EXPEDITED RESURFACING AND REPAIR MATOC
TASK ORDER REQUEST FOR PROPOSALS
Solicitation No. DTFH70-16-R-00005
WA NPS PRES 15(2)
PAVEMENT PRESERVATION OLYMPIC
PHASE II
Solicitation, Offer & Award, Bid Schedule, Contract Clauses, General Wage Decision, Special Contract Requirements, and Plans
This solicitation cites
Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14
This project uses U.S. Customary units of measure
ISSUING OFFICE:
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
610 EAST FIFTH STREET
VANCOUVER, WA 98661-3801
Phone: (360) 619-7520 – FAX: (360) 619-7932 e-mail: wfl.contracts@dot.gov
WORLD HERITAGE SITE
Proposal Due Date:
See page A-3, Block 13A
QUICK INDEX
Page Item --- Special Notice --- Bid Submittal Checklist --- Authority to Sign --- Bid Bond --- Table of Contents A-1 Notice to Offerors A-3 SF 1442, Solicitation, Offer and
Award A-6a Subcontracting Plan A-7 Bid Schedule B-1 Solicitation Provisions C-1 Contract Clauses D-1 General Wage Decision E-1 Special Contract Requirements H-1 Plans
PROPOSAL REMINDERS
Electronic proposals will not be accepted.
Submit printed copy to the address listed on the enclosed SF 1442. Before submitting your proposal, please review the following:
Have you rechecked your figures?
Have you completed the bid schedule?
Have you completed and signed the SF 1442, Solicitation, Offer & Award?
Have you acknowledged all amendments?
Have you completed the Representations & Certifications (Page B-1)?
Is your bid guarantee enclosed in proper form and amount (see FAR Clause 52.228-1), including Power of Attorney affidavit?
Does the lower left corner of the proposal envelope state “Proposal Enclosed”?
Does the lower left corner include the DTFH70-16-R-00005 and the project number/name?
A-1 Notice to Offerors
PROJECT No/Name WA NPS PRES 15(2)
PAVEMENT PRESERVATION OLYMPIC PHASE II
BEGINNING/ENDING AT VARIOUS
LENGTH 21.23 MILES
NATIONAL PARK OLYMPIC
COUNTY JEFFERSON & CLALLAM
STATE WASHINGTON
FIXED COMPLETION DATE See FAR Clause 52.211-10 (FAR Clauses begin on page C-1)
SPECIAL NOTICE
WA NPS PRES 15(2), PAVEMENT PRESERVATION OLYMPIC PHASE II
Solicitation No.: DTFH70-16-R-00005
THIS “TASK ORDER REQUEST FOR PROPOSAL” IS SOLELY FOR THE
FOLLOWING CONTRACTS AND CONTRACTORS:
Contract Number Contractor Name Contractor Number DTFH6812D00004 Eagle Peak Rock & Paving, Inc. 530.233.4568 DTFH6812D00005 Intermountain Slurry Seal 800.595.0452 DTFH6812D00006 George Reed, Inc. 877.823.2305
THIS PROJECT IS BEING ADVERTISED ON THE FEDERAL BUSINESS
OPPORTUNITIES WEBSITE TO ANNOUNCE THE UPCOMING PROJECT
AND ASSIST POTENTIAL SUBCONTRACTORS BY PUBLICIZING
OPPORTUNITIES. A PROPOSAL WILL ONLY BE ACCEPTED FROM THE
ABOVE PRIME CONTRACTORS.
Additional information may be found on our web pages:
Advertised Projects:
http://flh.fhwa.dot.gov/business/construction/#opportunities Description: This web page contains a link to the projects currently advertised on FBO.
WA NPS PRES 15(2)
Pavement Preservation Olympic Phase II
INSTRUCTIONS: When the offeror/principal is a corporation, include this certification with your offer/bid.
Corporate Certificate
I, ____________________________________________ (name), certify that I am the
________________________________________(title), of the corporation named as the Offeror/Principal herein;
that _________________________________________(name), who signed this offer and/or bid bond on behalf of ___________________________ (company name) is
________________________________________ (title) of this corporation;
that the offer was duly signed for and on behalf of said corporation by authority and scope of its governing body, and within the scope of its corporate powers.
