E - Schedule of Submittals.xlsx

XLSX spreadsheet 39 KB Posted

Attached to
Outside Runway Repair
Solicitation number
MXDP261002
Issued by

About this file

This is a Schedule of Submittals template for federal construction contract MXDP 26-1002, titled "Repair R05C1/2 Outside Runway 13L," establishing the timeline and documentation requirements for contractor submissions throughout the project lifecycle at Laughlin Air Force Base.

The schedule encompasses 41 submittal items organized into 11 categories: pre-construction submittals, shop drawing submittals, product data submittals, samples, design data, test reports, certificates, manufacturer's instructions, field reports, operation and maintenance data, and close-out submittals. Pre-construction submittals due prior to or shortly after Notice to Proceed include safety plans and certificates (14 days after NTP), backflow preventor documentation, entry access lists, temporary fire protection equipment proof, ATFP certificates, training certifications, FOD plans, work clearance permits, FAA notifications, airfield driving authorization, laydown yard requests, storm water permits, and traffic control plans, with critical items required 45 days prior to the pre-construction meeting. Design submittals follow a phased schedule: 65% design due 63 days after NTP, 95% design due 42 days after 65% approval, and 100% design due 35 days after 95% approval. Ongoing submittals include weekly daily inspection reports and progress reports, project schedules due 14 days after 100% design acceptance, and paint and glass bead compliance documentation. Close-out submittals required prior to final acceptance and within specified timeframes after final inspection include rubber weight tickets, hazmat usage logs, approved dump locations, OSHA reports, punchlist items, as-built drawings, O&M manuals, construction warranty management plans, and DD Form 1354 transfer documentation. The template provides fields for tracking required submission dates, receipt dates, review dates, return suspense dates, approval/disapproval notifications, and associated remarks for contract administration purposes.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittals Schedule SCHEDULE OF SUBMITTALS PROJECT # MXDP 26-1002 PROJECT TITLE Repair R05C1/2 Outside Runway 13L SOLICITATION / CONTRACT NO.

(To be completed by Project Engineer)(To be completed by Contract Administrator)
NUMBER OF COPIES REQUIRED
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALSTATEMENT OF WORK REFERENCECERTIFICATION OF COMPLIANCEDESIGN DRAWINGSSPECIFICATIONSDESIGN CALCULATIONSSHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURER'S RECOMMENDATIONMANUFACTURER'S WARRANTYCATALOG DATAOPERATING INSTRUCTIONSSCHEDULES, LISTINGS, REPORTS, PLANSTECHNICAL DATA/ SDSTEST REPORTSFIELD REPORTSMEMORADUM, APPROVAL LETTERSREQUIRED SUBMISSION DATE

fergusog: Enter the due date from the Contractor (MM/DD/YY)

DATE RECEIVED IN CONTRACTING

fergusog: Enter the date received from the Contractor. (MM/DD/YY)

DATE TO CIVIL ENGINEERING

fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY)

RETURN SUSPENSE DATE

fergusog: Enter the date the submittal is due back from CE

(MM/DD/YY)

SUBMITTAL NUMBERS

fergusog: Enter the Submittal Number

DATE CONTRACTOR NOTIFIED CONTRACTOR RESUBMITTAL FINAL APPROVAL

fergusog: Enter the submittal final approval date

(MM/DD/YY)

REMARKS

fergusog: Enter any comments pertaining to the submittal

APPR

fergusog: Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

DIS

fergusog: Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

fergusog: Enter the submittal final approval date fergusog: Enter any comments pertaining to the submittal fergusog: Enter the due date from the Contractor (MM/DD/YY) fergusog: Enter the date received from the Contractor. (MM/DD/YY) fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY) fergusog: Enter the date the submittal is due back from CE fergusog: Enter the Submittal Number fergusog: Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

SD-01 PRE-CONSTRUCTION SUBMITTALS
1BACKFLOW PREVENTOR (IF FIRE HYDRANT USED)SOW, 2.6.2.81BEFORE START OF CONSTRUCTION
2ENTRY ACCESS LISTDiv 1, 1.8.2114 DAYS PRIOR TO NEEDING ACCESS ON BASEMust be updated with every new personel
3PROOF OF TEMPORARY FIRE PROTECTION EQUIPMENT ON SITEDiv 1, 1.8.71NLT 14 DAYS PRIOR TO CONSTRUCTION
4AF FORM 3000 (USE FOR ALL FORMAL CORRESPONDANCE SUBMITTED TO CO AND ATTACH PDF COPY)Div 1, 11.11USE FOR ALL FORMAL CORRESPONDANCE SUBMITTED TO CO AND ATTACH PDF COPY
5CONTRACTOR'S SAFETY PLANDiv 1, 3.2.21NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE
6CERTIFICATES OF CONTRACTOR'S SAFETY COMPLIANCEDiv 1, 3.2.311NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE
7HAZMAT USAGE LOGEQ spec, 6.11PRIOR TO CONSTRUCTION AND NLT 7 DAYS AFTER FINAL INSPECTION
8CONSTRUCTION SITE PLANDiv 1, 12.11NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE
9ATFP CERTIFICATEDiv 1, 2.41PRIOR TO BEGINNING CONSTRUCTION
10INFORMATION PROTECTION TRAINING CERTIFICATESOW 2.4.21NLT 14 DAYS AFTER NTP
11CONFIRMATION OF EMS AWARENESS TRAININGEQ Specs Appendix B1NLT 14 DAYS AFTER NTP
12FOD PLANDiv 1, 14.91NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE
13Worker/Area Protection PlanEQ Specs Appendix BNLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE
14AF103 WORK CLEARANCE PERMITDiv 1, 2.2145 DAYS PRIOR TO PRE-CON MEETING
15FAA NOTIFICATION 7460Div 1, 14.7145 DAYS PRIOR TO PRE-CON MEETING
16AIRFIELD DRIVINGDiv 1, 14.1017 DAYS PRIOR TO PRE-CON MEETING
17LAYDOWN YARD REQUESTDiv 1, 12.3145 DAYS PRIOR TO PRE-CON MEETING
18STORM WATER CONSTRUCTION PERMITEQ Spec, 3.4.2145 DAYS PRIOR TO PRE-CON MEETING
19TRAFFIC CONTROL PLANDiv 1, 12.21NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE
SD-02 SHOP DRAWING SUBMITTALS
2065% DESIGNSOW, 3.1.1NLT 63 DAYS AFTER NTP
2195% DESIGNSOW, 3.1.2NLT 42 DAYS AFTER GOVERNMENT APPROVED 65%
22100% DESIGNSOW, 3.1.3NLT 35 DAY AFTER GOVERNMENT APPROVED 95%
SD-03 PRODUCT DATA SUBMITTALS
23DAILY INSPECTION REPORTSDiv 1, 4,2,61WEEKLY
24PROJECT SCHEDULEDiv 1, 6.1.11NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE
25PROGRESS SCHEDULE /SCHEDULE OF VALUESDiv 1, 6.1.11NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE
26PROGRESS REPORTDiv 1, 6.1.21WEEKLY
SD-04 SAMPLES SUBMITTALS
27PAINT COMPLIANCEUFC 3-260-041NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE
28GLASS BEAD COMPLIANCEUFC 3-260-041NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE
SD-05 DESIGN DATA SUBMITTALS
SD-06 TEST REPORT SUBMITTALS
29BACKFLOW PREVENTOR TEST REPORTSOW, 2.6.2.81NLT 7 DAYS ATER COMPLETION OF TEST
SD-07 CERTIFICATE SUBMITTALS
30SUPERVISOR REQUIREMENTDiv 1, 4.2.211NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE
31PERSONNEL REQUIREMENT FOR QUALITY CONTROLDiv 1, 4.2.311NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE
SD-08 MANUFACTURER'S INSTRUCTION SUBMITTALS
SD-09 MANUFACTURER'S FIELD REPORT SUBMITTALS
SD-10 OPERATION AND MAINTENANCE DATA SUBMITTALS
SD-11 CLOSE OUT SUBMITTALS
32RUBBER WEIGHT TICKETAttachment B, EQ Specs1PRIOR TO FINAL ACCEPTANCE
33HAZMAT USAGE LOGAppendix C, EQ specs1PRIOR TO CONSTRUCTION AND NLT 7 DAYS AFTER FINAL INSPECTION
34APPROVED DUMP LOCATIONEQ specs, 5.11PRIOR TO FINAL ACCEPTANCE
35OSHA REPORT(S)Div 1, 3.2.41AS RECEIVED
36QC MANAGER'S PUNCHLISTDiv 1, 13.4NLT 3 DAYS AFTER PRE-INSPECTION
37AS BUILT DRAWINGSSOWNLT 7 DAYS AFTER FINAL INSPECTION
38O & M MANUALSDiv 1, 10.4NLT 14 DAYS AFTER FINAL INSPECTION
29CONSTRUCTION WARRANTY MANAGEMENT PLANDiv 1, 13.21NLT 14 DAYS AFTER FINAL ACCEPTANCE
40DRAFT DD FORM 1354 TRANSFER AND ACCEPTANCE OF MILITARY REAL PROPERTYDiv 1, 13.3PRIOR TO FINAL INSPECTION
41FINAL DD FORM 1354 TRANSFER AND ACCEPTANCE OF MILITARY REAL PROPERTYDiv 1, 13.31AT FINAL INSPECTION
Schedule of Submittals Template, Feb 05 (SAF/AQCP)

&"Times New Roman,Regular"&12Page &P of &N