About this file

This document is a Request for Proposal (RFP) #4/24/2018 issued by Essexville-Hampton Public Schools (E-HPS) in Essexville, Michigan for a Garber High School Office Renovation Project. The project involves converting two classrooms into new office areas and transforming the current office area into multipurpose rooms. A mandatory pre-bid walkthrough is scheduled for Tuesday, May 1, 2018, at 11:00 am, with proposals due on Monday, May 14, 2018, at 1:00 PM EST. The project will be overseen by Project Engineer J. William Jensen, P.E. from Great Lakes Critical Power and Cooling, with owner contacts being Matthew Cortez and Steve Barlow from E-HPS.

The RFP outlines comprehensive terms and conditions for bidders, including evaluation criteria such as bidder's ability to satisfy requirements, compliance with specifications, experience, cost, and references. E-HPS reserves the right to accept or reject any proposals and is not obligated to select the lowest-cost bid. Bidders must submit a complete proposal on their letterhead, including individual pricing, discounts, and option pricing. The school district requires all materials to be new, genuine manufacturer products with full warranty coverage. Proposals cannot be withdrawn for 90 days, and the successful bidder will be an independent contractor responsible for their own insurance, employees, and performance.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP #4/24/2018 Essexville-Hampton Public Schools- Office Renovation April 24, 2018

GLCPC bill@jwjensenpe.com 810-701-8768

Pa ge

Essexville-Hampton Public Schools Garber High School Office Renovation

REQUEST FOR PROPOSAL

RFP #4/24/2018 Office Renovation

Mandatory Pre-Bid Walkthrough

Tuesday, May 1, 2018 11:00 am in Garber High School

PROP0SALS DUE:

MONDAY, May14, 2018

1:00 PM EST

OWNER CONTACTS:

Matthew Cortez: cortezm@e-hps.net;

Steve Barlow: barlows@e-hps.net

303 Pine Street Essexville, Michigan 48732 989-984-9700

PROJECT ENGINEER/ CONTACT:

J. William Jensen, P.E.

bjensen@glcpc.com 810-701-8768 mailto:cortezm@e-hps.net mailto:bjensen@glcpc.com

Pa ge

NOTICE!

PROPOSAL: Essexville-Hampton Public Schools (E-HPS) is soliciting bids for the E-HPS Garber OFFICE RENOVATION Project. Proposals are due to E-HPS; Attention Matthew Cortez on May 14th, 2018 no later than 1:00 PM. E-mailed Protected Proposals will be accepted using a “Return Receipt, Read Format”.

RIGHT TO REJECT: Essexville-Hampton Public Schools (E-HPS) reserves the right to accept or reject any and all proposals, to negotiate terms of proposal(s) with successful vendor(s), to accept a proposal that is not the lowest cost, and to accept the proposal(s) that is in the best interest of E-HPS

WITHDRAWAL OF ANY PROPOSALS is prohibited for a period of ninety (90) days after the proposal due date.

LATE, INCOMPLETE AND NON-CONFORMING PROPOSALS: E-HPS reserves the right to reject without evaluation late, incomplete or otherwise non-conforming proposals.

COMPLETE PROPOSALS: All proposals must contain terms of purchase and delivery in writing. E-HPS will negotiate the actual delivery terms and timetable with the successful manufacturer’s representative, but each proposal must include the anticipated time frame during which E-HPS may reasonably expect materials and equipment to be delivered. E-HPS will not be responsible for any ancillary charges, costs, and/or fees not expressly delineated in the terms of the proposal.

PRESENTATIONS: Prospective bidders are requested to prepare a reference list of previous E- HPS projects.

QUESTIONS: Prospective bidders are solely responsible for understanding the requirements of this RFP. Questions regarding any part of this proposal should be submitted in writing to the OWNER via e-mail using “Read Receipt” format.

PROJECT ENGINEER:

J. William Jensen, P.E.

Great Lakes Critical Power and Cooling bill@jwjensenpe.com

810-701-8768

OWNER:

Matthew T. Cortez, Superintendent 303 Pine Street Essexville, Michigan 48732 989-984-9700

Pa ge

INTRODUCTION

This Request for Proposal #4/24/2018 is released by Essexville-Hampton Public Schools (E-HPS) through their Project Engineer for the Garber OFFICE RENOVATION Project.

SECTION 1

GENERAL INFORMATION

Essexville-Hampton Public Schools (E-HPS) intends to solicit bids for the OFFICE

RENOVATION of Garber High School. The project scope includes the conversion of two classrooms to new office areas and the conversion of the current office area to multipurpose rooms..

The requirements included in this proposal are complete. The representations made by E-HPS herein are accurate, true and complete to the best of our knowledge. E-HPS, through their Project Engineer prefers to work with only one (1) contact person throughout the proposal process. Please appoint one (1) representative from your firm as your contact for this proposal. This person will be responsible for all communications with the OWNER and Project Engineer that relate to this Request for Proposal. The OWNER will receive all bids and communicate directly with your primary contact for the project.

Your final proposal must be complete and presented in its entirety. All conditions, terms, costs, charges and fees must be included in the proposal. Should E-HPS accept your proposal, any terms, conditions, costs, charges and/or fees excluded from your proposal at the time of submission shall remain excluded and will become the responsibility of the winning bidder.

All proposals must be submitted in writing. Proposals must be signed by a representative who is duly authorized to make such representations to E-HPS on behalf of your firm. Your proposal will form the basis of a purchase contract with E-HPS and should include all equipment and materials that, in your judgment, are necessary to meet the requirements of this proposal.

Pa ge

SECTION 2

TERMS AND CONDITIONS

2.01. Your complete and entire response to this RFP must be received by the OWNER prior to 1:00 pm (EST) May 14th, 2018. Please MAIL or DELIVER your response, with supporting documentation, IN WRITING. Your response should include all requested and required information, as well as any supporting data needed to complete your response. Late responses will not be considered. Bidders are solely responsible for confirming that their responses were received in a timely way. A Verification phone call to the OWNER is acceptable.

2.02. Questions, uncertainties, noted discrepancies and omissions regarding this RFP shall be reported immediately in writing to the OWNER. Should any reported issues require clarification, written instructions or an addendum to the RFP will be distributed to all potential bidders.

E-HPS will not accept any responsibility for any oral interpretation of the requirements. Bidders should rely only on the written responses of the OWNER. E-HPS reserves the right to solicit additional information from bidders to aid our determination of the bid that best meets the needs of E-HPS If our request for additional information on a proposal is not met in a timely way, E-HPS reserves the right to reject the proposal as non-conforming.

2.03. E-HPS reserves the right to reject or accept any bids, in part or whole; select bidders whose proposals best meet the needs of E-HPS without respect to the lowest cost proposal;

and negotiate terms of the proposal to ensure the best interests of E-HPS are met. E-HPS does not assume any contractual obligations or duties as the result of issuing this RFP. No employment relationship will be assumed between E-HPS and the successful bidder.

2.04. Bidders are not entitled to use E-HPS’s name, service mark(s), trademarks or trade names without the express written permission of E-HPS

2.05. E-HPS will evaluate each bid received using the following criteria, listed here in no particular order of importance:

a. The bidder’s ability to satisfy each term and condition fully

b. Compliance with the specifications stated herein

c. Experience with delivering the requirements of the specification

d. Cost (including pricing and price protection)

e. References from previous customers for work of similar scope

f. Interviews as required by E-HPS

g. Other factors not specifically expressed here that are relevant to determining which proposal will succeed.

2.06. Proposals may not be withdrawn for ninety (90) days from the time of issue. After ninety (90) days, proposals may be withdrawn by way of a written request directed to the OWNER.

Successor proposals may not be substituted for a withdrawn proposal. Withdrawal of a proposal

Pa ge constitutes disqualification from the bid process, should E-HPS not render a decision within ninety

(90) days of the response due date.

2.07. Once the successful proposal has been determined and awarded, either party may withdraw from this agreement by giving the other party at least ninety (90) days’ prior written notice of the termination date. Termination or cancellation of this agreement does not affect the collection, enforcement or validity of any accrued obligations between the bidder and E-HPS

2.08. Once the successful proposal has been determined and awarded, modifications deemed necessary to correct errors found to be the sole fault of the bidder and to satisfy performance of the agreement shall be made expediently and at no additional cost to E-HPS This clause will survive the termination and/or expiration of this agreement without respect to the cause or reason for the error.

2.09. No information, report, etc. developed in connection with this RFP may be reproduced without E-HPS’s prior written consent. No portion of this RFP may be reproduced without E-HPS’s prior written consent.

2.10. The successful bidder must perform all work unless E-HPS specifically approves subcontracting in writing prior to the commencement of any work related to this RFP.

2.11. The successful bidder is an independent contractor, licensed and bonded as necessary, and is solely responsible for employment, acts, omissions, insurance, control and direction of its employees. The bidder agrees to indemnify and hold harmless E-HPS, its trustees, officers, employees and agents from any and all damages, injury, loss, claims, demands, or causes of action in the event that the bidder fails or neglects to provide appropriate insurance coverage for its employees while working in performance of this contract at E-HPS, including but not limited to payment of any claims.

2.12. Any personal injury to the bidder, its successors, assigns, employees, agents, subcontractors or third parties or any property damage incurred in the performance of this agreement shall be the responsibility of the bidder. The bidder agrees to restore or make whole any loss of or damage to the property of E-HPS incurred during the performance of this agreement.

2.13. Bidder warrants that all equipment offered for sale to E-HPS are all new materials, genuine products of the chosen manufacturer, delivered in original packaging with all parts and manuals, able to be registered for warranty purposes by E-HPS, eligible for the full manufacturer’s warranty period and warranted as described by the manufacturer.

2.14. Bidder agrees to accept E-HPS’s standard payment terms. Prices quoted in bidder’s response shall be FOB E-HPS, Essexville, Michigan unless otherwise specified. All items on the bidder’s response will be itemized, and all charges and discounts shall be clearly shown.

Pa ge

SECTION 3

BID FORM

E-HPS will accept proposals on your letterhead which should include all appropriate prices for each size of unit as individual pricing, any discounts and individual option pricing for features that you suggest for added energy and operating efficiency.

All Proposals should clearly indicate the RFP #4/24/2018 and should acknowledge the Terms and Conditions of E-HPS as reflected herein. PLEASE INDICATE RECEIPT OF THIS RFP by RETURN RECEIPT.

SECTION 1
SECTION 2
TERMS AND CONDITIONS
2.01. Your complete and entire response to this RFP must be received by the OWNER prior to 1:00 pm (EST) May 14th, 2018. Please MAIL or DELIVER your response, with supporting documentation, IN WRITING. Your response should include all requested and ...
2.02. Questions, uncertainties, noted discrepancies and omissions regarding this RFP shall be reported immediately in writing to the OWNER. Should any reported issues require clarification, written instructions or an addendum to the RFP will be dist...
2.03. E-HPS reserves the right to reject or accept any bids, in part or whole; select bidders whose proposals best meet the needs of E-HPS without respect to the lowest cost proposal; and negotiate terms of the proposal to ensure the best interests ...
2.04. Bidders are not entitled to use E-HPS’s name, service mark(s), trademarks or trade names without the express written permission of E-HPS
2.05. E-HPS will evaluate each bid received using the following criteria, listed here in no particular order of importance:
a. The bidder’s ability to satisfy each term and condition fully
b. Compliance with the specifications stated herein
c. Experience with delivering the requirements of the specification
d. Cost (including pricing and price protection)
e. References from previous customers for work of similar scope
f. Interviews as required by E-HPS
g. Other factors not specifically expressed here that are relevant to determining which proposal will succeed.
2.06. Proposals may not be withdrawn for ninety (90) days from the time of issue. After ninety (90) days, proposals may be withdrawn by way of a written request directed to the OWNER. Successor proposals may not be substituted for a withdrawn propos...
2.07. Once the successful proposal has been determined and awarded, either party may withdraw from this agreement by giving the other party at least ninety (90) days’ prior written notice of the termination date. Termination or cancellation of this ...
2.08. Once the successful proposal has been determined and awarded, modifications deemed necessary to correct errors found to be the sole fault of the bidder and to satisfy performance of the agreement shall be made expediently and at no additional ...
2.09. No information, report, etc. developed in connection with this RFP may be reproduced without E-HPS’s prior written consent. No portion of this RFP may be reproduced without E-HPS’s prior written consent.
2.10. The successful bidder must perform all work unless E-HPS specifically approves subcontracting in writing prior to the commencement of any work related to this RFP.
2.11. The successful bidder is an independent contractor, licensed and bonded as necessary, and is solely responsible for employment, acts, omissions, insurance, control and direction of its employees. The bidder agrees to indemnify and hold harmles...
2.12. Any personal injury to the bidder, its successors, assigns, employees, agents, subcontractors or third parties or any property damage incurred in the performance of this agreement shall be the responsibility of the bidder. The bidder agrees to...
2.13. Bidder warrants that all equipment offered for sale to E-HPS are all new materials, genuine products of the chosen manufacturer, delivered in original packaging with all parts and manuals, able to be registered for warranty purposes by E-HPS, ...
2.14. Bidder agrees to accept E-HPS’s standard payment terms. Prices quoted in bidder’s response shall be FOB E-HPS, Essexville, Michigan unless otherwise specified. All items on the bidder’s response will be itemized, and all charges and discounts ...
2.15.
SECTION 3
BID FORM
E-HPS will accept proposals on your letterhead which should include all appropriate prices for each size of unit as individual pricing, any discounts and individual option pricing for features that you suggest for added energy and operating efficiency.
All Proposals should clearly indicate the RFP #4/24/2018 and should acknowledge the Terms and Conditions of E-HPS as reflected herein. PLEASE INDICATE RECEIPT OF THIS RFP by RETURN RECEIPT.