_____________________________________ (signature) Affix Corporate Seal
_____________________________________ (title)
WA NPS PRES 15(2)
RESERVED
BID BOND
(See instructions on reverse)
OMB Control Number: 9000-0045 Expiration Date: 7/31/2019
PRINCIPAL (Legal name and business address) TYPE OF ORGANIZATION ("X" one)
STATE OF INCORPORATION
SURETY(IES) (Name and business address)
PERCENT
OF BID
PRICE
PENAL SUM OF BOND
AMOUNT NOT TO EXCEED
MILLION(S) THOUSAND(S) HUNDRED(S) CENTS
BID IDENTIFICATION
BID DATE INVITATION NUMBER
PRINCIPAL
SIGNATURE(S)
NAME(S) &
TITLE(S)
(Typed)
1.
1. 2.
2.
3.
3.
(Seal) (Seal) (Seal) Corporate Seal
INDIVIDUAL SURETY(IES)
SIGNATURE(S)
NAME(S)
(Typed)
1.
1.
2.
2.
(Seal) (Seal)
CORPORATE SURETY(IES)
SU
R
ET
Y
A
NAME &
ADDRESS
STATE OF INCORPORATION LIABILITY LIMIT ($)
SIGNATURE(S)
NAME(S) &
TITLE(S)
(Typed)
1.
1.
2.
2. Corporate Seal
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is NOT usable
STANDARD FORM 24 (REV. 8/2016)
Prescribed by GSA - FAR (48 CFR) 53.228(a)
FOR (Construction, Supplies or Services)
OBLIGATION:
We, the Principal and Surety(ies) are firmly bound to the United States of America (hereinafter called the Government) in the above penal sum. For payment of the penal sum, we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally. However, where the Sureties are corporations acting as co-sureties, we, the Sureties, bind ourselves in such sum "jointly and severally" as well as "severally" only for the purpose of allowing a joint action or actions against any or all of us. For all other purposes, each Surety binds itself, jointly and severally with the Principal, for the payment of the sum shown opposite the name of the Surety. If no limit of liability is indicated, the limit of liability is the full amount of the penal sum.
CONDITIONS:
The Principal has submitted the bid identified above.
THEREFORE:
The above obligation is void if the Principal - (a) upon acceptance by the Government of the bid identified above, within the period specified therein for acceptance (sixty (60) days if no period is specified), executes the further contractual documents and gives the bond(s) required by the terms of the bid as accepted within the time specified (ten (10) days if no period is specified) after receipt of the forms by the principal; or (b) in the event of failure to execute such further contractual documents and give such bonds, pays the Government for any cost of procuring the work which exceeds the amount of the bid.
Each Surety executing this instrument agrees that its obligation is not impaired by any extension(s) of the time for acceptance of the bid that the Principal may grant to the Government.
Notice to the surety(ies) of extension(s) is waived. However, waiver of the notice applies only to extensions aggregating not more than sixty (60) calendar days in addition to the period originally allowed for acceptance of the bid.
WITNESS:
The Principal and Surety(ies) executed this bid bond and affixed their seals on the above date.
DATE BOND EXECUTED (Must not be later than bid opening date)
Paperwork Reduction Act Statement - This information collection meets the requirements of 44 USC § 3507, as amended by section 2 of the Paperwork Reduction Act of 1995. You do not need to answer these questions unless we display a valid Office of Management and Budget (OMB) control number. The OMB control number for this collection is 9000-0045. We estimate that it will take 25 minutes to read the instructions, gather the facts, and answer the questions. Send only comments relating to our time estimate, including suggestions for reducing this burden, or any other aspects of this collection of information to: General Services Administration, Regulatory Secretariat Division (M1V1CB), 1800 F Street, NW, Washington, DC 20405.
JOINT VENTURE
OTHER (Specify)
PARTNERSHIPINDIVIDUAL
CORPORATION
WA NPS PRES 15(2)
DTFH70-16-R-00005
INSTRUCTIONS
1. This form is authorized for use when a bid guaranty is required. Any deviation from this form will require the written approval of the Administrator of General Services.
2. Insert the full legal name and business address of the Principal in the space designated "Principal" on the face of the form. An authorized person shall sign the bond. Any person signing in a representative capacity (e.g., an attorney-in-fact) must furnish evidence of authority if that representative is not a member of the firm, partnership, or joint venture, or an officer of the corporation involved.
3. The bond may express penal sum as a percentage of the bid price. In these cases, the bond may state a maximum dollar limitation (e.g., 20% of the bid price but the amount not to exceed dollars).
4. (a) Corporations executing the bond as sureties must appear on the Department of the Treasury's list of approved sureties and must act within the limitations listed therein. The value put into the LIABILITY LIMIT block is the penal sum (i.e., the face value) of the bond, unless a co-surety arrangement is proposed.
