(E) NAVFAC RFI form.pdf

PDF 168 KB Posted

Attached to
Building 17 Replace Elevator and Associated Electrical Work Federal contract opportunity
Solicitation number
N4008520R3015
Issued by
Department of the Navy Naval Facilities Engineering Command

View the file

Other files for this federal contract opportunity

Other files attached to Building 17 Replace Elevator and Associated Electrical Work, newest first.
File Type Posted
N4008520R3015AMEND03.pdf PDF
20-R-3015 -0002 Amend.pdf PDF
2016-R-0149.pdf PDF
ip06-35_Building_Contractors_Guide_to_Taxes.pdf PDF
cert-141.pdf PDF
20R3015 Amendment 0001.pdf PDF
Revised B17 Elevator Drawings.pdf PDF
(F) 01 31 23.13 20 ECMS Spec.pdf PDF
(C) CT20200024 Rev. 3.pdf PDF
(I) BASE MAP BLDG 135.pdf PDF
(H) B17 Elevator Drawings.pdf PDF
(D) Base Access Pass Request.pdf PDF
(B) Price Proposal Form.pdf PDF
(A) B17 Elevator Specs.pdf PDF
N4008520R3015 RFP.pdf PDF
(G) General Req Revised -9 2018.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT NUMBER:

N40085-20-R-3015

REQUEST FOR INFORMATION RFI NUMBER:

CONTRACT TITLE:

PRIME CONTRACTOR: SUBCONTRACTOR/SUPPLIER:

SUBJECT/TITLE OF RFI:

DRAWING(S): DETAIL(S): SPECIFICATION: CPM ACTIVITY NUMBER:

COST EFFECT: INCREASE: DECREASE: NONE:

INFORMATION REQUESTED & RECOMMENDED SOLUTION:

Date Response Required By: Date: Signature:

From:

To: Field Office Code

RECOMMENDATION:

Date: Signature:

From: Field Office To: Prime Contractor

REPLY:

Date: Signature:

This reply is given with the expressed understanding that it does not constitute basis for change in the amount or time of subject contract. If you do not concur, DO NOT PROCEED, and notify this office immediately.

Please assign PC # to this change. It is requested that a proposal be forwarded by . THIS DOES NOT

CONSTITUTE AUTHORIZATION TO PROCEED.

copy to: File 2L

Supv Civil Engineer Construction Representative

The RFI system is intended to provide an efficient mechanism for responding to contractor’s request for information ONLY. This system DOES NOT authorize the contractor to proceed with work - to do so, the contractor proceeds at his own risk. If the contractor considers the RFI response a changed condition, written notice to the Contracting Officer is required within 20 calendar days.

DISTRIBUTION: Original to File via REICC PL/DM ET A/E PC # via AROICC/CONTRACT OFFICER