Durango Irrigation Raw Water Line Replacement IFB 2025.pdf

PDF 552 KB Posted

Attached to
Durango Irrigation Raw Water Line Replacement
Solicitation number
2025-0039
Issued by
La Plata County, Colorado

About this file

This is an Invitation for Bids issued by the City of Durango, Colorado for the Durango Irrigation Raw Water Line Replacement project (#0014). The project involves installing a 10-inch HDPE raw water irrigation line running from the existing pump shed at 950 Roosa Avenue to Greenmount Cemetery at 900 Cemetery Road, including connection points, curb and gutter replacement, asphalt patching, tree protection, fence relocation, ART concrete panel replacement, site rehabilitation, irrigation stub valve installation, third-party testing, and traffic control. The city is also seeking quotes for two additional alternates: repaving a 10,000 SF Maintenance Shop Parking Lot (Add Alt 1) and a 5,000 SF Schneider Park Parking Lot (Add Alt 2). A non-mandatory pre-bid conference is scheduled for August 19, 2025, at 1:00 p.m. at the project site, with questions due by August 27, 2025, and bids due September 19, 2025, at 3:00 p.m. The project must be completed by December 31, 2025, with construction ideally starting October 1, 2025, to avoid the cemetery's irrigation season that resumes April 1, 2026.

The contract requires a 5% bid bond and 100% performance and payment bonds upon award. Bidders must submit electronic proposals through Rocky Mountain E-Purchasing (www.bidnetdirect.com/colorado) and provide subcontractor lists, residency statements, and company qualifications including three similar project references. Payment terms are net 30 days with 5% retainage (capped at 2.5% of contract value). Local bidders receive a 5% preference (up to $100,000), regional bidders receive a 3% preference over non-resident bidders (up to $40,000), and liquidated damages are set at $1,500 per day for delays. The contractor must maintain comprehensive general liability insurance ($1M/$2M), automobile liability ($500K/$1M), and workers' compensation coverage, and the city reserves the right to reject any or all bids.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Durango Irrigation Raw Water Line Replacement #0014 Page 1 of 32 rev 8/5/2025

INVITATION FOR BIDS

PROJECT MANUAL

including

CONTRACT DOCUMENTS, PLANS

and

SPECIFICATIONS

for the

Durango Irrigation Raw Water Line Replacement Project # 0014

CITY OF DURANGO, COLORADO

August 1, 2025

City of Durango, Colorado

Durango Irrigation Raw Water Line Replacement #0014 Page 2 of 32 rev 8/5/2025

ADVERTISEMENT FOR BID

Invitation for Bids

Durango Irrigation Raw Water Line Replacement #0014

Sealed bids for the Durango Irrigation Raw Water Line Replacement project will be received by the City of Durango until 3:00 PM (Local Time) on September 19th, 2025.

Introduction: The City of Durango invites interested, qualified persons or firms capable of providing the required service to submit bids for improvements that generally consist of the installation of a 10” HDPE raw water irrigation line running from the existing pump shed at 950 Roosa Avenue to Greenmount Cemetery at 900 Cemetery Road.

Services provided by the Contractor will include but will not be limited to: raw water line installation, connection points 1 & 2 per plan, replacement of curb, gutter, and asphalt patching, tree protection as directed by COD, relocating fences along trench path, replacement of ART concrete panel, site rehabilitation, installation of irrigation stub valve, 3rd party testing, traffic control, and ensuring a clean and safe jobsite.

In addition to the above-mentioned work, the City of Durango is seeking quotes for the repaving of two of its parking lots affected by this project: Add Alt 1 - 10,000 SF Maintenance Shop Parking Lot and Add Alt 2 – 5,000 SF Schneider Park Parking Lot.

The Contractor shall furnish all labor, materials, tools, transportation, supplies, permits, and safety equipment needed to complete the work in accordance with the contract and the plans.

The intent is for the existing waterline to remain functional during the installation of the new line.

Schedule: This project is being scheduled outside of the irrigation season for the cemetery. Ideally, the project will start on October 1, 2025, and reach completion by December 31, 2025. Irrigation at the cemetery resumes April 1, 2026.

There will be a non-mandatory pre-bid conference at 1:00 p.m. (Local Time - MST) on Tuesday, August 19th, 2025, at the Project Site located near 950 Roosa Avenue, Durango, CO 81301, to familiarize bidders with the project.

Bids must be submitted via Rocky Mountain E-Purchasing www.bidnetdirect.com/colorado. It is the sole responsibility of the bidder to see that the proposal is received before the submission deadline. Late proposals will not be considered.

Bid documents and/or supporting information may be downloaded, at no charge, from the following web site:

www.bidnetdirect.com/colorado Click on “Vendor Registration” or “Vendor Login”, as applicable. Or at the City of Durango’s website: www.durangoCO.gov. No addendums or plans will be available on the City’s website.

The City of Durango reserves the right to reject any and all bids, to waive any informalities and minor irregularities in bids, and to accept the bid deemed, in the opinion of the City, to be in the best interest of the City of Durango.

This project is being bid in accordance with the City of Durango Purchasing Policy.