(b) When multiple corporate sureties are involved, their names and addresses shall appear in the spaces (Surety A, Surety B, etc.) headed "CORPORATE SURETY(IES)." In the space designated "SURETY(IES)" on the face of the form, insert only the letter identifier corresponding to each of the sureties. Moreover, when co-surety arrangements exist, the parties may allocate their respective limitations of liability under the bond, provided that the sum total of their liability equals 100% of the bond penal sum.
(c) When individual sureties are involved, a completed Affidavit of Individual Surety (Standard Form 28) for each individual surety, shall accompany the bond.
The Government may require the surety to furnish additional substantiating information concerning its financial capability.
5. Corporations executing the bond shall affix their corporate seals. Individuals shall execute the bond opposite the word "Corporate Seal"; and shall affix an adhesive seal if executed in Maine, New Hampshire, or any other jurisdiction requiring adhesive seals.
6. Type the name and title of each person signing this bond in the space provided.
7. In its application to negotiated contracts, the terms "bid" and "bidder" shall include "proposal" and "offeror."
SU
R
ET
Y
B
NAME &
ADDRESS
STATE OF INCORPORATION LIABILITY LIMIT ($)
SIGNATURE(S)
NAME(S) &
TITLE(S)
(Typed)
1.
1.
2.
2. Corporate Seal
Corporate Seal
LIABILITY LIMIT ($)STATE OF INCORPORATION
2.
2.
1.
1.NAME(S) &
TITLE(S)
(Typed)
SIGNATURE(S)
NAME &
ADDRESS
SU
R
ET
Y
C
Corporate Seal
LIABILITY LIMIT ($)
2.
2.
STATE OF INCORPORATION
1.
1.
NAME(S) &
TITLE(S)
(Typed)
SIGNATURE(S)
NAME &
ADDRESS
SU
R
ET
Y
D
Corporate Seal
LIABILITY LIMIT ($)
2.
2.
STATE OF INCORPORATION
1.
1.
NAME(S) &
TITLE(S)
(Typed)
SIGNATURE(S)
NAME &
ADDRESS
SU
R
ET
Y
E
Corporate Seal
LIABILITY LIMIT ($)
2.
2.
STATE OF INCORPORATION
1.
1.
NAME(S) &
TITLE(S)
(Typed)
SIGNATURE(S)
NAME &
ADDRESS
SU
R
ET
Y
F
Corporate Seal
LIABILITY LIMIT ($)
2.
2.
STATE OF INCORPORATION
1.
1.
NAME(S) &
TITLE(S)
(Typed)
SIGNATURE(S)
NAME &
ADDRESS
SU
R
ET
Y
G
STANDARD FORM 24 (REV. 8/2016) BACK
Table of Contents Project: WA NPS PRES 15(2), Pavement Preservation Olympic Phase II
TABLE OF CONTENTS
08/01/14–FP14
DESCRIPTION PAGE
Notice to Offeror ......................................................................................................................... A-1
Solicitation, Offer, and Award (SF 1442) ................................................................................... A-3
Bid Schedule ............................................................................................................................... A-7
Solicitation Provisions ................................................................................................................ B-1
Contract Clauses ......................................................................................................................... C-1
General Wage Decision .............................................................................................................. D-1
SCRs Table of Contents
SPECIAL CONTRACT REQUIREMENTS (SCR)
The following Special Contract Requirements amend and supplement the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-14), U.S. Department of Transportation, Federal Highway Administration.
Division 100 ..................................................................................................................... E-1 Division 150 ................................................................................................................... E-24 Division 400 ..................................................................................................................... F-1 Division 600 ..................................................................................................................... F-6 Division 700 .................................................................................................................... G-1
Plans ............................................................................................................................................ H-1
Table of Contents
(This page intentionally left blank)
A-1
Notice to Offerors Project: WA NPS PRES 15(2), Pavement Preservation Olympic Phase II
NOTICE TO OFFEROR
08/05/16–FP14
THIS PROJECT IS BEING SOLICITED AND AWARDED UNDER FP-14.
The FP-14 is a new release of FLH’s Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects. Carefully review the entire FP-14 as significant modifications have been made and new requirements added. Additionally, sections from the previous FP version may have shifted or been deleted.
To view the FP-14 electronically go to:
https://flh.fhwa.dot.gov/business/resources/specs/
The FP-14 is a dual unit document with U.S. Customary units being the primary unit shown.
