About this file

Draft Solicitation. Final shall be posted before pre-proposal conference.

View the file

Other files

File Type Posted
Amendment_1.pdf PDF
Revised_Exhibit_1-_4-15-16.pdf PDF
Exhibit_2_-_4-15-16.pdf PDF
Q_ A_DU100R-16-R-0001_4-15-16.pdf PDF
Revised__PWS_4-15-16.pdf PDF
List_of_Attendes.pdf PDF
DU100R-16-R-0001_Amen_2.pdf PDF
Revised_Exhibit_3_-_4-15-16.pdf PDF
ATTACHMENT_6_-_PRICING_SHEET_4-16-16.xlsx XLSX spreadsheet
Pre-Prosal_Conference_Single_Family_Supplemental_Claims_PowerPoint__Presentation_3-9-16_(final).pptx PPTX presentation
Attachment_4_Past_Performance_Survey.docx DOCX document
Exhibit_I.pdf PDF
Exhibit_2.pdf PDF
DU100R-16-R-0001.pdf PDF
Attachment_3_Past_Performance_Information.docx DOCX document
Attachment_5_Non-Disclosure_Form.doc DOC document
Exhibit_3.pdf PDF
Revised_PWS_2-19.pdf PDF
ATTACHMENT_3_-_PRICING_SHEET.xlsx XLSX spreadsheet
Attachment_6_Non-Disclosure_Form.doc DOC document
Attachment_5_Past_Performance_Survey.docx DOCX document
Exhibit_2.pdf PDF
Exhibit_3.pdf PDF
Attachment_4_Past_Performance_Information.docx DOCX document
Eshibit_I.pdf PDF
PWS.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUMIS CHECKED

CODE 18a. PAYMENT WILL BE MADE BY

CODE

FACILITYCODE

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER

OFFEROR

HUD-NPR

WASHINGTON DC 20410-1000

451 SEVENTH STREET SW

OFFICER

OFFICE OF THE CHIEF PROCUREMENT

US DEPARTMENT OF HUD

CODE 16. ADMINISTERED BYCODE

X

X

X

541211

SIZE STANDARD:

% FOR:SET ASIDE:UNRESTRICTED ORHUD-NPR

RFPIFB

10. THIS ACQUISITION ISCODE

RFQ

14. METHOD OF SOLICITATION

13b. RATING

SMALL BUSINESS

02/29/2016 1400 ET

01/15/2016

SARAH HEYWARD

(No collect calls)

INFORMATION CALL:

FOR SOLICITATION 8. OFFER DUE DATE/LOCAL TIMEb. TELEPHONE NUMBER a. NAME

4. ORDER NUMBER3. AWARD/ 6. SOLICITATION

DU100R-16-R-0001

5. SOLICITATION NUMBER

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS 1. REQUISITION NUMBER PAGE OF

1 2 OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

ROOM 5256

TELEPHONE NO.

17a. CONTRACTOR/

TO ALL OFFERORS-DRAFT SOLICITATION

15. DELIVER TO

WASHINGTON DC 20410-1000

ROOM 5256

451 SEVENTH STREET SW

OFFICER

OFFICE OF THE CHIEF PROCUREMENT

9. ISSUED BY

7.

2. CONTRACT NO.

EFFECTIVE DATE

$20.5

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW

ISSUE DATE

DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

11.

SEE SCHEDULE

12. DISCOUNT TERMS

THIS CONTRACT IS A

RATED ORDER UNDER

DPAS (15 CFR 700)

13a.

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

HUBZONE SMALL

BUSINESS

8(A)

WOMEN-OWNED SMALL BUSINESS

(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

US DEPARTMENT OF HUD

EDWOSB

NAICS:

24.

AMOUNT

23.

UNIT PRICE

22.

UNIT

21.

QUANTITY

20.

SCHEDULE OF SUPPLIES/SERVICES

19.

ITEM NO.

