 | 1 electronic copy | ||
| 3.7.3 | Produce and deliver field test dataset | based on the deadline of international contractor | 1 electronic copy | ||
| 3.8 | Produce main assessment dataset | ||||
| 3.8.1 | Draft plan for main assessment data entry per international contractor's specifications | 2 months prior to create dataset | 1 electronic copy | ||
| 3.8.2 | Final plan for main study data entry | within 2 weeks of receipt of comments on deliverable 3.8.1 | 1 electronic copy | ||
| 3.8.3 | Draft Disclosure Analysis Plan (DAP); | 3 months prior to submit data to international contractor | 1 electronic copy | ||
| 3.8.4 | Final disclosure analysis plan | within 1 week after receiving comments | 1 electronic copy | ||
| 3.8.5 | Draft data matching and swapping report | within 1 week after the approval of DAP | 1 electronic copy | ||
| 3.8.6 | Final data matching and swapping report | within 1 week after receiving comments | 1 electronic copy | ||
| 3.8.7 | Main study dataset | after the approval by DAP and based on the negotiated deadline with the international contractor | 1 electronic copy | ||
| 3.9 | Score field test assessment and code questionnaire data | ||||
| 3.9.1 | Draft plan for field test scoring and coding recruitment, and for scoring/training program | at least 2 months prior to anticipated start of data coding/scoring | 1 electronic copy | ||
| 3.9.2 | Final plan for field test scoring and coding recruitment, and for scoring/training program | within 1 week of receipt of comments on deliverable 3.9.1 | 1 electronic copy | ||
| 3.9.3 | Field test scoring/coding training materials | within 5 working dates prior to distributing to trainees | 1 electronic copy | ||
| 3.9.4 | End of training report on inter-rater reliability for field test | at the end of scoring training | 1 electronic copy | ||
| 3.9.5 | Mid-point inter-rater reliability for field test | at the mid-point of scoring activities | 1 electronic copy | ||
| 3.9.6 | End-point inter-rater reliability for field test | at the end of scoring activities | 1 electronic copy | ||
| 3.9.7 | Report on scoring/coding training and plan for improvements during main assessment | 1 month after completion of scoring | 1 electronic copy | ||
| 3.10 | Score main study assessment and code questionnaire data | ||||
| 3.10.1 | Draft plan for main study scoring and coding recruitment, and for scoring/training program | at least 2 months prior to anticipated start of data coding/scoring | 1 electronic copy | ||
| 3.10.2 | Final plan for main study scoring and coding recruitment, and for scoring/training program | within 1 week of receipt of comments on deliverable 3.10.1 | 1 electronic copy | ||
| 3.10.3 | Main assessment scoring/coding training materials | within 5 working dates prior to distributing to trainees | 1 electronic copy | ||
| 3.10.4 | End of training report on inter-rater reliability for main assessment | at the end of scoring training | 1 electronic copy | ||
| 3.10.5 | Mid-point inter-rater reliability for main assessment | at the mid-point of scoring activities | 1 electronic copy | ||
| 3.10.6 | End-point inter-rater reliability for main assessment | at the end of scoring activities | 1 electronic copy | ||
| 3.10.7 | Report on scoring/coding training and suggestions for improvement for next administration | 1 month after completion of scoring | 1 electronic copy |
| Task 4: Prepare and Disseminate Results | FP | ||||
| 4.1 | Prepare technical reports | ||||
| 4.1.1.1 | Draft field test item review memo | no later than 3 weeks prior to NPM meeting on Field test results | 1 electronic copy | ||
| 4.1.1.2 | Final field test item review memo | 1 week after comments on deliverable 4.1.1.1 | 1 electronic copy | ||
| 4.1.2.1 | Outline for survey operations/technical report | within 6 weeks after submitting main study dataset to international contractor | 1 electronic copy | ||
| 4.1.2.2 | Draft survey operation/technical report | within 4 months prior to release of national and international reports | 1 electronic copy | ||
| 4.1.2.3 | Final survey operations/technical report | within 2 months of the release of the national and international reports | 1 electronic copy | ||
| 4.1.3.1 | Outline for non-response bias analysis | 1 month prior to main study data collection | 1 electronic copy | ||
| 4.1.3.2 | Preliminary non-response bias analysis report | within 2 months of completion of data collection (submitted along with data to international contractor) | 1 electronic copy | ||
| 4.1.3.3 | Draft non-response bias analysis report | 10 months prior to release of national report | 1 electronic copy | ||
| 4.1.3.4 | Final Non-response bias analysis report | 6 months prior to release of national report | 1 electronic copy | ||
| 4.2 | Develop and Produce PISA U.S. national report |
| 4.2.1.1 | Draft national report analysis plan | no later than 18 months prior to release of national report | 1 electronic copy | |
| 4.2.1.2 | Final national report analysis plan | within 2 weeks after comments from COR | 1 electronic copy | |
| 4.2.1.3 | Draft table/figure shells and technical appendix | 10 months prior to release of national report; revised versions due within 2 weeks after comments from COR | 1 electronic copy | |
| 4.2.1.4 | Draft analyses to populate table/figure shells | 6 months prior to international data release | 1 electronic copy | |