Metric equivalents are shown in parenthesis.
When submitting bids, drawings, calculations, and other construction documents, use only U.S. Customary units of measure, unless otherwise stated.
I. Project Location
General Location. The project work is located in Olympic National Park Clallam and Jefferson County near Port Angeles, Forks, and Aberdeen, WA
Project Limits. Signs have not been erected to identify the project limits. No Government personnel will be available for show-me tours.
II. Pre- proposal Information.
MATOC. This solicitation is solicited under the Pacific West Expedited Roadway Surfacing, Resurfacing, and Repair Multiple Award Task Order Contract (MATOC). Selection of the successful offer is based on price.
GENERAL AND TECHNICAL QUESTIONS REGARDING PROPOSED WORK FOR THIS
PROJECT WILL BE ACCEPTED UNTIL CLOSE-OF-BUSINESS ON December 6, 2016.
Refer to page A-5 for information on how to submit questions related to General Information and Technical Information. Answers to General and Technical Questions will be posted at:
https://www.fbo.gov/spg/DOT/FHWA/WFL/DTFH70-16-R-00005/listing.html.
Every attempt to respond to questions will be made. However, response to questions received after the above posted date is not guaranteed.
Physical Data. Road Inventory Program (RIP) data applicable to this project is listed in FAR Clause 52.236-4 Physical Data.
Representations & Certifications. Submit or update Representations and Certifications online at https://www.sam.gov/portal/public/SAM/ before bid submittal. For more details go to FAR https://www.fbo.gov/spg/DOT/FHWA/WFL/DTFH70-16-R-00005/listing.html https://www.sam.gov/portal/public/SAM/
A-2
Project: WA NPS PRES 15(2), Pavement Preservation Olympic Phase II
Provision 52.204-8 Annual Representations and Certifications (see page B-2.). If you have previously registered on-line and the NAICS code for this solicitation is different than the code listed in your online file, please note the amended changes on the lines provided in FAR 52.204- 8.
Requests for Information. Requests for technical information (Plan and Division 100 – 700 Specification questions only) about this project will only be accepted in writing (see Block 9 on page A-5).
SF 1442, Solicitation, Offer, and Award. Particular attention should be paid to Standard Form l442, Solicitation, Offer and Award, to assure that Blocks 14, 15, 16, 19, 20A, and 20C are completed correctly. Sign Block 20B according to the instructions in Subsection 102.02. You must submit a completed ‘Authority to Sign’ document. You must also complete the representations and certifications contained in the Contract Provisions beginning on page B-1.
Failure to furnish or complete any of the above may result in your bid being considered nonresponsive and being rejected.
Facsimile and email offers, modifications, and withdrawals. Facsimile and email offers are not authorized for this solicitation. Offers may be modified or withdrawn by facsimile, if such notice is received by the time specified for receipt of offers. The Government will not be responsible for any failure attributable to the transmission or receipt of facsimile data. See FAR Provision 52.215-1, Instructions to Offerors – Competitive Acquisition. FAX 360.619.7932.
Surety Bond Guarantee Program. Small businesses that need surety bonds can qualify for U.S.
Small Business Administration (SBA) backed surety bonds. SBA assistance in locating a participating surety company or agent, and completing application forms is available online. For more information on the U.S. SBA’s Surety Bond Guarantee program, go online to http://www.sba.gov/content/contractors or call 1-800-U-ASK-SBA.
http://www.sba.gov/content/contractors
A-2a
Project: WA NPS PRES 15(2), Pavement Preservation Olympic Phase II
Fraud Alert. Current and potential U.S. Department of Transportation (DOT) Contractors have recently been receiving fraudulent letters purporting to be issued by DOT. These fraudulent letters request that the Contractors resubmit their banking information to DOT. If you receive such a letter, please DO NOT complete the requested worksheet that is attached to the letters and DO NOT release any information. To register or update information, Contractors are required to go directly through the System for Award Management (SAM) website and never through a third party. You can access SAM at https://www.sam.gov/portal/public/SAM/.
III. Post Award Information.
Insurance. Insurance requirements are described in Subsection 107.05.
Contractor Performance Evaluations. This office posts performance evaluations in the Contractor Performance Assessment Reporting System (CPARS); for additional information see http://www.cpars.gov/index.htm. Upon receiving an email notice of evaluation availability, you will have 14-60 days to review the evaluation online and submit comments. If you are unable to access the system, call 360.619.7520 for assistance or for a copy of the evaluation.
