Q&A_4-27-17.pdf

PDF 76 KB Posted

Attached to
AK FS TNF 2(1), Auke Recreation Roadway Rehab
Solicitation number
DTFH7017B00008
Issued by

View the file

Other files

File Type Posted
BidSum_Auke.pdf PDF
Auke-Road_Earthwork_Report.pdf PDF
IFB_AUKE.pdf PDF
Auke-Road_Plans100_.pdf PDF
Plan_Request_form_AUKE.pdf PDF
Auke-Road_Alignment_Report.pdf PDF
Project_Description.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No. AK FS TNF 2(1) Project AUKE RECREATION ROADWAY REHAB

# General Technical Question Answer Date 1 x Will a material transfer vehicle (MTV) be required for the asphalt paving on this project?

No. See Subsection 403.08 Placing and Finishing.

4/27/17

2 x Will the roadway be measured for roughness before and after asphalt paving?

No. See Subsection 403.11 Pavement Straightedge Measurement.

4/27/17

3 x

What performance grade asphalt cement is required for this Type 1 mix design and will it require lime?

Provide a State Department of Transportation approved Job Mix Formula.

See Subsection 403.02 Composition of Mix

(JMF).

4/27/17