Title: Single Family Supplemental Claims Processing, Business Process Improvement and Property Disposition Support Services

(Use Reverse and/or Attach Additional Sheets as Necessary)

HEREIN, IS ACCEPTED AS TO ITEMS:

X

XX

DATED

BRENDA K. LEE

. YOUR OFFER ON SOLICITATION (BLOCK 5),

INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER

ARE

ARE

31c. DATE SIGNED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print)

ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL

SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA

26. TOTAL AWARD AMOUNT (For Govt. Use Only)

OFFER

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA - FAR (48 CFR) 53.212

ARE NOT ATTACHED.

ARE NOT ATTACHED.

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

30b. NAME AND TITLE OF SIGNER (Type or print)

30a. SIGNATURE OF OFFEROR/CONTRACTOR

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

25. ACCOUNTING AND APPROPRIATION DATA

29. AWARD OF CONTRACT:

REF.

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32c. DATE 32b. SIGNATURE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

40. PAID BY39. S/R VOUCHER NUMBER38. S/R ACCOUNT NUMBER

37. CHECK NUMBER

FINALPARTIAL

36. PAYMENT

FINALPARTIAL

35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER33. SHIP NUMBER

COMPLETE

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

42d. TOTAL CONTAINERS42c. DATE REC'D (YY/MM/DD)

42b. RECEIVED AT (Location)

42a. RECEIVED BY (Print)

41c. DATE41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

STANDARD FORM 1449 (REV. 2/2012) BACK

24.

AMOUNT

23.

UNIT PRICE

22.

UNIT

21.

QUANTITY

20.

SCHEDULE OF SUPPLIES/SERVICES

19.

ITEM NO.

32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

2 2 of

CONTINUATION OF BLOCK 20 FOR SCHEDULE OF SUPPLIES/SERVICES OF THE

SECTION I SCHEDULE OF SUPPLIES OR SERVICE

(1). Brief Description of Supplies or Services

The U.S. Department of Housing and Urban Development, Office of The Single Family Post Insurance Division (SFPID) need support services to provide business process improvement, control and risk-based process of supplemental claims, and to review, verify and key data into the Single Family Acquired Assets Management System (SAMS/A80S) and provide support to the Homeownership Centers (HOCs) and Headquarters staff.

(2) Contract Type

The is a fixed price contract, total small business set-aside with a twelve month base period plus 4 one year option periods utilizing FAR Part 19.502-2 and FAR Part 12 Acquisition of Commercial Items.

This is a single award to provide a business process for the supplemental claims process and assist HUD’s transition into a paperless and risk-based operation.

(3) Description/Specifications

Performance Work Statement (PWS) Title: Single Family Supplemental Claims Processing, Business Process Improvement & Property Disposition Support Services see Section Attachment 1, Performance Work Statement.

(4) Pricing

Each month the contractor shall process, at a minimum of 4000 claims of the supplemental claims for forward mortgage. The Contractor shall be paid a fixed unit price per lot 4000 monthly. If the contractor does not process the entire 400 claims monthly, the contractor shall not be paid until the completion of each lot is processed. No partial payment shall be authorized for this contract.

Each month the contractor shall process at a minimum of 420 claims of the HERMIT Supplemental Claims for Reverse Mortgages – Claim (Type 24). The Contractor shall be paid a fixed unit price per lot 420 per month. If the contractor does not process the entire 420 claims monthly, the contractor shall not be paid until the completion of each lot is process. No partial payment shall be authorized for this contract.

The Optional Line item shall be exercised, if a need for increase, to the quantities stated in the contract utilizing the established price for each line item and period in the contract.

(5) Period of Performance

The period of performance is a twelve month base period with four 12 month option periods.

(6) Place of Performance

The services to be performed under this contract shall be performed at the Contractor facility with the exception of Task 5.1.1.5, which shall be performed at HUD Headquarters located at 451 7th Street, SW, Washington, DC 20410. If the Contractor office space is not large enough to store at least 5.000 government storage box files worth of records, Contractor shall obtain an additional storage facility which is easily accessible in order to retrieve records when requested.

(7) Inspection and Acceptance

HUDAR 2452.246-70 Inspection and Acceptance (Feb 2006)

Inspection and acceptance of all work required under this contract shall be performed by the Government Technical Representative (GTR) or other individual as designated by the Contracting Officer.

