Questions-Answers_19_Sep_14.pdf
PDF 8 KB Posted
- Solicitation number
- Durbin-F1L3SM4216A002
About this file
This is a response to a question regarding if a drop test will be required for the resurfacing. A drop test will not be required only documentation that the critical height requirement of at least 8 feet is met.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions-Answers_18_Sep_14.docx | DOCX document | |
| Amended_Playground_SOW.pdf | ||
| Playground_SOW.pdf | ||
| Playground_Resurface_Synopsis-Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers 19 Sep 14: Resurface Playground; Durbin-
F1L3SM4216A002
Question: Will there need to be a drop test conducted to determine the adequacy of the surface?
Answer: No drop test will be required at this time. The only documentation needed will be that the thickness of the entire surfacing meets the critical height requirement of at least 8 feet. This language is in the Statement of Work.