| 4.2.2.1 | Draft national report and factbook (Word/ Excel version) | 5 months prior to release of national report | 1 electronic copy | |
| 4.2.2.2 | Final national report and factbook (Word/Excel version) | at least 7 working days prior to scheduled release date | 1 electronic copy | |
| 4.2.2.3 | Final national report (PDF version) | at least 7 working days prior to scheduled release date | 1 electronic copy | |
| 4.2.2.4 | Final national report (HTML version) | at least 7 working days prior to scheduled release date | 1 electronic copy | |
| 4.2.2.5 | Final national report (eBook version) | at least 7 working days prior to scheduled release date | 1 electronic copy | |
| 4.2.2.6 | Final national report (GPO printing files of package) | within 2 weeks after release of national report | 1 electronic copy and 1 hard copy for GPO duplication | |
| 4.2.2.7 | Color, hard copies of report (up to 50), and 1 electronic and hard-bound copy of factbook | at least 7 working days prior to scheduled release date | 1 electronic copy and 50 colored hard copies | |
| 4.3 | PISA school-level reports | |||
| 4.3.1 | Draft school report plan with prototypes | at least 2 years before expected date of release of PISA 2015 data | 1 electronic copy | |
| 4.3.2 | Final school report plan with prototypes | within 2 weeks of receiving comments from NCES | 1 electronic copy | |
| 4.3.3 | Preliminary results web tool and reports for eligible PISA schools | within 1 month of availability of required data from international contractor | website access to get the school report | |
| 4.3.4 | Final results web tool and reports for eligible PISA schools | on or within 1 month of national or international report release | website access to get the school report | |
| 4.4 | Produce main study electronic public-use datafiles and user's guide | |||
| 4.4.1 | Draft public-use datafile | within 2 months after release of national report | 1 electronic copy | |
| 4.4.2 | Final public-use datafile; | within 7 months after the release of national report | 1 electronic copy | |
| 4.4.3 | Draft restricted-use datafile | within 2 months after release of national report | 1 electronic copy | |
| 4.4.4 | Final public-use datafile | within 7 months after the release of national report | 1 electronic copy | |
| 4.4.5 | Draft user's guide for public-use datafile | within 2 months after release of national report | 1 electronic copy | |
| 4.4.6 | Final user's guide for public-use datafile | within 7 months after the release of national report | 1 electronic copy | |
| 4.4.7 | Draft user's guide for restricted-use datafile | within 2 months after release of national report | 1 electronic copy | |
| 4.4.8 | Final user's guide for restricted-use datafile | within 7 months after the release of national report | 1 electronic copy |
| Task 5: Use Expert Help | CR | ||||
| 5.1 | Scope of work for expert(s) | at least 2 weeks and up to 3 months prior to the activity/event | 1 electronic copy | ||
| 5.2 | Materials to support activity | at least 3 weeks prior to the activity/event | 1 electronic copy, and hard copies as needed | ||
| 5.3 | Summary report of activity | within 2 weeks of the expert panel meeting or the conclusion of the task/activity | 1 electronic copy | ||
| Task 6: PISA Validation Study (TBD) | CR | ||||
| Options | TBD |
| Task 7 (Optional): Manage subnational participation in PISA | CR | ||||
| 7.1 | Memorandum detailing state participation plans | within 3 weeks of COR request | 1 electronic copy | ||
| 7.2 | Draft brochure | within 2 weeks of COR request | 1 electronic copy | ||
| 7.3 | Final brochure | within 2 weeks of COR comments | 1 electronic copy | ||
| Task 8 (Optional): Conference for PISA 2015 Schools | CR | ||||
| 8.1 | Conference agenda | 6 months prior to the conference | 1 electronic copy | ||
| 8.2 | Conference materials | 6 weeks prior to the conference | 1 electronic copy | ||
| 8.3 | Conference summary report | within 2 weeks after the conference | 1 electronic copy |
| Task 9 (Optional): Additional Subject-Matter Assessments | CR | ||||
| 9.1 | Memorandum with plans for integrating additional subject matter assessments into data collection | within 3 weeks of COR request | 1 electronic copy |
| Task 10 (Optional): Disseminate Results | FP | ||||
| 10.1 | Draft plan for dissemination of study results | 4 months prior to national report release | 1 electronic copy | ||
| 10.2 | Final plan for dissemination of study results | within 2 weeks after comments received on deliverable | 1 electronic copy | ||
| 10.3 | Prepare and deliver national report release materials | at least 5 days prior to national report release | 1 electronic copy, and hard copies | ||
| 10.4 | Press briefing | day of national report release | 1 electronic copy, and hard copies | ||
| 10.5 | Study release announcements | no later than 5 days prior to national release date | 1 electronic copy | ||
| Task 11 (Optional): Item Development | FP | ||||
| 11.1 | Draft items for review by COR | at least 3 weeks prior to international deadline for submission | 1 electronic copy | ||
| 11.2 | Final items for submission to international contractor | in accordance with international schedule | 1 electronic copy |
&"Arial,Regular"&12Schedule of Deliverables for PISA 2015