(8) Packaging, Marking Deliveries

a. All deliverables required under this contract shall be packaged, marked and shipped in accordance with Government specifications. At a minimum, all deliverables shall be marked with the contract number and contractor name. The Contractor shall guarantee that all required materials shall be delivered in immediate usable and acceptable condition.

b. Deliveries required by the Contractor shall be made F.O.B. Destination as set forth in FAR Clause 52.247-35, F.O.B. Destination, Within consignees Premises (April 1984) and any specification stated in PACKAGING AND MARKING AND SHIPPING.

c. Unless otherwise specified, deliveries shall be made to the Delivery Point specified in each tasks order Mondays through Fridays (excluding Federal Holidays & Executive Order) between the hours of 8:30 a.m. and 5:30 p.m.(local time). Supplies or services scheduled for delivery on a Federal holiday shall be made the following day.

SECTION II CONTRACT CLAUSES

(1) FAR 52.212-4 CONTRACT TERMS AND CONDITIONS -- COMMERCIAL ITEMS.

(May 2015)

(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights --

(1) Within a reasonable time after the defect was discovered or should have been discovered; and

(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C.3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.

(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.

(d) Disputes. This contract is subject to 41 U.S.C. chapter 71,Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at FAR 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.

(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.

(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.

(g) Invoice.

(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include

(i) Name and address of the Contractor;

(ii) Invoice date and number;

(iii) Contract number, contract line item number and, if applicable, the order number;

(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;

(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;

(vi) Terms of any discount for prompt payment offered;

(vii) Name and address of official to whom payment is to be sent;

(viii) Name, title, and phone number of person to notify in event of defective invoice; and

(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.

(x) Electronic funds transfer (EFT) banking information.

(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.

(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer— System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer—Other Than System for Award Management), or applicable agency procedures.

(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.

(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C.

3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.

(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.

(i) Payment.

(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.

(2) Prompt Payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR Part 1315.

(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.

(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.

(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—

(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—

(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);

(B) Affected contract number and delivery order number, if applicable;

(C) Affected contract line item or subline item, if applicable; and

(D) Contractor point of contact.

(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.

(6) Interest.

(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period at fixed by the Secretary until the amount is paid.

(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.

(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if—

(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;

(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or

(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).

(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.

(v) Amounts shall be due at the earliest of the following dates:

(A) The date fixed under this contract.

(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.

(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—

(A) The date on which the designated office receives payment from the Contractor;

(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or

(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.

(vii) The interest charge made under this clause may be reduced under the procedures prescribed in 32.608-2 of the Federal Acquisition Regulation in effect on the date of this contract.

(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:

(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or

(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.

(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.

(l) Termination for the Government’s convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor’s records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.

(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law.

If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.

(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.

(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.

(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.

(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 41 U.S.C. 4712 and 10 U.S.C. 2409 relating to whistleblower protections; 49 U.S.C. 40118, Fly American; and 41 U.S.C. chapter 21 relating to procurement integrity.

(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:

(1) The schedule of supplies/services.

(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause.

(3) The clause at 52.212-5.

(4) Addenda to this solicitation or contract, including any license agreements for computer software.

(5) Solicitation provisions if this is a solicitation.

(6) Other paragraphs of this clause.

(7) The Standard Form 1449.

(8) Other documents, exhibits, and attachments.

(9) The specification.

(t) System for Award Management (SAM).

(1) Unless exempted by an addendum to this contract, the Contractor is responsible during performance and through final payment of any contract for the accuracy and completeness of the data within the SAM database, and for any liability resulting from the Government’s reliance on inaccurate or incomplete data. To remain registered in the SAM database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the SAM database to ensure it is current, accurate and complete. Updating information in the SAM does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.

(2)

(i) If a Contractor has legally changed its business name, “doing business as” name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in Subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day’s written notification of its intention to:

(A) Change the name in the SAM database;

(B) Comply with the requirements of Subpart 42.12 of the FAR;

(C) Agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.

(ii) If the Contractor fails to comply with the requirements of paragraph (t)(2)(i) of this clause, or fails to perform the agreement at paragraph (t)(2)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the SAM information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the “Suspension of Payment” paragraph of the electronic funds transfer (EFT) clause of this contract.