IV. Specifications and Permits.
Specifications. This solicitation and subsequent contract are governed by the Federal Acquisition Regulation (FAR), agency supplemental regulations, and the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14. An electronic version may be found at http://flh.fhwa.dot.gov/business/resources/specs/. A single paper copy can also be obtained from the Research & Technology Product Distribution Center (RTPDC) by e-mail to: report.center@dot.gov, or by phone 814-239-1160, or fax 814-239-2156.
Material Sources. Sources have not been identified for this project. Secure all permits and clearances for Contractor-located sites and sources. See Subsection 105.02(c).
http://www.cpars.gov/index.htm http://flh.fhwa.dot.gov/business/resources/specs/ mailto:report.center@dot.gov
A-2b
(This page intentionally left blank)
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
Federal Highway Administration
Western Federal Lands Highway Div.
610 East Fifth Street Vancouver WA 98661-3801
WFLHD
Attn: Contracts
See Page A-5 360-619-7520
SEE BLOCK 10
x 11/09/2016
DTFH70-16-R-00005
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
This solicitation is designated WA NPS PRES 2015(2), Pavement Preservation Olympic
Phase II, Olympic National Park, Clallam County, Washington.
In Strict Accordance with:
Bid Schedule
Federal Acquisition Regulations (FAR) and Transportation Acquisition Regulations
(TAR)
General Wage Decision
Special Contract Requirements
Standard Specifications for Construction of Roads and Bridges on Federal Highway
Projects, FP-14, US Customary
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 calendar days and complete it within ________________ ________________ calendar days after receiving page A-5
12/13/2016
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
A-3
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
Federal Highway Administration Western Federal Lands Highway Div.
610 East Fifth Street Vancouver WA 98661-3801
WFLHD
Angy Liljedahl
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
A-4
Unique Entity Identifier:________________________ Cage Code:____________________
See Bid Schedule
All Items on bid schedule
See page A-5
Federal Highway Administration Western Federal Lands Highway Div.
610 East Fifth Street Vancouver WA 98661-3801 Attn: Finance
A-5
Continuation SF 1442
WA NPS PRES 15(2)
Pavement Preservation Olympic Phase II
Block 9 FOR GENERAL INFORMATION, call 360.619.7520 from the hours of 8:00 a.m. to 4:00 p.m. local time or e-mail us at wfl.contracts@dot.gov.
FOR TECHNICAL INFORMATION (plan and specification questions only), requests for technical information about this project will only be accepted in writing.
Submit questions via fax (360.619.7932) or e-mail at plans_spec@dot.gov (plans_spec@dot.gov).
QUESTIONS/ANSWERS POSTED ONLINE. You can view questions and answers on the Federal Business Opportunities (FBO) Website https://www.fbo.gov/ .
Insert the solicitation number in “Keyword / Solicitation #:”
Scroll to the project.
Make sure you are on the most recent view and look in the right section of the page for the most recent Q&A document.
FOR DAVIS-BACON WAGE RATE INFORMATION call the Department of Labor at 415.625.7716 (DRBA - Western Region).
FOR PHYSICAL DATA, See FAR Contract Clause 52.236-4, Physical Data, (clauses begin on page C-1) for a listing of available data. Physical Data will be posted with the solicitation on the Federal Business Opportunities website.
Block 11 COMPLETION DATE: Work shall be completed on or before the date specified in FAR Clause 52.211-10, Commencement, Prosecution, and Completion of Work, subject to such extensions as may be authorized by the terms of the contract and the specifications made a part thereof. Contract Clauses begin on pages C-1.
Block 12A PERFORMANCE & PAYMENT BONDS: See FAR Clause, 52.228-15, Performance and Payment Bonds - Construction (clauses begin on page C-1) and Subsection 102.06 of the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14.
Block 13B BID BOND AMOUNT: See FAR Clause 52.228-1, Bid Guarantee (clauses begin on page C-1).
ADDITIONAL INFORMATION: See Subsections 102.03 and 102.04 of Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14.
Block 24 SUBMITTING INVOICES: See Subsection 109.08 of the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects FP-14.
A-6
Continuation SF 1442
WA NPS PRES 15(2)
Pavement Preservation Olympic Phase II
ESTIMATED PRICE RANGE. The price range of the project work is between $2,000,000 and $3,000,000.
