Project No.: ID CANYON 2013(1) Project Name: Riverside Road and Lake Shore Drive Rehabilitation
# General Technical Question Answer Date
1 X THE ROAD MUST BE OPEN TO TRAFFIC FROM
6;00 AM TO 8;00 AM AGAIN FROM 4;00 PM TO
6;00 PM WE CAN HAVE ONE LANE CLOSED WITH
30 MIN. DELAYS FROM 8;00 AM TO 4;00 PM
THAN AGAIN FROM 6;00 PM TO 6;00 AM. I
WAS WONDERING IF THAT WOULD BE ONE DAY
OR TWO DAYS FOR A TRAFFIC CONTROL
SUPERVISOR.IF THE PRIME WAS TO WORK
DURING BOTH INTERVALS.
One TCS will be paid for each day that TCS work is measured according to Subsection 635.24
4/4/17