(3) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the SAM record to reflect an assignee for the purpose of assignment of claims (see FAR Subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the SAM database. Information provided to the Contractor’s SAM record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the “Suspension of payment” paragraph of the EFT clause of this contract.

(4) Offerors and Contractors may obtain information on registration and annual confirmation requirements via SAM accessed through https://www.acquisition.gov.

(u) Unauthorized Obligations.

(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End Use License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:

(i) Any such clause is unenforceable against the Government.

(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an “I agree” click box or other comparable mechanism (e.g., “click- wrap” or “browse-wrap” agreements), execution does not bind the Government or any Government authorized end user to such clause.

(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.

(2) Paragraph (u) (1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.

(v) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.

(End of Clause)

(2) ADDENDUM TO 52.212-4; AND ADDITIONAL CONTRACT CLAUSES

(a) HUDAR 2452.232-70 PAYMENT SCHEDULE AND INVOICE SUBMISSION (FIXED-PRICE (DEC 2012) Alternate II (Deviation May 2015)

(a) Payment Schedule. Payment of the contract price (see Attachment 3 Pricing Sheet of the solicitation) will be made “Schedule of Charges” upon completion and acceptance of all work.

The contractor shall submit invoices electronically via email to the email addresses shown on the contract award document (e.g., block 12 of the Standard Form (SF) 26, block 25 of the SF-33, or block 18a of the SF-1449) and carbon copy the Contracting Officer and the Government Technical Representative (GTR). To constitute a proper invoice, the invoice must include all items required by the FAR clause at 52.232-25, “Prompt Payment.” The contractor shall clearly include in the Subject line of the email: INVOICE INCLUDED; CONTRACT/ORDER #:

_______________, INVOICE NUMBER _______________ and Contract Line Item Number(s)

(b) Submission of Invoices.

(1) The Contractor shall obtain access and submit invoices to the Department of Treasury Bureau of Fiscal Services’ Invoice Platform Processing System via the Web at URL:

https://arc.publicdebt.treas.gov/ipp/fsippqrg.htm https://arc.publicdebt.treas.gov/ipp/fsippqrg.htm in accordance with the instructions on the Web site. To constitute a proper invoice, the invoice must include all items required by the FAR clause at 52.232-25, "Prompt Payment."

(2) To assist the government in making timely payments, the contractor is also requested to include on each invoice the appropriation number shown on the contract award document (e.g., block 14 of the Standard Form (SF) 26, block 21 of the SF-33, or block 25 of the SF-1449).

(End of Alternate II)

(b) HUDAR 2452.237-70 KEY PERSONNEL (FEB 2006)

(a) Definition. "Personnel" mean employees of the contractor, or any subcontractor(s), affiliates, joint venture partners, or team members, and consultants engaged by any of those entities.

(b) The personnel specified below are considered to be essential to the work being performed under this contract. Prior to diverting any of the specified individuals to other projects, the contractor shall notify the Contracting Officer reasonably in advance and shall submit justification (including proposed substitutions) in sufficient detail to permit evaluation of the impact on the program. No diversion shall be made by the contractor without the written consent of the Contracting Officer. Key personnel shall perform as follows:

[List Key Personnel and/or positions, and tasks, percentage of effort, number of hours, etc., for which they are responsible, as applicable.]

(c) HUDAR 2452.237-73 CONDUCT OF WORK AND TECHNICAL GUIDANCE (DEC 2012)

(a) The Contracting Officer will provide the contractor with the name and contact information of the Government Technical Representative (GTR) assigned to this contract.

The GTR will serve as the contractor's liaison with the Contracting Officer with regard to the conduct of work. The Contracting Officer will notify the contractor in writing of any change to the current GTR's status or the designation of a successor GTR.

(b) The GTR will provide guidance to the contractor on the technical performance of the contract. Such guidance shall not be of a nature which:

(1) causes the contractor to perform work outside the performance work statement or specifications of the contract;

(2) Constitutes a change as defined in FAR 52.243-1;

Name Title Task % of Effort

(3) Causes an increase or decrease in the cost of the contract;

(4) Alters the period of performance or delivery dates; or

(5) Changes any of the other express terms or conditions of the contract.