Published: August 6 & 8, 2025 http://www.bidnetdirect.com/colorado file://chfs2/projects/2024%20Projects/1159%20Rockridge%20Pump%20Station%20Replacement/02%20-Construction/01%20-%20Bidding/FINALS%20TO%20PURCHASING/www.durangoCO.gov

Durango Irrigation Raw Water Line Replacement #0014 Page 3 of 32 rev 8/5/2025

TABLE OF CONTENTS

I. Invitation for Bids

II. Instructions to Bidders

• Bidding Timetable

III. Scope of Services

IV. Insurance

V. Bidder Qualifications

VI. Bid Submission

• Bid Form

• List of Subcontractors

• Statement of Residency

Sample Documents

• Notice of Award

• Acceptance of Notice of Award

• Standard Form of Agreement Between City and Contractor for Construction Services

• Notice to Proceed and Acceptance of Notice to Proceed

• Change Order Form

Attachments

• General Conditions

• City of Durango Development Standards for Public Improvements and Construction

Specification

• City of Durango Multi-Use Trail Standards

• City of Durango Parks & Recreation Irrigation and Landscape Standards

• Project Plans o Greenmount Cemetery Irrigation Waterline Stamped Plans

• Bid Schedule

• COD SWQ Application

Durango Irrigation Raw Water Line Replacement #0014 Page 4 of 32 rev 8/5/2025

I. INVITATION FOR BIDS

The City of Durango, Colorado, by and through its Purchasing Administrator, invites interested, qualified bidders capable of providing the required services to submit bids for the Durango Irrigation Raw Water Line Replacement in accordance with the terms, conditions, and specifications contained in these documents.

Introduction: The City of Durango invites interested, qualified persons or firms capable of providing the required service to submit bids for improvements that generally consist of the installation of a 10” HDPE raw water irrigation line running from the existing pump shed at 950 Roosa Avenue to Greenmount Cemetery at 900 Cemetery Road.

Services provided by the Contractor will include but will not be limited to: raw water line installation, connection points 1 & 2 per plan, replacement of curb, gutter, and asphalt patching, tree protection as directed by COD, relocating fences along trench path, replacement of ART concrete panel, site rehabilitation, installation of irrigation stub valve, 3rd party testing, traffic control, and ensuring a clean and safe jobsite.

In addition to the above-mentioned work, the City of Durango is seeking quotes for the repaving of two of its parking lots affected by this project: Add Alt 1 - 10,000 SF Maintenance Shop Parking Lot and Add Alt 2 – 5,000 SF Schneider Park Parking Lot.

The Contractor shall furnish all labor, materials, tools, transportation, supplies, permits, and safety equipment needed to complete the work in accordance with the contract and the plans.

The intent is for the existing waterline to remain functional during the installation of the new line.

Schedule: This project is being scheduled outside of the irrigation season for the cemetery. Ideally, the project will start on October 1, 2025, and reach completion by December 31, 2025. Irrigation at the cemetery resumes April 1, 2026.

Bidders wishing to participate should ensure they have all addenda prior to submission of their bid. Failure to acknowledge receipt of any addenda applicable to this project could result in the rejection of your bid.

This request for proposals and any subsequent addenda will be posted to the Rocky Mountain E-Purchasing System website (www.bidnetdirect.com/colorado) then click on Vendor Login or Vendor Registration if you have not already registered. Firms are encouraged to register with RMEPS for all City bid opportunities.

There will be a non-mandatory pre-bid conference at 1:00 p.m. (Local Time - MST) on Tuesday, August 19th, 2025, at the Project Site located near 950 Roosa Avenue, Durango, CO 81301, to familiarize bidders with the project.

Questions: Each bidder, before submitting their bid, shall become fully informed as to the extent and character of work required. All questions must be submitted via the Rocky Mountain E-Purchasing System website (www.bidnetdirect.com/colorado).

Question Deadline: August 27, 2025, Time: 3:00 p.m. (Local Time) (Questions received after the deadline may not be accepted.)

Final Addendum: September 15, 2025, Time: 3:00 p.m. (Local Time) Submittal Instructions: Submittal requirements are outlined in the Bid Submission Section of the Bid Documents.

Deliver Bid via: Rocky Mountain E Purchasing (www.bidnetdirect.com/colorado) using the form furnished.

Bid Due Date and Time: September 19, 2025, Time: 3:00 p.m. (Local Time) It is the sole responsibility of the respondent to see that the bid is received before the submission deadline. Late bids will not be considered.

All bids submitted shall be binding upon the respondent if accepted by the City within sixty (60) calendar days of the submission date. Negligence upon the part of the respondent in preparing the bid confers no right of withdrawal after http://www.bidnetdirect.com/colorado

Durango Irrigation Raw Water Line Replacement #0014 Page 5 of 32 rev 8/5/2025 the time fixed for the submission of bid. This project is being bid in accordance with the City of Durango Purchasing Policy.

II. INSTRUCTIONS TO BIDDERS

The Bid Documents and any Addenda issued contain the provisions required for the construction of the Project.

Information otherwise obtained from an officer, agent, or employee of the Contracting Agency, or any other person, shall not affect the risks or obligations assumed by the Contractor or relieve him from fulfilling any of the conditions of the contract.

Bidders must verify the accuracy of the estimated quantities in the Bid Schedule by examining the site and reviewing the project documents, including Any Addenda. After Bids have been submitted, the Bidder shall not assert that there was a misunderstanding concerning the quantities of Work or the nature of the Work to be done.

All Bids must be made on the required Bid sheet and Bid Schedule. All blank spaces for Bid prices must be filled in, and the Bid sheet must be fully completed and executed when submitted. Only one copy of the Bid sheet is required.

Any improperly completed bids will not be accepted.

The Contracting Agency may waive any informalities or minor defects or reject any and all Bids. Any Bid may be withdrawn prior to the above-scheduled time for the opening of Bids or authorized postponement thereof. Any Bid received after the time and date specified shall not be considered and will be rejected. No Bidder may withdraw a Bid within 30 days after the actual date of the opening thereof. Should there be reasons why the Contract cannot be awarded within the specified period, the time may be extended by mutual agreement between the Contracting Agency and the Bidder.

The following information regarding Bonding requirements is applicable. Failure to comply as stated will result in a withdrawal of the contract:

Each bid must be accompanied by an executed Bid Bond from your firm's Surety, naming the Contracting Agency / Owner in the amount of five percent (5%) of the total amount of the submitted Bid. Bid Bonds will only be accepted, and no U.S. Cash or Cashier's Checks will be accepted in lieu of a fully executed surety issued bid bond.

A Performance Bond and a Labor and Material Payment Bond, each in the amount of 100 percent (100%) of the Contract Price (Base Bid plus Force Account Items), with a corporate surety approved by the Contracting Agency, will be required for the faithful performance of the Contract.

Attorneys-in-fact who sign Bid Bonds or Labor and Material Payment Bonds and Performance Bonds must file with each Bond a certified and effective dated copy of their Power of Attorney.

Each Bid must include the provided List of Subcontractors to be assisting in the project.

The party to whom the Contract is awarded will be required to execute the Agreement and obtain the Performance Bond and Labor and Material Payment Bond within fifteen (15) calendar days from the date when Notice of Award is delivered to the Bidder. The Notice of Award shall be accompanied by the necessary Agreement and Bond forms. In case the Bidder fails to execute the Agreement, the Contracting Agency reserves the right to exercise its option to consider the Bidder in default, in which case, the Bid Bond accompanying the Proposal shall become the property of the Contracting Agency.

Within fifteen (15) calendar days of receipt of acceptable Performance Bond, Labor and Material Payment Bond, proof of insurance, W9, any other required documents, and an Agreement signed by the party to whom the Agreement was awarded, the Contracting Agency shall sign the agreement and return to such party an executed duplicate of the Agreement. Should the Contract Agency not execute the Agreement within such period, the Bidder may, by Written

Durango Irrigation Raw Water Line Replacement #0014 Page 6 of 32 rev 8/5/2025

Notice, withdraw said signed Agreement. Such notice of withdrawal shall be effective upon receipt of the notice by the Contracting Agency.

The Contracting Agency shall issue the Notice to Proceed within ten (10) calendar days of the execution of the Agreement. Should there be reasons why the Notice to Proceed cannot be issued within such a period, the time may be extended by mutual agreement between the Contracting Agency and Contractor. If the Notice to Proceed has not been issued within the ten (10) calendar day period or within the period mutually agreed upon, the Contractor may terminate the Agreement without further liability on the part of either party.

Each Bidder shall demonstrate their experience in trades related to the work. At the time of the Bid, the Bidder shall provide to the Contracting Agency a list of at least three (3) successfully completed projects of a similar nature. Include the size and a description of each of the three projects. Include in each list the date, dollar amount of the project, and name of the responsible person for whom the work was done.

The Contracting Agency reserves the right to reject any or all Bids and to waive informalities when such action is deemed to be in the best interest of the Contracting Agency. A conditional or qualified Bid may be cause for rejection.

All applicable laws, ordinances, and the rules and regulations of all authorities having jurisdiction over the construction of the Projects shall apply to the Contract throughout.

Each Bidder is responsible for inspecting the site and for reading and being thoroughly familiar with the Contract Documents. The failure or omission of any Bidder to do any of the foregoing shall in no way relieve any Bidder from any obligation in respect to their Bid. For the purposes of this Invitation for Bids, the City of Durango shall be designated “City” and the successful Contractor shall be “Contractor.”

The City reserves the right to negotiate any and all elements of any proposal.

The successful bidder must provide all equipment and personnel necessary to perform the required services. This IFB includes a project description, scope of work, submission requirements, selection process and criteria, insurance requirements, and Sample Standard Form of Agreement between City and Contractor for Contractor Services Agreement. The Sample Agreement is for reference only and is non-negotiable.

Any bid that fails to conform to the essential requirements of the Invitation for Bids will be rejected.

a. Any bid that does not conform to the applicable specifications shall be rejected unless the invitation authorizes the submission of alternate bids and the items or services offered as alternates meet the requirements specified in the IFB.

b. Bid shall be rejected when the bidder imposes conditions that would modify requirements of the invitation or limit the bidder's liability to the Owner, since to allow the bidder to impose such conditions would be prejudicial to other bidders. For example, bids shall be rejected in which the bidder:

1. Protects against future changes in conditions, such as increased costs, and of total possible costs to the Owner cannot be determined

2. Fails to state a price and indicates that price shall be “price in effect at time of delivery”.

3. Takes exception to the IFB terms and conditions.

4. Inserts the bidder’s terms and conditions

Prospective firms are encouraged to carefully read this IFB in its entirety.

Durango Irrigation Raw Water Line Replacement #0014 Page 7 of 32 rev 8/5/2025

BIDDING TIMETABLE

Project Goals Due Dates

Projects 1st Publication August 6, 2025.

Projects 2nd Publication August 8, 2025.

Non-mandatory Pre-Bid Conference 1:00 p.m., August 19, 2025 (Local Time)

Location of Pre-Bid Schneider Park 950 Roosa Avenue Durango, CO 81301 (meet at existing pumphouse by river)

Contractor Questions Due August 27, 2025, 3:00 p.m. (Local Time)

Final Addendum Issued by Purchasing September 15, 2025, 3:00 p.m. (Local Time)

Bid Opening September 19, 2025, 3:00 p.m. (Local Time)

Notice of Award Estimated September 22, 2025.

Notice to Proceed Estimated October 3, 2025.