SUBCONTRACTING PLAN. This Request for Proposals requires an offeror who is a LARGE business to submit an acceptable subcontracting plan with their proposal. A large business is one whose average gross annual receipts over the past 3 years equal $36.5 million or more. For your information the subcontracting plan form is included beginning on page A-6a. This requirement does not apply to SMALL businesses
Subcontracting Plan – A-6a
Project: WA NPS PRES 15(2), PAVEMENT PRESERVATION OLYMPIC PHASE II
For Information Only. Do not submit with your bid.
NOTES:
1. Consider the following FHWA small business goals in development of Task Order
Subcontracting plans and efforts:
FHWA Small Business Goals (As of FY 2016) Business Size Goal (%)
SB 49.5%
SDB 5.0%
HUBZone 3.0%
WOSB 5.0%
SDVOSB 3.0%
Where the offeror has an existing approved master subcontracting plan, those goals may be reflected in the proposed plan for this task order. Please note as such.
Where subcontracting opportunities will not exist for this task order, furnish a statement to that effect signed by an authorized official.
Offeror may use their subcontracting plan format provided the information remains clear, consistent, and meets the requirements of FAR Clause 52.219-9 Small Business Subcontracting Plan.
Text lines may be added to this form as needed.
In the first table, provide information expressed in terms of goal percentages of the total planned subcontracting dollars.
If a subcontractor qualifies in more than one category, include the subcontract amount in each applicable category. If you have questions, contact the Contracting Officer. [Example: If ABC Inc is a small business, a certified HUBZone small business, and a Women-owned small business, then their subcontract amount of $100,000 would be included in the dollar values shown in rows d, g, and i.]
Subcontracting Plan – A-6b
1. The following principal types of supplies and/or services are planned to be subcontracted under this task order. (Indicate if planned to subcontract to a LARGE, SB, VOSB, SDVOSB, HUBz, SDB, or WOSB business concern.)
Type of Supply/Service to be subcontracted
Company (if known) Address (city/state)
Subcontractor type
LARGE, SB, VOSB,
SDVOSB, HUBz, SDB, WOSB
(enter one or more as applicable)
TASK ORDER SUBCONTRACTING PLAN
a. Total prime task order amount $
Ratio Goals
Percent
b. Total planned subcontract awards $
c. Total planned subcontract awards to Large Business concerns (LARGE) $
d. Total planned subcontract awards to all Small Business concerns (SB)
$ (d/b) %
e. Total planned subcontract awards to Veteran-Owned
Small Business concerns (VOSB) $ (e/b) %
f. Total planned subcontract awards to Service-Disabled
Veteran-Owned Small Business concerns (SDVOSB) $ (f/b) %
g. Total planned subcontract awards to certified HUBZone Small Business concerns (HUBz)
$ (g/b) %
h. Total planned subcontract awards to Small
Disadvantaged Business concerns (SDB) (includes ANCs and Indian Tribes)
$ (h/b) %
i. Total planned subcontract awards to Women-Owned
Small Business concerns (WOSB) $ (i/b) %
Subcontracting Plan – A-6c
2. The following methods were used to develop the subcontract percentage goals:
3. The following methods were used to identify potential subcontract sources for solicitation purposes.
(What source lists were used, such as the System for Award Management (SAM), Veterans service organizations, the National Minority Purchasing Council Vendor Information Service, the Research and Information Division of the Minority Business Development Agency in the Department of Commerce, or small, HUBZone, small disadvantaged, and women-owned small business trade associations, and what organizations were contacted to identify potential SB, VOSB, SDVOSB, HUBz, SDB, and WOSB subcontractors.):
4. (Check one) Indirect costs (_)were (__)were not included in establishing the subcontracting goals specified in the table above.
5. If indirect costs were included, the following method was used to determine the proportionate share of indirect costs to be incurred with SB, SDVOSB, HUBz, SDB, and WOSB subcontractors:
6. The following individual will administer the subcontracting program:
Name:_______________________________________________ Title:________________________________________________ Telephone & e-mail:____________________________________________________________
This individual's specific duties, as they relate to the subcontracting program, are as follows:
7. The following efforts will be taken to ensure that SB, VOSB, SDVOSB, HUBz, SDB, and WOSB business concerns will have an equitable opportunity to compete for subcontracts:
8. It is agreed that: a) FAR Clause 52.219-8, Utilization of Small Business Concerns, will be included in
Subcontracting Plan – A-6d all subcontracts that offer further subcontracting opportunities; and b) All subcontractors (except small business concerns) at all tiers below the prime contractor who receive subcontracts in excess of $700,000 ($1,500,000 if construction) will be required to adopt and comply with a subcontracting plan in accordance with FAR Clause 52.219-9 Small Business Subcontracting Plan.