(c) The GTR will issue technical guidance in writing or, if issued orally, he/she will confirm such direction in writing within five calendar days after oral issuance. The GTR may issue such guidance via telephone, facsimile (fax), or electronic mail.

(d) Certain of the GTR's duties and responsibilities may be delegated to one or more Government Technical Monitors (GTMs) (see HUDAR subpart 2402.1). The Contracting Officer will notify the contractor in writing of the appointment of any GTMs.

(e) Other specific limitations None:

(f) The contractor shall promptly notify the Contracting Officer whenever the contractor believes that guidance provided by any government personnel, whether or not specifically provided pursuant to this clause, is of a nature described in paragraph (b) above

(d) FAR 52.217-8 OPTION TO EXTEND SERVICES. (Nov 1999)

The Government may require continued performance of any services within the limits and at the rates specified in the contract. These rates may be adjusted only as a result of revisions to prevailing labor rates provided by the Secretary of Labor. The option provision may be exercised more than once, but the total extension of performance hereunder shall not exceed 6 months. The Contracting Officer may exercise the option by written notice to the Contractor no later than 10 days prior to the expiration of the contract.

(e) FAR 52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (Mar 2000)

(a) The Government may extend the term of this contract by written notice to the Contractor within 30 days; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 60 days before the contract expires. The preliminary notice does not commit the Government to an extension.

(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.

(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed the period of time set in the Schedule except that extensions pursuant to FAR 52.217-8 permit the duration to extend up to 6 months beyond the stated limit.

(f) FAR CLAUSE 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these addresses:

http://www.hud.gov http://www.hud.gov/offices/cpo/hudar.cfm http://www.arnet.gov/far/loadmainre.html

(End of clause)

FAR CLAUSE 52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE

(NOV 2011)

FAR CLAUSE 52.227-14 RIGHTS IN DATA—GENERAL

FAR CLAUSE 52.227-16 ADDITIONAL DATA REQUIREMENTS

FAR CLAUSE 52.227-19 COMMERCIAL COMPUTER SOFTWARE LICENSE DEC

FAR CLAUSE 52.224-2 PRIVACY ACT. (APR 1984)

FAR CLAUSE 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS

(JUL 2013)

FAR CLAUSE 52.209-5 CERTIFICATION REGARDING RESPONSIBILITY MATTERS

(Apr 2010) FAR CLAUSE 52.237-3 CONTINUITY OF SERVICES (Jan 1991) FAR CLAUSE 52.245-1 GOVERNMENT PROPERTY (Apr 2012) FAR CLAUSE 52.233-2 SERVICE OF PROTESTS (Sept 2006)

FAR CLAUSE 52.239-1 PRIVACY OR SECURITY SAFEGUARDS. (AUG 1996)

FAR CLAUSE 52.242-15 STOP-WORK ORDER. (AUG 1989)

FAR CLAUSE 52.242-14 SUSPENSION OF WORK (APR 1984)

(End of clause)

(g) U.S. DEPARTMENT OF DEPARTMENT OF HOUSING AND URBAN

DEVELOPMENT ACQUISITION REGULATION (HUDAR) 48 CFR CLAUSES.

(1) HUDAR 2452.203-70 PROHIBITION AGAINST THE USE OF FEDERAL

EMPLOYEES (FEB 2006)

In accordance with Federal Acquisition Regulation 3.601, contracts are not to be awarded to government employees or a business concern or other organization owned or substantially owned or controlled by one or more government employees. For the purposes of this contract, this prohibition against the use of government employees includes any work performed by the contractor or any of its employees, subcontractors, or consultants.

(End of clause)

(2) HUDAR 2452.204-70 PRESERVATION OF, AND ACCESS TO, CONTRACT

RECORDS (TANGIBLE AND ELECTRONICALLY STORED INFORMATION (ESI)

FORMATS. (DEC 2012)

Contract records means information created or maintained by the contractor in the performance of the contract. Contract records include documents required to be retained in accordance with FAR 4.703 and other information generated or maintained by the contractor that is pertinent to the contract and its performance including, but not limited to: email and attachments, formal and informal correspondence, calendars, notes, reports, memoranda, spreadsheets, tables, telephone logs, forms, survey, books, papers, photographs, drawings, machine-readable materials, and data. Contract records may be maintained as electronically stored information or as tangible materials. Contract records may exist in either final or any interim version (e.g., drafts that have been circulated for official purposes and contain unique information, such as notes, edits, comments, or highlighting). Contract records may be located or stored on the contractor's premises or at off-site locations.

