Amendment_0001_-FW-OHRI_10(1) _100(1).pdf
PDF 393 KB Posted
- Solicitation number
- DTFH71-15-B-00035
About this file
Bid Opening date of August 11 2015 at 2 00 remains the same.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Opening_Results_-_FW-OHRI_10(1) _100(1).ppt | PPT presentation | |
| IFB_Solicitation_FW-OHRI_10(1) _100(1).pdf | ||
| Report_2_NOI_Instructions.pdf | ||
| VETS-100A-Form.pdf | ||
| Synopsis_-_FWS-OHRI_10(1) _100(1).pdf | ||
| Report_3_GPP.pdf | ||
| FP14_Eng.pdf | ||
| Plans_FW-OHRI_10(1) _100(1).pdf | ||
| Report_1_NEPA.pdf | ||
| Report_4_SWPPP.pdf | ||
| ADV_Bidder's_Qualifications_Form.doc | DOC document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment No. 0001
Info Page 1 of 1
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
Amendment No. 0001 Project FW-OHRI 10(1), 100(1)
Ohio River Islands National Wildlife Refuge Solicitation: DTFH71-15-B-00035
The purpose of this Amendment is to:
1) Revise the Solicitation B Pages to replace the Bid Schedule to change the guardrail class and pay item.
2) Revise the Plan sheet C01 to change the guardrail class and pay item.
The Bid Opening date of August 11, 2015, at 2:00 p.m. will remain the same.
Solicitation B Pages changes
Delete the Solicitation Bid Schedule pages B-1 thru B-5 and substitute the amended Bid Schedule pages B-1 thru B-5.
a) Deleted pay item 61701-1800 [Guardrail System G4, Type 4, Class A Steel posts].
b) Added pay item 61701-1950 [Guardrail System G4, Type 4, Class B Steel posts].
Plan changes
Delete Plan Sheet C01 and substitute the amended Plan Sheet C01.
1) Sheet C01 (Tabulation of Quantities Schedule A) updated to replace the guardrail pay item number and description to change the guardrail class from Class A to Class B.
B - 1
Amendment Item No. Pay Item No. Description Quantity Unit Unit Price Amount
A0100 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
A0120 15201-0000 CONSTRUCTION SURVEY AND STAKING
ALL LPSM $___LPSM_____ $____________
A0140 15401-0000 CONTRACTOR TESTING
ALL LPSM $___LPSM_____ $____________
A0160 15705-0100 SOIL EROSION CONTROL, SILT FENCE
3,150 LNFT $____________ $____________
A0180 15706-1100 SOIL EROSION CONTROL, INLET PROTECTION TYPE A
1 EACH $____________ $____________
A0200 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
ALL LPSM $___LPSM_____ $____________
A0220 20202-0000 SELECTIVE CLEARING
80 SQYD $____________ $____________
A0240 20301-1100 REMOVAL OF GATE
1 EACH $____________ $____________
A0260 20301-1400 REMOVAL OF INLET
1 EACH $____________ $____________
A0280 20301-2400 REMOVAL OF SIGN
1 EACH $____________ $____________
A0300 20302-1200 REMOVAL OF GUARDRAIL
800 LNFT $____________ $____________
A0320 20303-0300 REMOVAL OF CONCRETE (CEMENT TREATED BASE)
4,950 SQYD $____________ $____________
A0340 20303-1600 REMOVAL OF PAVEMENT, ASPHALT
4,950 SQYD $____________ $____________
A0360 20420-0000 EMBANKMENT CONSTRUCTION
180 CUYD $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base Contract
Project No:FW-OHRI 10(1), 100(1)
Project Name:Ohio River Islands National Wildlife Refuge
B - 2
A0380 30101-4000 AGGREGATE BASE GRADING C OR D
1,500 TON $____________ $____________
A0400 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1
700 TON $____________ $____________
A0420 60201-0800 24-INCH PIPE CULVERT
60 LNFT $____________ $____________
A0440 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT
1 EACH $____________ $____________
A0460 60403-1200 INLET, FLH TYPE 5A
1 EACH $____________ $____________
A0480 60915-1000 WHEELSTOP, CONCRETE
14 EACH $____________ $____________
0001 A0500 61701-1800 GUARDRAIL SYSTEM G4, TYPE 4, CLASS A STEEL POSTS