9. The Contractor agrees to:
a. Cooperate in any studies or surveys as may be required.
b. Submit periodic reports as may be required so that the Government can determine the extent of compliance by the Contractor with the subcontracting plan.
c. After November 30, 2017, include subcontracting data for each order when reporting subcontracting achievements for indefinite-delivery, indefinite-quantity contracts intended for use by multiple agencies;
d. Submit the Individual Subcontract Report (ISR) and/or the Summary Subcontract Report (SSR), in accordance with paragraph (l) of this clause using the Electronic Subcontracting Reporting System (eSRS) at http://www.esrs.gov. The reports shall provide information on subcontract awards to small business concerns (including ANCs and Indian tribes that are not small businesses), veteran-owned small business concerns, service-disabled veteran-owned small business concerns, HUBZone small business concerns, small disadvantaged business concerns (including ANCs and Indian tribes that have not been certified by SBA as small disadvantaged businesses), women-owned small business concerns, and for NASA only, Historically Black Colleges and Universities and Minority Institutions. Reporting shall be in accordance with this clause, or as provided in agency regulations;
e. Ensure that its subcontractors with subcontracting plans agree to submit the ISR and/or the SSR using eSRS;
f. Provide its prime task order number, its Unique entity identifier, and the email address of the Offeror's official responsible for acknowledging receipt of or rejecting the ISRs, to all first-tier subcontractors with subcontracting plans so they can enter this information into the eSRS when submitting their ISRs; and
g. Require that each subcontractor with a subcontracting plan provide the prime task order number, its own Unique entity identifier, and the email address of the subcontractor's official responsible for acknowledging receipt of or rejecting the ISRs, to its subcontractors with subcontracting plans.
10. The following types of records concerning procedures that have been adopted to comply with the requirements and goals in the plan shall be maintained through task order completion:
a. Source lists (e.g., SAM), guides, and other data that identify small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business concerns.
b. Organizations contacted in an attempt to locate sources that are small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, or women-owned small business concerns.
c. Records on each subcontract solicitation resulting in an award of more than $150,000, indicating—
i. Whether small business concerns were solicited and, if not, why not;
ii. Whether veteran-owned small business concerns were solicited and, if not, why not;
Subcontracting Plan – A-6e
iii. Whether service-disabled veteran-owned small business concerns were solicited and, if not, why not;
iv. Whether HUBZone small business concerns were solicited and, if not, why not;
v. Whether small disadvantaged business concerns were solicited and, if not, why not;
vi. Whether women-owned small business concerns were solicited and, if not, why not; and
vii. If applicable, the reason award was not made to a small business concern.
d. Records of any outreach efforts to contact—
i. Trade associations;
ii. Business development organizations;
iii. Conferences and trade fairs to locate small, HUBZone small, small disadvantaged, service-disabled veteran-owned, and women-owned small business sources; and
iv. Veterans service organizations.
e. Records of internal guidance and encouragement provided to buyers through—
i. Workshops, seminars, training, etc.; and
ii. Monitoring performance to evaluate compliance with the program’s requirements.
f. On a task order-by-task order basis, records to support award data submitted by the offeror to the
Government, including the name, address, and business size of each subcontractor. Contractors having commercial plans need not comply with this requirement. Assurances that the Offeror will make a good faith effort to acquire articles, equipment, supplies, services, or materials, or obtain the performance of construction work from the small business concerns that it used in preparing the bid or proposal, in the same or greater scope, amount, and quality used in preparing and submitting the bid or proposal. Responding to a request for a quote does not constitute use in preparing a bid or proposal. The Offeror used a small business concern in preparing the bid or proposal if—
i. The Offeror identifies the small business concern as a subcontractor in the bid or proposal or associated small business subcontracting plan, to furnish certain supplies or perform a portion of the subcontract; or
ii. The Offeror used the small business concern's pricing or cost information or technical expertise in preparing the bid or proposal, where there is written evidence of an intent or understanding that the small business concern will be awarded a subcontract for the related work if the Offeror is awarded the task order.
11. The Contractor will provide the Contracting Officer with a written explanation if the Contractor fails to acquire articles, equipment, supplies, services or materials or obtain the performance of construction work as described in (d)(12) of this clause. This written explanation must be submitted to the Contracting Officer within 30 days of task order completion.