Electronically stored information (ESI) means any contract records that are stored on, or generated by, an electronic device, or contained in electronically accessible media, either owned by the contractor, subcontractor(s), or employees of the contractor or subcontractor(s) regardless of the physical location of the device or media (e.g., offsite servers or data storage).

ESI devices and media include, but are not be limited to:

(1) Computers (mainframe, desktop, and laptop);

(2) Network servers, including shared and personal drives;

(3) Individual email accounts of the contractor's principals, officers, and employees, including all folders contained in each email account such as "inbox," "outbox," "drafts," "sent," "trash," "archive," and any other folders;

(4) Personal data assistants (PDAs);

(5) External data storage devices including portable devices (e.g., flash drive); and

(6) Data storage media (magnetic, e.g., tape; optical, e.g., compact disc, microfilm, etc.).

Tangible materials means contract records that exist in a physical (i.e., non-electronic) state.

(b) If during the period of performance of this contract, HUD becomes, or anticipates becoming, a party to any litigation concerning matters related to records maintained or generated by the Contractor in the performance of this contract, the Contracting Officer may provide the contractor with a written (either hardcopy or email) preservation hold notice and certification of compliance with the preservation hold notice. Upon receipt of the hold notice, the Contractor shall immediately take the following actions--

(1) Discontinue any alteration, overwriting, deletion, or destruction of all tangible materials and ESI.

(2) Preserve tangible materials and ESI. The contractor shall preserve ESI in its "native" form to preserve metadata (i.e., creation and modification history of a document).

(3) Identify all individuals who possess or may possess tangible materials and ESI related to this matter, including contractor employees, subcontractors, and subcontractor employees.

The contractor shall provide the names of all such individuals via email to the HUD official indicated in the notice.

(4) Document in writing the contractor's efforts to preserve tangible materials and ESI. It may be useful to maintain a log documenting preservation efforts.

(5) Complete the certification of compliance with the preservation hold notice upon receipt and return it to the identified contact person; and

(6) Upon the request of the Contracting Officer, provide the Contracting Officer or other HUD official designated by the Contracting Officer with any of the information described in this clause. The contractor shall immediately confirm receipt of such request. The contractor shall describe in detail any records that the contractor knows or believes to be unavailable and provide a detailed explanation of why they are unavailable, and if known, their location.

(c)(1) If any request for records pursuant to paragraph (b)(6) of this clause causes an increase in the estimated cost or price or the time required for performance of any part of the work under this contract, or otherwise affects any other terms and conditions of this contract, the Contracting Officer shall make an equitable adjustment in the contract price, the delivery schedule, or both, and shall modify the contract.

(2) The Contractor must assert its right to an adjustment under this clause within ___ [Contracting Officer insert period; 30 days if no other period inserted] from the date of receipt of the Contracting Officer's request made pursuant to paragraph (b)(6) of this clause.

However, if the Contracting Officer decides that the facts justify it, the Contracting Officer may receive and act upon a request submitted before final payment of the contract.

(3) Failure to agree to any adjustment shall be a dispute under the "Disputes" clause of this contract. However, nothing in this clause shall excuse the contractor from providing the records requested by the Contracting Officer.

(e) The Contractor shall include this clause in all subcontracts.

(3) HUDAR 2452.208-71 REPRODUCTION OF REPORTS. (APR 1984)

In accordance with Title I of the Government Printing and Binding Regulations, printing of reports, data, or other written material, if required herein, is authorized provided that the material produced does not exceed 5,000 production units of any page and that items consisting of multiple pages do not exceed 25,000 production units in aggregate. The aggregate number of production units is determined by multiplying pages times copies. A production unit is one set, size 8 1/2 by 11 inches or less, printed on one side only and in one color. All copy preparation to produce camera ready copy for reproduction must be set by methods other than hot metal typesetting. The reports should be produced by methods employing stencils, masters, and plates which are to be used in single unit duplicating equipment no larger than 11 by 17 inches with a maximum image of 10 3/4 by 14 1/4 inches and are prepared by methods or devices that do not utilize reusable contact negatives and/or positives prepared with a camera requiring a darkroom. All reproducible (camera ready copies for reproduction by photo offset methods) shall become the property of the Government and shall be delivered to the Government with the report, data, or other written materials.

