DTRT5717Q80146
Department of Transportation Volpe National Transportation Systems Center Security Turnstiles
Statement of Work
SCOPE
Contractor shall supply and install security turnstiles with single bar or clear acrylic panel barrier (if clear acrylic barrier it must include DOT Emblem embossed, example will be provided upon request) as detailed below:
5 Ramped Lanes Total:
· Front Building Entry: 3 ramped lanes including 1 Americans with Disabilities Act (ADA) Access with total width across all lanes equal to but not more than 11’ 8’’
· Second Building Entry: 2 ramped lanes including 1 ADA Entry with total width across all lanes equal to but not more than 9’ 8’’
· Each entry must include:
| · | 2 manual control panels |
| · | ADA passage width must be 36”* |
| · | Standard lane passage width must be 20”* |
| · | Height must be 36”* |
* Height/width guidelines provided above are approximate but all equipment must meet ADA standards.
Power/Noise
120 VAC, 50/60 Hz Power Consumption: Operating 35W/Stationary 25W (must be within 5W) Ambient Temperature: 5 degrees Fahrenheit – 120 degrees Fahrenheit Noise: Not to exceed 55dB
Software/Card Reader Compatibility
Security turnstiles shall:
· Be compatible with Lenel Access Control System
· Include Card Reader Mount Option on all lanes (ADA Lanes must have Holder for access from both left/right side).
· Have installation of software to ensure compatibility with Lenel
Installation Requirements
Upon award contractor shall:
· Field verify existing conditions, dimensions for placement and power requirements prior to manufacture/order of equipment and installation.
· Provide full installation to include all power requirements to source. Power source currently in place for existing turnstiles can be used for installation.
· No wiring or power cords will run through existing floors/walls and all must be covered.
· Steel raised floor platforms must be used to ensure damage cannot occur from foot traffic across lanes.
Removal/Disposal
Contractor shall remove and dispose of existing Turnstiles and all associated materials. Recycling/disposal of existing turnstiles and materials shall be done in accordance with appropriate Federal, State and Local laws and documentation of proper disposal shall be provided to the Government.
WARRANTY
Contractor shall warranty of all work and equipment for 12 months upon installation.
5 YEAR PREVENTATIVE MAINTENANCE AND REPAIR SERVICES:
Contractor shall provide 5 year preventative maintenance and repair plan which includes regular preventive maintenance scheduled at least annually and repair response within 24 hours of request.
SUBMITTAL REVIEW UPON AWARD
Upon award, contractor shall provide security turnstiles equipment placement drawings with catalog cuts and manufacturers schematics for concurrence by the Government prior to manufacture/order of equipment.
SUSTAINABLE AQCUISITION REQUIREMENT
To the maximum extent possible and consistent with Federal Acquisition Regulations Part 23, the government requires during the performance of the work under this SOW the Contractor is to provide or use products that are energy efficient (Energy Star) or Federal Energy Management Program (FEMA) designated; water-efficient; bio based; environmentally preferable; non-ozone depleting; or made with recovered materials. Unless otherwise identified in this SOW, each recovered materials or bio based content of EPA or USDA designated product. The sustainable acquisition requirements specified herein apply only to products that are required to be (1) delivered by the Government during contract performance; (2) acquired by the contractor for use in performing services (including the Government or specified in the design of a building work or incorporated during its construction, removal or maintenance.
SHIPPING ADDRESS AND HOURS
U.S. DOT/Volpe Center David Coombs, V241 125 Munroe Street Receiving Dock Cambridge MA 02142
Monday – Friday 6:30AM – 3:00PM