QUESTIONS_AND_ANSWERS.docx

DOCX document 14 KB Posted

Attached to
ARC FLASH STUDY
Solicitation number
DTMA93Q1500026
Issued by

About this file

QUESTIONS AND ANSWERS

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS AND ANSWERS

- How many generators are there and what size generators?

- How many utility service entrance transformers?

- How many buildings does the electrical distribution serve?

- What is the maximum system voltage to be included in the arc flash analysis?

- Who will affix the arc flash labels?

- Is a training needed for qualified personnel?

- The amendment of solicitation shows only site plan. Is there a one-line diagram of the electrical distribution system?

We have four Generators, two are 350 KW and one is 184 KW and one is 150KW.

There are 11 utility service entrance transformers There are 11 buildings being distributed to.

13.2 KV is the max voltage to be included in the arc flash analysis The contractor awarded this solicitation will affix the labels.

Training will be needed for qualified employees We did not have a one line drawing. (this is where the site visit would help).

File details come from the government source that posted it. Updated .