(4) HUDAR 2452.209-70 POTENTIAL ORGANIZATIONAL CONFLICTS OF

INTEREST. (FEB 2000)

(a) The Contracting Officer has determined that the proposed contract contains a potential organizational conflict of interest. Offerors are directed to FAR subpart 9.5 for detailed information concerning organizational conflicts of interest.

(b) The nature of the potential conflict of interest is: all classes of mortgagers, lenders or loan servicers are excluded from the competition. This applies to both prime and sub-prime contractors.

(c) Offerors shall provide a statement which describes concisely all relevant facts concerning any past, present or planned interest (financial, contractual, organizational, or otherwise) relating to the work to be performed under the proposed contract and bearing on whether the offeror has a possible organizational conflict of interest with respect to:

(1) Being able to render impartial, technically sound, and objective assistance or advice, or

(2) Being given an unfair competitive advantage. The offeror may also provide relevant facts that show how its organizational structure and/or management systems limit its knowledge of possible organizational conflicts of interest relating to other divisions or sections of the organization and how that structure or system would avoid or mitigate such organizational conflict.

(d) No award shall be made until any potential conflict of interest has been neutralized or mitigated to the satisfaction of the Contracting Officer.

(e) Refusal to provide the requested information or the willful misrepresentation of any relevant information by an offeror shall disqualify the offeror from further consideration for award of a contract under this solicitation.

(f) If the Contracting Officer determines that a potential conflict can be avoided, effectively mitigated, or otherwise resolved through the inclusion of a special contract clause, the terms of the clause will be subject to negotiation.

(5) HUDAR 2452.209-72 ORGANIZATIONAL CONFLICTS OF INTEREST (APR 1984)

(a) The Contractor warrants that to the best of its knowledge and belief and except as otherwise disclosed, he or she does not have any organizational conflict of interest which is defined as a situation in which the nature of work under a Government contract and a Contractor's organizational, financial, contractual or other interests are such that:

(1) Award of the contract may result in an unfair competitive advantage; or

(2) The Contractor's objectivity in performing the contract work may be impaired.

(b) The Contractor agrees that if after award he or she discovers an organizational conflict of interest with respect to this contract, he or she shall make an immediate and full disclosure in writing to the Contracting Officer which shall include a description of the action which the Contractor has taken or intends to take to eliminate or neutralize the conflict.

The Government may, however, terminate the contract for the convenience of the Government if it would be in the best interest of the Government.

(c) In the event the Contractor was aware of an organizational conflict of interest before the award of this contract and intentionally did not disclose the conflict to the Contracting Officer, the Government may terminate the contract for default.

(d) The provisions of this clause shall be included in all subcontracts and consulting agreements wherein the work to be performed is similar to the service provided by the prime contractor. The Contractor shall include in such subcontracts and consulting agreements any necessary provisions to eliminate or neutralize conflicts of interest.

(6) HUDAR 2452.239-70 ACCESS TO HUD SYSTEMS (DEVIATION SEPT 2015)

(a) Definitions: As used in this clause –

"Access" means the ability to obtain, view, read, modify, delete, and/or otherwise make use of information resources.

"Application" means the use of information resources (information and information technology) to satisfy a specific set of user requirements (see OMB Circular A-130).

“Contract” means any authorized contractual instrument, including but not restricted to task orders, purchase orders, Blanket Purchase Agreement calls, etc.

"Contractor employee" means an employee of the prime contractor or of any subcontractor, affiliate, partner, joint venture, or team members with which the contractor is associated. It also includes consultants engaged by any of those entities.

"Mission-critical system" means an information technology or telecommunications system used or operated by HUD or by a HUD contractor, or organization on behalf of HUD, that processes any information, the loss, misuse, disclosure, or unauthorized access to, or modification of which would have a debilitating impact on the mission of the agency.

