E - Schedule of Submittals.xlsx
XLSX spreadsheet 39 KB Posted
- Attached to
- Outside Runway Repair
- Solicitation number
- MXDP261002
About this file
This is a Schedule of Submittals template for federal construction contract MXDP 26-1002, titled "Repair R05C1/2 Outside Runway 13L," establishing the timeline and documentation requirements for contractor submissions throughout the project lifecycle at Laughlin Air Force Base.
The schedule encompasses 41 submittal items organized into 11 categories: pre-construction submittals, shop drawing submittals, product data submittals, samples, design data, test reports, certificates, manufacturer's instructions, field reports, operation and maintenance data, and close-out submittals. Pre-construction submittals due prior to or shortly after Notice to Proceed include safety plans and certificates (14 days after NTP), backflow preventor documentation, entry access lists, temporary fire protection equipment proof, ATFP certificates, training certifications, FOD plans, work clearance permits, FAA notifications, airfield driving authorization, laydown yard requests, storm water permits, and traffic control plans, with critical items required 45 days prior to the pre-construction meeting. Design submittals follow a phased schedule: 65% design due 63 days after NTP, 95% design due 42 days after 65% approval, and 100% design due 35 days after 95% approval. Ongoing submittals include weekly daily inspection reports and progress reports, project schedules due 14 days after 100% design acceptance, and paint and glass bead compliance documentation. Close-out submittals required prior to final acceptance and within specified timeframes after final inspection include rubber weight tickets, hazmat usage logs, approved dump locations, OSHA reports, punchlist items, as-built drawings, O&M manuals, construction warranty management plans, and DD Form 1354 transfer documentation. The template provides fields for tracking required submission dates, receipt dates, review dates, return suspense dates, approval/disapproval notifications, and associated remarks for contract administration purposes.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| G - Airfield Pavement Condition Index Survey report.pdf | ||
| 5 - MXDP 26-1002 SOW.docx | DOCX document | |
| D. LAFB IFS.pdf | ||
| C - LAFB Environmental Quality Construction Specifications.pdf | ||
| B - Division 01 Specification Guidelines.docx | DOCX document | |
| F - Progress Schedule Form and Contract Progress Report.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittals Schedule SCHEDULE OF SUBMITTALS PROJECT # MXDP 26-1002 PROJECT TITLE Repair R05C1/2 Outside Runway 13L SOLICITATION / CONTRACT NO.
| (To be completed by Project Engineer) | (To be completed by Contract Administrator) | |||||||||||||||||||
| NUMBER OF COPIES REQUIRED | ||||||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | STATEMENT OF WORK REFERENCE | CERTIFICATION OF COMPLIANCE | DESIGN DRAWINGS | SPECIFICATIONS | DESIGN CALCULATIONS | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATION | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | SCHEDULES, LISTINGS, REPORTS, PLANS | TECHNICAL DATA/ SDS | TEST REPORTS | FIELD REPORTS | MEMORADUM, APPROVAL LETTERS | REQUIRED SUBMISSION DATE |
