This document is a Questions and Answers (Q&A) file for a Request for Information (RFI) regarding Large Caliber Penetrators Tail Kits. The government is seeking information about a potential contract for three to five tail kits, with an anticipated contract award in FY27 Q1. The project involves an existing design at Level 2 Technical Data Package (TDP) with level 2 drawings, for which the government will retain all data rights. The RFI is requesting capability for flight testing on non-government aircraft, with the entire effort including flight testing to be completed within a 9-12 month period of performance.
Key details include that the specific aircraft for the munition has not yet been identified, and the vendor will be responsible for store-to-aircraft integration. The contract type, funding profile, and whether there will be a small business lead or teamed approach are still undetermined, as the government is in the acquisition planning phase. No funding has been secured at this time, and the government has not made a final decision about potentially replacing an incumbent, stating that all options will be considered.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend 1_Large Caliber Penetrator - Phase 1B RFI.pdf | ||
| Large Caliber Penetrator - Phase 1B RFI.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions Answers 1 Is there an existing design or is this a new design? Existing design a If there is an existing design, what level is it. Level 2 TDP with level 2 drawings
2 Is there an incumbent on this tail kit requirement?
The Government will have all data rights from the Level 2 TDP a If so, is it the government’s intent to possibly replace the incumbent with a best value solution?
The Government has not made a final decision as we are still in the planning phase. All options offered will be considered.
Are you interested in a small business lead for this contract? If so, we may be able to offer a small business led effort with a large OEM as a sub, where the strengths of both companies are brought to bear.
Please present the approach you see as best fit to the government for consideration a In relation to the RFI response options, should a teamed approach be presented, would the government prefer an All-Inclusive response that combines both the small and large business capabilities?
Please present the approach you see as best fit to the government for consideration
What contract-type (firm-fixed-price, cost-plus-award-fee, IDIQ) and funding profile will be used throughout the effort?
Unknown at this time, still in Acquisition Planning Phase.
5 Are there any data-rights or IP-sharing clauses that affect the transfer of design data, software, or test results?
For the purposes of this RFI, all that will be provided is a Level II TDP for the tailkit. No software or tailkit development test results
6 Are there any data-rights or IP-sharing clauses that affect the transfer of design data, software, or test results? see above
7 Has funding been secured for this effort? Not at this time
8 When do you anticipate contract award should funding and a decision to move forward be received? FY27 Q1
9 How many Tail Kits to anticipate being required over the period of performance? three to five
10 Do you anticipate the need for additional Tail Kits for testing? No, included in amount above a If so, how many Tail Kits would likely be used for testing?
11 Can you identify which aircraft(s) would use this munition?
Not at this time. The aircraft will be identitifed at a later date if the Government moves forward with this effort.
a Would the integrator receive the necessary data to ensure store-to-aircraft integration?
The RFI is requesting capabilty for flight testing off of non- Government aircraft. Any store to aircraft integration for the non-government aircraft is the vendors responsibiilty.
In response to Request for Information - Large Caliber Penetrators, Contractor is seeking confirmation that flight testing is excluded from the 9-12 month Period of Performance (PoP).
Completion of flight testing is included in the 9-12 month period of performance.
If your company does not feel this is realistic, please state why and provide your timeline.