1,000 LNFT $____________ $____________
0001 A0510 61701-1950 GUARDRAIL SYSTEM G4, TYPE 4, CLASS B STEEL POSTS
1,000 LNFT $____________ $____________
A0520 61702-0800 TERMINAL SECTION TYPE TANGENT
1 EACH $____________ $____________
A0540 61703-0000 TERMINAL END
2 EACH $____________ $____________
A0560 61901-2400 FENCE, SPLIT RAIL, 2 RAIL
250 LNFT $____________ $____________
A0580 61902-0000 GATE (AUTOMATIC)
1 EACH $____________ $____________
A0600 62401-0300 FURNISHING AND PLACING TOPSOIL, 4-INCH DEPTH
4,900 SQYD $____________ $____________
A0620 62502-0000 TURF ESTABLISHMENT
6,300 SQYD $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base Contract
B - 3
A0640 62632-0000 PLANTINGS
ALL LPSM $___LPSM_____ $____________
A0660 63304-0900 SIGNS, ALUMINUM PANELS, TYPE 3 SHEETING
12 SQFT $____________ $____________
A0680 63401-1500 PAVEMENT MARKINGS, TYPE H, SOLID
1,300 LNFT $____________ $____________
A0700 63405-2950 PAVEMENT MARKINGS, TYPE H, STRAIGHT ARROW
4 EACH $____________ $____________
A0720 63405-3250 PAVEMENT MARKINGS, TYPE H, ACCESSIBILITY SYMBOL
2 EACH $____________ $____________
A0740 63503-0300 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
10 LNFT $____________ $____________
A0760 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
30 SQFT $____________ $____________
A0780 63602-2000 SYSTEM INSTALLATION, LIGHTING
1 EACH $____________ $____________
A0800 63602-3000 SYSTEM INSTALLATION, ELECTRICAL
1 EACH $____________ $____________
A0820 63602-6000 SYSTEM INSTALLATION, TRAFFIC DETECTOR SYSTEM
1 EACH $____________ $____________
A0840 63701-0000 FIELD OFFICE
1 EACH $____________ $____________
Submitted by:____________________________________ Schedule Total:____________
Bid Schedule Schedule:A Schedule Type:Base Contract
B - 4
Amendment Item No. Pay Item No. Description Quantity Unit Unit Price Amount
B0100 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
B0120 15201-0000 CONSTRUCTION SURVEY AND STAKING
ALL LPSM $___LPSM_____ $____________
B0140 15401-0000 CONTRACTOR TESTING
ALL LPSM $___LPSM_____ $____________
B0160 15705-0100 SOIL EROSION CONTROL, SILT FENCE
180 LNFT $____________ $____________
B0180 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
ALL LPSM $___LPSM_____ $____________
B0200 20301-3100 REMOVAL OF UTILITY POLE
10 EACH $____________ $____________
B0220 20702-0700 GEOTEXTILE FILTER, CLASS 2, TYPE B
200 SQYD $____________ $____________
B0240 30110-0000 AGGREGATE SURFACE COURSE
60 TON $____________ $____________
B0260 61901-2400 FENCE, SPLIT RAIL, 2 RAIL
150 LNFT $____________ $____________
B0280 61902-0000 GATE (AUTOMATIC)
1 EACH $____________ $____________
B0300 61904-0000 BOLLARD POST
1 EACH $____________ $____________
B0320 63304-0900 SIGNS, ALUMINUM PANELS, TYPE 3 SHEETING
4 SQFT $____________ $____________
B0340 63503-0300 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
10 LNFT $____________ $____________
B0360 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
10 SQFT $____________ $____________
Bid Schedule Schedule:B Schedule Type:Government Option 1
B - 5
B0380 63602-3000 SYSTEM INSTALLATION, ELECTRICAL (SOLAR POWER SYSTEM)
1 EACH $____________ $____________
B0400 63602-6000 SYSTEM INSTALLATION, TRAFFIC DETECTOR SYSTEM
1 EACH $____________ $____________
Submitted by:____________________________________ Schedule Total:____________
Bid Schedule Schedule:B Schedule Type:Government Option 1
| Amendment 1 info.pdf |
| U.S. DEPARTMENT OF TRANSPORTATION |
| FEDERAL HIGHWAY ADMINISTRATION |
| EASTERN FEDERAL LANDS HIGHWAY DIVISION |
| Amendment No. 0001 |
| Project FW-OHRI 10(1), 100(1) |
| Ohio River Islands National Wildlife Refuge |
| Solicitation: DTFH71-15-B-00035 |