"NACI" means a National Agency Check with Inquiries, the minimum background investigation prescribed by OPM.

"PIV Card" means the Personal Identity Verification (PIV) Card, the Federal Government-issued identification credential (i.e., identification badge).

"Sensitive information" means any information of which the loss, misuse, or unauthorized access to, or modification of, could adversely affect the national interest, the conduct of federal programs, or the privacy to which individuals are entitled under section 552a of title 5, United States Code (the Privacy Act), but which has not been specifically authorized under criteria established by an Executive Order or an Act of Congress to be kept secret in the interest of national defense or foreign policy.

"System" means an interconnected set of information resources under the same direct management control, which shares common functionality. A system normally includes hardware, software, information, data, applications, communications, and people (see OMB Circular A¬130). System includes any system owned by HUD or owned and operated on HUD's behalf by another party.

(b) General.

(1)The performance of this contract requires contractor employees to have access to a HUD system or systems. All such employees who do not already possess a current PIV Card acceptable to HUD shall be required to provide personal background information, undergo a background investigation (NACI or other OPM-required or approved investigation), including an FBI National Criminal History Fingerprint Check, and obtain a PIV Card prior to being permitted access to any such system in performance of this contract. HUD may accept a PIV Card issued by another Federal Government agency but shall not be required to do so. No contractor employee will be permitted access to any HUD system without a PIV Card.

(2) All contractor employees who require access to mission-critical systems or sensitive information contained within a HUD system or application(s) are required to have a more extensive background investigation. The investigation shall be commensurate with the risk and security controls involved in managing, using, or operating the system or applications(s).

(c) Citizenship-related requirements. Each affected contractor employee as described in paragraph (b) of this clause shall be:

(1) A United States (U.S.) citizen; or,

(2) A national of the United States (see 8 U.S.C. 1408); or,

(3) An alien lawfully admitted into, and lawfully permitted to be employed in the United States, provided that for any such individual, the Government is able to obtain sufficient background information to complete the investigation as required by this clause. Failure on the part of the contractor to provide sufficient information to perform a required investigation or the inability of the Government to verify information provided for affected contractor employees will result in denial of their access.

(d) Background investigation process.

(1) The Government Technical Representative (GTR) shall notify the contractor of those contractor employee positions requiring background investigations.

(i) For each contractor employee requiring access to HUD information systems, the contractor shall submit the following properly completed forms: Electronic Standard Form (SF) 85, "Questionnaire for Non-sensitive Positions” via e-QIP, completed USAccess enrollment (electronic fingerprinting) and Optional Form (OF) 306 (Items 1 thru 17). The SF-85 and OF-306 are available from the OPM website, http://www.opm.gov . The Electronic questionnaire is available on OPM’s e-QIP site https://www.opm.gov/investigations/e-qip-application/.

(ii) For each contractor employee requiring access to mission-critical systems and/or sensitive information contained within a HUD system and/or application(s), the contractor shall submit the following properly completed forms: Electronic SF-85P, "Questionnaire for Public Trust Positions” via e-QIP;" Electronic Standard Form (SF) 85, "Questionnaire for Non-sensitive Positions via e-QIP," completed USAccess enrollment (electronic fingerprinting) and Optional Form (OF) 306 (Items 1 thru 17). The SF-85 and OF-306 are available from the OPM website, http://www.opm.gov . The Electronic questionnaire is available on OPM’s e-QIP site https://www.opm.gov/investigations/e-qip-application/; and a Fair Credit Reporting Act form (authorization for the credit-check portion of the investigation). Contractor employees shall complete the Medical Release behind the SF-85P.

(iii)The electronic questionnaires (e-QIP) SF-85, 85P, and OF-306 are available from OPM's websites https://www.opm.gov/investigations/e-qip-application/and http://www.opm.gov.

The GTR will provide all other forms that are not obtainable via the Internet.

(2) The contractor shall deliver the forms and information required in paragraph (d)(1) of this clause to the GTR as securely as possible.

(3) Affected contractor employees who have had a federal background investigation without a subsequent break in federal employment or federal contract service exceeding 2 years may be exempt from the investigation requirements of this clause subject to verification of the previous investigation.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .