Federal Highway Administration

Eastern Federal Lands Highway Division

Bid Opening for

Gulf Islands National Seashore

PROJECT: PRA-GUIS 12(2) and FTNP-GUIS 11(2)

SOLICITATION NO. DTFH71-16-B-00016

February 18, 2016 at 2:00 p.m.

Sterling, VA

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

BID OPENING for SOLICITATION NO. DTFH71-16-B-00016 Project: PRA-GUIS 12(2) and FTNP-GUIS 11(2) February 18, 2016, 2:00 p.m. local time

BIDDER’S BID TOTALS DAYS TOTAL PRICE

Central Southern Corp. SCHEDULE A $1,239,140.00

OPTION 1

$2,839,125.00

OPTION 2

$296,516.00

OPTION 3

$2,926,812.00

OPTION 4

$621,025.00

SCHEDULES A, B, E, F & G

Construction activities at the project site cannot begin any earlier than September 15, 2016.

All work required for Substantial Completion must be completed by no later than January 31, 2017.

SCHEDULE A + OPTIONS

$7,922,618.00

Gulf Atlantic Constructors SCHEDULE A $670,830.00

OPTION 1

$2,307,116.25

OPTION 2

$93,249.00

OPTION 3

$2,259,159.00

OPTION 4

$400,433.75

SCHEDULES A, B, E, F & G

Construction activities at the project site cannot begin any earlier than September 15, 2016.

All work required for Substantial Completion must be completed by no later than January 31, 2017.

SCHEDULE A + OPTIONS

$5,730,788.00

Construction activities at the project site cannot begin any earlier than September 15, 2016.

All work required for Substantial Completion must be completed by no later than January 31, 2017.

Tootle Construction SCHEDULE A $979,147.50

OPTION 1

$3,098,857.50

OPTION 2

$166,396.00

OPTION 3

$3,590,605.00

OPTION 4

$601,545.00

SCHEDULES A, B, E, F & G

Construction activities at the project site cannot begin any earlier than September 15, 2016.

All work required for Substantial Completion must be completed by no later than January 31, 2017.

SCHEDULE A + OPTIONS

$8,436,551.00

Cronin Construction SCHEDULE A $785,808.96

OPTION 1

$2,659,609.90

OPTION 2

$132,201.23

OPTION 3

$3,025,058.50

OPTION 4

$648,454.64

SCHEDULES A, B, E, F & G

Construction activities at the project site cannot begin any earlier than September 15, 2016.

All work required for Substantial Completion must be completed by no later than January 31, 2017.

SCHEDULE A + OPTIONS

$7,251,133.23

Engineers Estimate SCHEDULE A $960,000.00

OPTION 1

$2,410,000.00

OPTION 2

$220,000.00

OPTION 3

$2,995,000.00

OPTION 4

$605,000.00

SCHEDULES A, B, E, F & G

Construction activities at the project site cannot begin any earlier than September 15, 2016.

All work required for Substantial Completion must be completed by no later than January 31, 2017.

SCHEDULE A + OPTIONS

$7,190,000.00

Slide Number 1
FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. DTFH71-16-B-00016 Project: PRA-GUIS 12(2) and FTNP-GUIS 11(2)�February 18, 2016, 2:00 p.m. local time �
FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. DTFH71-16-B-00016 Project: PRA-GUIS 12(2) and FTNP-GUIS 11(2)�February 18, 2016, 2:00 p.m. local time �
FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. DTFH71-16-B-00016 Project: PRA-GUIS 12(2) and FTNP-GUIS 11(2)�February 18, 2016, 2:00 p.m. local time �