Project Commences Estimated October 6, 2025

Number of Construction Days T.B.D.

Project Completion December 31, 2025.

*Notice to Proceed will be given as soon as possible to initiate the procurement process for long-lead items.

Working days will not start counting until the beginning of construction on October 6, 2025.

III. SCOPE OF SERVICES

Introduction The City of Durango invites interested, qualified persons or firms capable of providing the required service to submit bids for improvements that generally consist of the installation of a 10” HDPE raw water irrigation line running from the existing pump shed at 950 Roosa Avenue to Greenmount Cemetery at 900 Cemetery Road.

Services provided by the Contractor will include but will not be limited to: raw water line installation, connection points 1 & 2 per plan, replacement of curb, gutter, and asphalt patching, tree protection as directed by COD, relocating fences along trench path, replacement of ART concrete panel, site rehabilitation, installation of irrigation stub valve, 3rd party testing, traffic control, and ensuring a clean and safe jobsite.

In addition to the above-mentioned work, the City of Durango is seeking quotes for the repaving of two of its parking lots affected by this project: Add Alt 1 - 10,000 SF Maintenance Shop Parking Lot and Add Alt 2 – 5,000 SF Schneider Park Parking Lot.

The Contractor shall furnish all labor, materials, tools, transportation, supplies, permits, and safety equipment needed to complete the work in accordance with the contract and the plans.

The intent is for the existing waterline to remain functional during the installation of the new line.

The construction plans and specifications are included as attachments to this invitation.

Durango Irrigation Raw Water Line Replacement #0014 Page 8 of 32 rev 8/5/2025

Project Schedule Schedule: This project is being scheduled outside of the irrigation season for the cemetery. Ideally, the project will start on October 6, 2025, and reach completion by December 31, 2025. Irrigation at the cemetery resumes April 1, 2026.

Standard Requirements All improvements must meet City of Durango standards and comply with the project's construction drawings and specifications. Specification documents include the City of Durango Parks & Recreation Irrigation and Landscape Standards and Tree Planting Details, and the City of Durango Development Standards for Public Improvements and Construction Specifications.

The selected Contractor shall include a proposed Project Manager. The Project Manager’s responsibilities shall include transmitting instructions, receiving information, and coordinating all matters arising pursuant to this contract during all phases of the construction of the project. The Project Manager shall be intimately familiar with the day-to-day construction of the project and the operational activities of the facility.

The selected Contractor shall perform construction services at a high level of proficiency, and be judged by a standard of care, that is consistent with the standards and quality prevailing among first-rate, nationally recognized construction management and general contracting firms of superior knowledge, skills, and experience engaged in projects of similar size and complexity. The selected Contractor shall carry out and complete the work in an efficient, economical, and timely manner, in accordance with the contract documents.

The selected Contractor shall be required to maintain accurate records of project progress and of any meetings and make appropriate distributions of these records if requested. Project construction progress meetings can be held at a frequency and in a manner of the Contractor’s preference. The selected Contractor shall also attend any on-call meeting that may be required by the City from time to time in connection with the construction, provided that the selected Contractor has at least 24 hours’ notice of such meeting.

The selected Contractor shall take reasonable precautions for the safety of its employees and others, and shall provide reasonable protection to prevent damage/injury or loss to its employees on the project, and others affected thereby, and the work, materials and equipment to be incorporated therein, whether in storage or off the site under care, custody or control of the Contractor team or its Subcontractors, or other property at the site or adjacent thereto including but not limited to trees, shrubs, lawns, walks, pavements, roadways, structures and utilities not designed for removal, relocation or replacement in the course of construction.

The Contractor will coordinate all contract activities and scheduling between the Contractor and sub-contractor(s), as well as ensure that the project work is completed on schedule and within budget. All work is ultimately the responsibility of the Contractor awarded the project. The oversight and quality control of any work completed by a subcontractor will also be the responsibility of the Contractor. The Contractor must make timely and complete payments to any subcontractors that are hired by the Contractor.

It is the Contractor's responsibility to immediately notify the City of any discrepancies between the work and the design plans. Additional work performed outside of the plans or specifications will not be paid for without prior approval from the City of Durango.

The schedule will need to be updated at a minimum on a weekly basis during construction, and a current schedule must be submitted with any pay request.

Prior to submitting a bid and again prior to starting construction, Bidders/Contractors should review the Project Special Provisions and General Conditions for further and more detailed information related to the project and the contract.

Durango Irrigation Raw Water Line Replacement #0014 Page 9 of 32 rev 8/5/2025

The Bid Schedule is included as an attachment to this invitation and must be completed and returned with the other bid documents. The Bid Schedule is in an Excel Spreadsheet format, and Bidders are encouraged to fill out and return the schedule digitally (it can be saved as either an XLS or PDF file type). Bidders may also print a hard copy of the schedule and return a scanned ( PDF) copy, completely filled in, with the other bid documents.

IV. INSURANCE

A. The Successful Contractor shall not commence work under this Agreement until it has obtained all insurance required by the contract documents and such insurance has been approved by the City. The Contractor shall not allow any subcontractor to commence work on this project until all similar insurance required of the subcontractor has been obtained and approved. For the duration of this Agreement, the Contractor must maintain the insurance coverage required in this section.

B. The Successful Contractor shall procure and maintain, at its own cost, the following policy or policies of insurance. The Contractor shall not be relieved of any liability, claims, demands, or other obligations assumed pursuant to the contract documents by reason of its failure to procure or maintain insurance or by reason of its failure to procure or maintain insurance in sufficient amounts, durations, or types.

C. Successful Contractor shall procure and maintain and shall cause each Subcontractor of the Contractor to procure and maintain (or shall insure the activity of Contractor’s Subcontractors in Contractor’s own policy with respect to), the minimum insurance coverages listed below. Such coverages shall be procured and maintained with forms and insurers acceptable to the City. All coverages shall be continuously maintained from the date of commencement of the Work. In the case of any claims-made policy, the necessary retroactive dates and extended reporting periods shall be procured to maintain such continuous coverage.

1. Worker’s Compensation insurance to cover obligations imposed by the Workers’ Compensation Act of Colorado and any other applicable laws for any employee engaged in the performance of Work under this contract, and Employers’ Liability insurance with minimum limits of One Million Dollars ($1,000,000) each accident, One Million Dollars ($1,000,000) – policy limit, and One Million Dollars ($1,000,000) disease – each employee.

2. Comprehensive General Liability insurance with minimum single limits of One Million Dollars ($1,000,000) each occurrence and Two Million Dollars ($2,000,000) aggregate. The policy shall be applicable to all premises and operations. The policy shall include coverage for bodily injury, broad form property damage (including completed operations), personal injury (including coverage for contractual and employee acts), blanket contractual, independent contractors, products, and completed operations. The policy shall include coverage for explosion, collapse, and underground hazards. The policy shall contain a severability of interest’s provision.

3. Comprehensive Automobile Liability insurance with minimum combined single limits for bodily injury and property damage of not less than Five Hundred Thousand Dollars ($500,000) each occurrence and One Million Dollars ($1,000,000) aggregate with respect to each of Contractor’s owned, hired and/or non-owned vehicles assigned to or used in performance of the services. The policy shall contain a severability of interest’s provision.

D. The policies required above, except for the Workers’ Compensation insurance and Employer’s Liability insurance, shall be endorsed to include the City, and its officers and employees, as additional insured. Every policy required above shall be primary insurance, and any insurance carried by the City, its officers, or its employees, shall be excess and not contributory insurance to that provided by Contractor. The additional insured endorsement for the Comprehensive General Liability insurance required above shall not contain any exclusion for bodily injury or

Durango Irrigation Raw Water Line Replacement #0014 Page 10 of 32 rev 8/5/2025 property damage arising from completed operations. The Contractor shall be solely responsible for any deductible losses under each of the policies required above.

E. Certificates of insurance shall be completed by the Contractor’s insurance agent as evidence that policies providing the required coverages, conditions, and minimum limits are in full force and effect, and copies of such certificates shall be forwarded to the City prior to start of Work. Each certificate shall identify the Project and shall provide that the coverages afforded under the policies shall not be cancelled, terminated, or materially changed until at least 30 days prior written notice has been given to the City. If the words “endeavor to” appear in the portion of the certificate addressing cancellation, those words shall be stricken from the certificate by the agent(s) completing the certificate.

The City reserves the right to request and receive a certified copy of any policy and any endorsement thereto.

F. Failure on the part of the Contractor to procure or maintain policies providing the required coverages, conditions, and minimum limits shall constitute a material breach of contract upon which the City may immediately terminate the contract, or at its discretion may procure or renew any such policy or any extended reporting period thereto and may pay any and all premiums in connection therewith, and all monies so paid by the City shall be repaid by the Contractor to the City upon demand, or the City may offset the cost of the premiums against any monies due to Contractor from the Owner.

V. BIDDER QUALIFICATIONS

In evaluating each bidder, consideration shall be made utilizing the following criteria. Deficiency in any of the areas listed below may be adequate cause for bid rejection.

A. The ability, capacity, and skill of the bidder to perform the contract or provide the service required. The quality of performance of previous contracts or services, either with the City or with other customers.

Bidder shall provide a separate representative list of the firm’s current and previous contracts, with the contract person's telephone number, related to the services requested.

B. The total cost of the service to the City of Durango

VI. BID SUBMISSION

One (1) electronic copy of each proposal shall be submitted and organized in the format indicated below. Electronic copies shall be submitted as a single .pdf file, labeled with the name of the firm. Proposals shall not exceed 20 pages in length. Page limit shall include all required submittals. Each side of each page containing text or images counts as one page. The minimum font size is 12. The City desires submittals that are clear, concise, and specific to the needs and conditions of this project.

1. All bids are to be submitted on the attached Bid sheet and Bid Schedule via: www.bidnetdirect.com/colorado.

They must be received by September 19, 2025, 3:00 P.M. (Local Time) prior to bid opening date and time.

Late bids will not be accepted.

2. Each contractor shall complete and include the following attached forms with each bid:

• List of Subcontractors

• Statement of Residency Form

3. Each Bid must be accompanied by a Bid Bond payable to the Contracting Agency for five percent (5%) of the total amount of the Bid.

4. Provide a brief company history or work record demonstrating the firm’s ability and experience to perform work complying with the scope of services and specifications in Special Provisions. Include a list of equipment to be used in performing the services required. Include at least three references with contact name, project performed, and telephone number. Attach a copy of any license or certification that is essential to your trade or craft.

Durango Irrigation Raw Water Line Replacement #0014 Page 11 of 32 rev 8/5/2025

All bids must be in compliance with all aspects of this bid package. Any exceptions to the specifications must be attached hereto and may be cause for bid rejection.

The successful Contractor must have or obtain a City Business License prior to the start of the project. The successful Contractor must also complete a W-9 form (Taxpayer Identification No.). The City of Durango is exempt from all local, state and federal taxes.

The City of Durango reserves the right to reject any and all bids and to waive informalities and minor irregularities in bids received and to accept any portion of the bid or all items proposed if deemed in the best interest of the City of Durango.

Durango Irrigation Raw Water Line Replacement #0014 Page 12 of 32 rev 8/5/2025

BID

Proposal of (hereinafter called "Bidder"), organized and existing under the laws of the State of , doing business as * to the City of Durango (hereinafter called "Contracting Agency").

In compliance with your Advertisement for Bids, Bidder hereby proposes to perform all work for the Durango Irrigation Raw Water Line Replacement in strict accordance with the Bid Documents, within the time set forth therein, and at the prices stated below.

By submission of this Bid, the Bidder certifies, and in the case of a joint Bid, each party thereto certifies as to their own organization, that this Bid has been arrived independently, without consultation, communication, or agreement as to any matter relating to this Bid with any other Bidder or with any competitor.

Bidder hereby agrees to commence work under this contract on or before a date to be specified in the Notice to Proceed and to fully complete the Project by December 31, 2025, or within TBD Calendar Days after the start of construction. Bidder further agrees to pay as liquidated damages, and not as a penalty, of $1500 per day for each consecutive working day thereafter as provided in the General Conditions.

The date of beginning and the time for completion of the work are essential conditions of the Contract Documents and the work embraced shall be commenced on the date specified in the Notice to Proceed.

• Bidder acknowledges receipt of the following Addendum:

ADDENDUM NUMBER DATE ACKNOWLEDGEMENT

Addendum No. 1 Addendum No. 2 Addendum No. 3 Addendum No. 4 Addendum No. 5

* Insert "a Corporation", "a Partnership", "an Individual", as applicable.

Bidder agrees to perform all work described and contained in the bid documents for the unit prices or lump sums as shown on the Bid Schedule for the Project. Bidder acknowledges that quantities are estimated and are only for the purpose of comparing bids.

Bidder acknowledges that payment will be based on the lump sum price or the actual quantities furnished, installed, or constructed as provided for in the bid documents and approved by the City of Durango.

If applicable, bidder acknowledges that the cost of a 100% Performance and Payment Bond is included in the foregoing Bid and agrees to furnish said Bond in the amount of the Bid items plus all force account items specified by an asterisk in the Forced Account Project Special Provisions, with a Surety Company satisfactory to the Owner at the time of execution of the Agreement or a suitable Letter of Intent.

Signature: ________________________________________________________

Print Name & Title: ________________________________________________

Email: ____________________________________________________________________

Company: ____________________________________________________________

Durango Irrigation Raw Water Line Replacement #0014 Page 13 of 32 rev 8/5/2025

Address: ________________________________________________________

Telephone: ______________________________________________________

FAX: ___________________________________________________________

City of Durango Business License No. _____________________

(SEAL) - If bid is by a corporation

ATTEST:

Name: ______________________________________

(Please type)

Title: _______________________________________

Durango Irrigation Raw Water Line Replacement #0014 Page 14 of 32 rev 8/5/2025

LIST OF SUBCONTRACTORS

Contractor _____________________________________________________________

1. Subcontractor Name: Specialty: Phone:

Address: Percentage of Contract:

Email:

2. Subcontractor Name: Specialty: Phone:

3. Subcontractor Name: Specialty: Phone:

4. Subcontractor Name: Specialty: Phone:

5. Subcontractor Name: Specialty: Phone:

6. Subcontractor Name: Specialty: Phone:

7. Subcontractor Name: Specialty: Phone:

Attach additional pages if needed

Durango Irrigation Raw Water Line Replacement #0014 Page 15 of 32 rev 8/5/2025

STATEMENT OF RESIDENCY – CITY OF DURANGO

PROJECT – Durango Irrigation Raw Water Line Replacement

As a condition precedent to the award to me, or us, of a contract by the City of Durango for the products or services related to the above-listed project, I, ______________________________, as the individual owner, partner, manager, officer, or person delegated to sign this form, do hereby certify that the firm named below is a:

(Check one only) Local Bidder (La Plata County) Regional Bidder (Region 9 of Colorado) Non-resident Bidder Local Bidder* means:

A local bidder is defined as a person, partnership, corporation, limited liability company, or joint venture that is authorized to transact business in Colorado and that maintains a business office within La Plata County.

Regional Bidder** means:

A person, partnership, corporation, or joint venture that is authorized to transact business in Colorado and maintains a business office within Region 9 of Colorado.

Non-resident Bidder: Location (City/State) ____________________________________

I, ______________________________, declare under penalty of perjury that the statements made in this document are true and complete to the best of my knowledge.

(Insert name of corporation, limited Firm Name:

liability company, partnership or sole proprietorship)

(insert trade name or name under doing business as ____________ ____________ which corporation, company, partnership or proprietorship is doing business, if different from legal name of entity or proprietor) By:

Signature

Title

Date

* Local bidders shall receive a 5% preference over all bidders or $100,000, whichever is less. In no event shall the local bidder preference exceed the amount of $100,000.

** Regional Bidders will receive a 3% preference over Non-Resident Bidders or $40,000, whichever is less. In no event shall the regional bidder preference exceed the amount of $40,000.

Durango Irrigation Raw Water Line Replacement #0014 Page 16 of 32 rev 8/5/2025

NOTICE OF AWARD

City of Durango, Colorado

Date________

CONTRACTOR’S NAME

Re: Durango Irrigation Raw Water Line Replacement

Dear CONTRACTOR:

You are hereby notified that the City of Durango has accepted your bid for the above-referenced project in the amount of $00.00.Within fifteen (15) calendar days, you are required to provide the following items to the Financial Services Department, via Email bob.grogan@durangoco.gov or mail 949 East 2nd Avenue, Durango, CO 81301:

a. Executed Agreement/Contract (2 originals);

b. Certificate of Insurance NAMING THE CITY OF DURANGO and which contains a Notice of

Cancellation clause which is absolute and does not contain language such as “endeavor to” notify or “failure to mail such notice shall impose no obligation or liability of any kind upon the company, its agents or representatives.” If a standard certificate is used with such language crossed out, the representative shall initial and date said deletions.

c. Payment and Performance bonds, if required by Request for Proposal/Invitation to Bid;

d. Proof of Workers’ Compensation coverage.

e. Executed Acceptance of Notice of Award (Page 2 of this Notice of Award); and

f. Completed W-9.

g. City of Durango Business License

If you fail to return the above-described items within fifteen (15) calendar days from the date of this Notice, the City of Durango will be entitled to consider all your rights arising out of the acceptance of your bid as abandoned and as a forfeiture of your Bid Bond. The City of Durango will be entitled to such other rights as may be granted by law.

Sincerely, Bob Grogan Financial Services Department mailto:bob.grogan@durangoco.gov

Durango Irrigation Raw Water Line Replacement #0014 Page 17 of 32 rev 8/5/2025

ACCEPTANCE OF NOTICE OF AWARD

Receipt of the Notice of Award is hereby acknowledged on this ____ day of __________, 2025.

By __________________________________________________________________

Signature __________________________________________________________________

Title __________________________________________________________________

Company __________________________________________________________________

Please execute and return this form with the contracts, bonds, Certificates of Insurance, required licenses, and completed W-9 by email to purchasing@durangoco.gov or in one envelope to:

City of Durango

Financial Services Department 949 East 2nd Avenue Durango CO 81303 mailto:purchasing@durangoco.gov

Durango Irrigation Raw Water Line Replacement #0014 Page 18 of 32 rev 8/5/2025

949 E 2nd AVENUE

DURANGO CO 81301

STANDARD FORM OF AGREEMENT

BETWEEN

CITY AND CONTRACTOR

FOR

CONSTRUCTION SERVICES

AGREEMENT

Made as of the _______ day of _______________________ in the year 2025

BETWEEN the City: City of Durango 949 E 2nd Avenue Durango CO 81301

And the Contractor:

For the following Project: Durango Irrigation Raw Water Line Replacement

Durango Irrigation Raw Water Line Replacement #0014 Page 19 of 32 rev 8/5/2025

PART 1

CONTRACT DOCUMENTS

1.1 The Contract Documents consist of the following:

(a) This Agreement;

(b) The Invitation for Bids, and all addenda and attachments;

(c) The Contractor’s Bid;

(d) Information for Bidders, if applicable;

(e) City of Durango General Conditions and Standard Specifications, if applicable;

(f) Special Provisions;

(g) Other documents, plans, or drawings listed in the Invitation for Bids;

(h) Notice of Award;

(i) Acceptance of Notice of Award;

(j) Notice to Proceed;

(k) Statement of Residency;

(l) Change Orders, and

(m) Modifications issued after execution of the Agreement

1.2 All of the above-listed Contract Documents are incorporated by reference as though set forth in full herein, whether or not attached hereto, and shall form an integral part of this Agreement. If there is any conflict between this Agreement and the other Contract Documents, the specifications, terms and conditions indicated in the Invitation for Bids, Request for Proposals, or Request for Professional Services shall control.

1.3 The Contract Documents represent the entire and integrated agreement between the parties hereto and supersede any and all prior negotiations, representations or agreements, either written or oral. Except as provided herein, this Contract may not be modified or amended except by written agreement signed by the parties.

1.4 The Agreement is this executed Standard Form of Agreement between City and Contractor.

PART 2

CONTRACT SUM

2.1 The City shall pay the Contractor, in current funds, for the Contractor’s performance of the

Contract in the total lump sum amount of $____________, subject to additions and deductions as provided in the Contract Documents.

Durango Irrigation Raw Water Line Replacement #0014 Page 20 of 32 rev 8/5/2025

2.2 Based upon Invoices submitted by the Contractor, the City shall make payments to the Contractor for actual work performed. Invoices shall indicate a description of the work performed and percentage completion, as specified in the Contract Documents. All payments shall be paid no later than thirty (30) days from the receipt of invoice.

2.3 Payment terms will be set at Thirty (30) days from project manager acceptance of monthly pay application.

2.4 Retainage. The amount to be retained from payments shall be five (5) percent of the value of the completed work, exclusive of payments for materials on hand, but not greater than two and half (2.5) percent of the amount of the contract. When the retainage has reached two and half (2.5) percent of the amount of the contract, no further retainage will be made, and this amount will be retained until such time as final payment is made. If applicable, the Contractor shall make payments to its subcontractors in accordance with C.R.S. Section 24-91-103.

2.5 The appropriated funds for this project are equal to or exceed the amount of the contract stated in

Paragraph 4. Pursuant to C.R.S. § 24-91-103.6(2), any change order or change directive requiring additional compensable work to be performed which work causes the aggregate amount available under the contract to exceed the amount appropriated for the original contract shall be agreed to in writing, signed by both parties and shall assure that the City has made lawful appropriations to cover the costs of the additional work. Any change order or directive made by the City requiring additional compensable work to be performed shall be performed at the hourly rates and/or unit pricing set forth in the contractor’s bid and shall be reimbursed at the contractor's costs on a monthly basis for all additional directed work performed until a change order is finalized. However, in no instance shall the periodic reimbursement be required before the contractor has submitted an estimate of cost to the City for the additional compensable work to be performed.

PART 3

SCOPE OF SERVICES

3.1 The Contractor shall execute the entire Scope of Services described in the Bid Documents dated __________, any Addenda issued, and the Contractor’s Bid, submitted __________, except to the extent specifically indicated in the Contract Documents to be the responsibility of others.

PART 4

CITY’S RESPONSIBILITIES

4.1 The City shall provide full information regarding requirements for the Work to be performed.

4.2 The City shall designate, when necessary, a representative authorized to act on the City’s behalf with respect to the Project or Project Documents.

Durango Irrigation Raw Water Line Replacement #0014 Page 21 of 32 rev 8/5/2025

4.3 The City shall furnish required information as expeditiously as necessary for the orderly progress of the Work, and the Contractor shall be entitled to rely upon the accuracy and completeness thereof.

PART 5

DATE OF COMMENCEMENT

5.1 The date of commencement is the date of this Agreement, as first written above, unless a different date is stated below, or provision is made for the date to be fixed in a notice to proceed issued by the City.

PART 6

CONTRACTOR’S PROJECT SCHEDULE

6.1 The Contractor shall provide a Critical Path Method (CPM) schedule (“Project Schedule”) covering the duration of the Work, beginning with the receipt of the signed Agreement and concluding with Substantial Completion. The following requirements must be met:

(a) The Project Schedule shall include design, engineering, agency review, permitting process, construction, and anticipated weather days.

(b) The Project Schedule shall contain a sufficient number of activities to allow effective monitoring of the progress of the Work. Each activity shall contain only the Work of a single trade or subcontractor.

(c) Each activity shall be less than ten (10) working days in duration. Procurement and material delivery, surveying, and shop drawing approvals may exceed ten (10) working days in duration. Activities exceeding 10 working days in duration shall be separated into two or more individual activities by area, type of work, etc., to allow for effective monitoring of the Work.

(d) Each activity shall be cost-loaded. The sum of all cost-loaded activities shall be equal to the Contract Price. Any costs associated with drawings or submittals shall be included in the cost loading of the Work.

(e) The Project Schedule must include activities that indicate work by others that may affect the Contractor’s Work.

6.2 Adverse Weather Conditions. Extensions of time based upon weather conditions shall be granted only if the Contractor clearly demonstrates that such conditions were severe, could not have been reasonably anticipated, and that such conditions adversely affect the Contractor’s Work and thus require additional time to complete the Work.

6.2.1 An adverse weather day must prevent Work for 50 percent or more of the Contractor’s workday, delay Work critical to the timely completion of the Project, and be documented by the Contractor and provided to the City within two calendar days. The City will use the written notification in determining the number of calendar days for which Work was delayed during each month.

6.2.2 The Project Schedule must reflect anticipated adverse weather delays on all weather-dependent activities. While extensions of time can be granted for adverse weather as

Durango Irrigation Raw Water Line Replacement #0014 Page 22 of 32 rev 8/5/2025 described above, no monetary compensation shall be made by the City for any costs to the Contractor arising out of such delays.

6.3 Contractor shall update the Project Schedule on a monthly basis and review with the City on a weekly basis at the weekly progress meeting. Each revision shall indicate actual progress to date, changes resulting from change orders, and planned changes, as necessary to complete the Work in accordance with the Contract Documents.

6.4 All costs associated with the development and maintenance of the Project Schedule shall be borne by the Contractor.

PART 7

TIME FOR COMPLETION AND LIQUIDATED DAMAGES

7.1 The date of beginning and the time for completion of the work are essential conditions of the Contract

Documents, and the work embraced shall be commenced on the date specified in the Notice to Proceed.

7.2 The Contractor will proceed with the work at such a rate or progress to ensure full completion within the Contract time. It is expressly understood and agreed, by and between the Contractor and the Contracting Agency, that the contract time for the completion of the work described herein is a reasonable time, taking into consideration the average climatic and economic conditions and other factors prevailing in the locality of the work.

7.3 Should the Contractor fail to complete the work within the Contract time, or extension of time granted by the Contracting Agency, the Contractor shall pay the Contracting Agency the amount of liquidated damages as specified in the Bid Documents for each calendar day the Contractor may be in default of the time stipulated in the Contract Documents.

7.3.1 The Contractor shall not be charged with liquidated damages provided the delay in completion of the work is due to the following and the Contractor has promptly given written notice of such delay to the Contracting Agency or Engineer.

7.3.1.1 To any preference, priority or allocation order duly assigned by the Contracting

Agency.

7.3.1.2 To unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to, acts of God, or of the public enemy, acts of omission of the Contracting Agency, floods, epidemics, quarantine restrictions, strikes, material or fuel shortages due to governmental regulations or allocations, freight embargoes and abnormal or unusually severe weather.

7.3.1.3 Permitting the Contractor to continue and finish the work or any part of it after the time fixed for its completion, or after the date to which the time fixed for its completion may have been extended, will in no way operate as a waiver on the part of the Contracting Agency of any of its rights under the Contract.

Durango Irrigation Raw Water Line Replacement #0014 Page 23 of 32 rev 8/5/2025

PART 8

FINAL INSPECTION AND FINAL PAYMENT

8.1 Final Inspection. The Contractor shall notify the City when the Work is complete and ready for final inspection by means of a letter of completion. Within ten (10) working days thereafter, the City shall make a final inspection to determine whether the Work has been completed in accordance with the Contract Documents and shall submit a written list of any defects to the Contractor.

This is the start of the file's text. The full file is on GovTribe.