fergusog: Enter the due date from the Contractor (MM/DD/YY)
DATE RECEIVED IN CONTRACTING
fergusog: Enter the date received from the Contractor. (MM/DD/YY)
DATE TO CIVIL ENGINEERING
fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY)
RETURN SUSPENSE DATE
fergusog: Enter the date the submittal is due back from CE
(MM/DD/YY)
SUBMITTAL NUMBERS
fergusog: Enter the Submittal Number
DATE CONTRACTOR NOTIFIED CONTRACTOR RESUBMITTAL FINAL APPROVAL
fergusog: Enter the submittal final approval date
(MM/DD/YY)
REMARKS
fergusog: Enter any comments pertaining to the submittal
APPR
fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
DIS
fergusog: Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
fergusog: Enter the submittal final approval date fergusog: Enter any comments pertaining to the submittal fergusog: Enter the due date from the Contractor (MM/DD/YY) fergusog: Enter the date received from the Contractor. (MM/DD/YY) fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY) fergusog: Enter the date the submittal is due back from CE fergusog: Enter the Submittal Number fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
| SD-01 PRE-CONSTRUCTION SUBMITTALS | |||||||||||||||
| 1 | BACKFLOW PREVENTOR (IF FIRE HYDRANT USED) | SOW, 2.6.2.8 | 1 | BEFORE START OF CONSTRUCTION | |||||||||||
| 2 | ENTRY ACCESS LIST | Div 1, 1.8.2 | 1 | 14 DAYS PRIOR TO NEEDING ACCESS ON BASE | Must be updated with every new personel | ||||||||||
| 3 | PROOF OF TEMPORARY FIRE PROTECTION EQUIPMENT ON SITE | Div 1, 1.8.7 | 1 | NLT 14 DAYS PRIOR TO CONSTRUCTION | |||||||||||
| 4 | AF FORM 3000 (USE FOR ALL FORMAL CORRESPONDANCE SUBMITTED TO CO AND ATTACH PDF COPY) | Div 1, 11.1 | 1 | USE FOR ALL FORMAL CORRESPONDANCE SUBMITTED TO CO AND ATTACH PDF COPY | |||||||||||
| 5 | CONTRACTOR'S SAFETY PLAN | Div 1, 3.2.2 | 1 | NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE | |||||||||||
| 6 | CERTIFICATES OF CONTRACTOR'S SAFETY COMPLIANCE | Div 1, 3.2.3 | 1 | 1 | NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE | ||||||||||
| 7 | HAZMAT USAGE LOG | EQ spec, 6.1 | 1 | PRIOR TO CONSTRUCTION AND NLT 7 DAYS AFTER FINAL INSPECTION | |||||||||||
| 8 | CONSTRUCTION SITE PLAN | Div 1, 12.1 | 1 | NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE | |||||||||||
| 9 | ATFP CERTIFICATE | Div 1, 2.4 | 1 | PRIOR TO BEGINNING CONSTRUCTION | |||||||||||
| 10 | INFORMATION PROTECTION TRAINING CERTIFICATE | SOW 2.4.2 | 1 | NLT 14 DAYS AFTER NTP | |||||||||||
| 11 | CONFIRMATION OF EMS AWARENESS TRAINING | EQ Specs Appendix B | 1 | NLT 14 DAYS AFTER NTP | |||||||||||
| 12 | FOD PLAN | Div 1, 14.9 | 1 | NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE | |||||||||||
| 13 | Worker/Area Protection Plan | EQ Specs Appendix B | NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE | ||||||||||||
| 14 | AF103 WORK CLEARANCE PERMIT | Div 1, 2.2 | 1 | 45 DAYS PRIOR TO PRE-CON MEETING | |||||||||||
| 15 | FAA NOTIFICATION 7460 | Div 1, 14.7 | 1 | 45 DAYS PRIOR TO PRE-CON MEETING | |||||||||||
| 16 | AIRFIELD DRIVING | Div 1, 14.10 | 1 | 7 DAYS PRIOR TO PRE-CON MEETING | |||||||||||
| 17 | LAYDOWN YARD REQUEST | Div 1, 12.3 | 1 | 45 DAYS PRIOR TO PRE-CON MEETING | |||||||||||
| 18 | STORM WATER CONSTRUCTION PERMIT | EQ Spec, 3.4.2 | 1 | 45 DAYS PRIOR TO PRE-CON MEETING | |||||||||||
| 19 | TRAFFIC CONTROL PLAN | Div 1, 12.2 | 1 | NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE | |||||||||||
| SD-02 SHOP DRAWING SUBMITTALS | |||||||||||||||
| 20 | 65% DESIGN | SOW, 3.1.1 | NLT 63 DAYS AFTER NTP | ||||||||||||
| 21 | 95% DESIGN | SOW, 3.1.2 | NLT 42 DAYS AFTER GOVERNMENT APPROVED 65% | ||||||||||||
| 22 | 100% DESIGN | SOW, 3.1.3 | NLT 35 DAY AFTER GOVERNMENT APPROVED 95% | ||||||||||||
| SD-03 PRODUCT DATA SUBMITTALS | |||||||||||||||
| 23 | DAILY INSPECTION REPORTS | Div 1, 4,2,6 | 1 | WEEKLY | |||||||||||
| 24 | PROJECT SCHEDULE | Div 1, 6.1.1 | 1 | NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE | |||||||||||
| 25 | PROGRESS SCHEDULE /SCHEDULE OF VALUES | Div 1, 6.1.1 | 1 | NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE | |||||||||||
| 26 | PROGRESS REPORT | Div 1, 6.1.2 | 1 | WEEKLY | |||||||||||
| SD-04 SAMPLES SUBMITTALS | |||||||||||||||
| 27 | PAINT COMPLIANCE | UFC 3-260-04 | 1 | NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE | |||||||||||
| 28 | GLASS BEAD COMPLIANCE | UFC 3-260-04 | 1 | NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE | |||||||||||
| SD-05 DESIGN DATA SUBMITTALS | |||||||||||||||
| SD-06 TEST REPORT SUBMITTALS | |||||||||||||||
| 29 | BACKFLOW PREVENTOR TEST REPORT | SOW, 2.6.2.8 | 1 | NLT 7 DAYS ATER COMPLETION OF TEST | |||||||||||
| SD-07 CERTIFICATE SUBMITTALS | |||||||||||||||
| 30 | SUPERVISOR REQUIREMENT | Div 1, 4.2.2 | 1 | 1 | NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE | ||||||||||
| 31 | PERSONNEL REQUIREMENT FOR QUALITY CONTROL | Div 1, 4.2.3 | 1 | 1 | NLT 14 DAYS AFTER 100% DESIGN ACCEPTANCE | ||||||||||
| SD-08 MANUFACTURER'S INSTRUCTION SUBMITTALS | |||||||||||||||
| SD-09 MANUFACTURER'S FIELD REPORT SUBMITTALS | |||||||||||||||
| SD-10 OPERATION AND MAINTENANCE DATA SUBMITTALS | |||||||||||||||
| SD-11 CLOSE OUT SUBMITTALS | |||||||||||||||
| 32 | RUBBER WEIGHT TICKET | Attachment B, EQ Specs | 1 | PRIOR TO FINAL ACCEPTANCE | |||||||||||
| 33 | HAZMAT USAGE LOG | Appendix C, EQ specs | 1 | PRIOR TO CONSTRUCTION AND NLT 7 DAYS AFTER FINAL INSPECTION | |||||||||||
| 34 | APPROVED DUMP LOCATION | EQ specs, 5.1 | 1 | PRIOR TO FINAL ACCEPTANCE | |||||||||||
| 35 | OSHA REPORT(S) | Div 1, 3.2.4 | 1 | AS RECEIVED | |||||||||||
| 36 | QC MANAGER'S PUNCHLIST | Div 1, 13.4 | NLT 3 DAYS AFTER PRE-INSPECTION | ||||||||||||
| 37 | AS BUILT DRAWINGS | SOW | NLT 7 DAYS AFTER FINAL INSPECTION | ||||||||||||
| 38 | O & M MANUALS | Div 1, 10.4 | NLT 14 DAYS AFTER FINAL INSPECTION | ||||||||||||
| 29 | CONSTRUCTION WARRANTY MANAGEMENT PLAN | Div 1, 13.2 | 1 | NLT 14 DAYS AFTER FINAL ACCEPTANCE | |||||||||||
| 40 | DRAFT DD FORM 1354 TRANSFER AND ACCEPTANCE OF MILITARY REAL PROPERTY | Div 1, 13.3 | PRIOR TO FINAL INSPECTION | ||||||||||||
| 41 | FINAL DD FORM 1354 TRANSFER AND ACCEPTANCE OF MILITARY REAL PROPERTY | Div 1, 13.3 | 1 | AT FINAL INSPECTION | |||||||||||
| Schedule of Submittals Template, Feb 05 (SAF/AQCP) |