12. The Contractor will not prohibit a subcontractor from discussing with the Contracting Officer any material matter pertaining to payment to or utilization of a subcontractor.
13. In order to effectively implement this plan to the extent consistent with efficient task order performance, the Contractor shall perform the following functions:
a. Assist small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business concerns by arranging solicitations, time for the preparation of bids, quantities, specifications, and delivery schedules so as to facilitate the participation by such concerns. Where the Contractor’s lists of potential small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business subcontractors are excessively long, reasonable effort shall be made to give all such small business concerns an opportunity to compete over a period of time.
Subcontracting Plan – A-6f
b. Provide adequate and timely consideration of the potentialities of small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business concerns in all “make-or-buy” decisions.
c. Counsel and discuss subcontracting opportunities with representatives of small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business firms.
d. Confirm that a subcontractor representing itself as a HUBZone small business concern is certified by SBA as a HUBZone small business concern in accordance with 52.219-8(d)(2).
e. Provide notice to subcontractors concerning penalties and remedies for misrepresentations of business status as small, veteran-owned small business, HUBZone small, small disadvantaged, or women-owned small business for the purpose of obtaining a subcontract that is to be included as part or all of a goal contained in the Contractor’s subcontracting plan.
f. For all competitive subcontracts over the simplified acquisition threshold in which a small business concern received a small business preference, upon determination of the successful subcontract offeror, prior to award of the subcontract the Contractor must inform each unsuccessful small business subcontract offeror in writing of the name and location of the apparent successful offeror and if the successful subcontract offeror is a small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, or women-owned small business concern.
g. Assign each subcontract the NAICS code and corresponding size standard that best describes the principal purpose of the subcontract.
14. The Contractor acknowledges that a failure of the Contractor or subcontractor to comply in good faith with clause 52.219-8, Utilization of Small Business Concerns, or this approved subcontracting plan shall be considered a material breach of the task order.
Subcontracting Plan – A-6g
Contractor
Signed Date
Printed Name Title
Company Name and Address
Email address
Federal Highway Administration
Accepted by: _______________________________________ __________________ Angy Liljedahl, Contracting Officer Date
Subcontracting Plan – A-6h
RESERVED
A-7
Bid Schedule
Project: WA NPS PRES 15(2)
Bidders please note: Before preparing the bid, carefully read the Solicitation Provisions.
Insert a unit bid price, in figures, for each pay item for which a quantity appears in the bid schedule. Multiply the unit bid price by the quantity for each pay item and show the amount bid. Should any mathematical check made by the Government show a mistake in the amount bid, the Amount Bid for the item will be based on the Unit Bid Price.
When a “LPSM” (Lump Sum) appears as a unit bid price, insert an amount for each lump sum pay item.
When a sum based on a fixed rate appears for any pay item in the amount bid column, include the Government inserted amount bid for the item in the total bid amount.
Total the amounts bid for all pay items and insert the total bid amount.
A-8
B I D S C H E D U L E Account: ALL
Project No: WA NPS PRES 15(2)
Name: Pavement Preservation Olympic Phase II CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
15101-0000 Line A0050 ALL LPSM $
15301-0000 Line A0100 ALL LPSM $
15401-0000 Line A0150 ALL LPSM $
15501-0000 Line A0200 ALL LPSM $
40901-2000 Line A0250 109,000 SQYD $ $
40901-3000 Line A0300 216,500 SQYD $ $
41402-2000 Line A0350 26.0 MILE $ $
41801-1000 Line A0400 140 SQYD $ $
41801-2000 Line A0450 4,300 SQYD $ $
41802-3000 Line A0500 100 TON $ $
62201-0050 Line A0550 20 HOUR $ $
62201-0450 Line A0600 20 HOUR $ $
62301-0000 Line A0650 40 HOUR $ $
63301-0000 Line A0700 30 EACH $ $
63401-0000 Line A0750 761,000 LNFT $ $
63405-0050 Line A0800 86 EACH $ $
63501-1000 Line A0850 ALL LPSM $
63502-0700 Line A0900 220 EACH $ $
Schedule Total: ________________________
Submitted by: _________________________
PAVEMENT MARKINGS, SYMBOLS
TEMPORARY TRAFFIC CONTROL, TRAFFIC CONTROL SUPERVISOR
TEMPORARY TRAFFIC CONTROL, CONE
MOBILIZATION
CONTRACTOR QUALITY CONTROL
CONTRACTOR TESTING
CONSTRUCTION SCHEDULE
MICRO SURFACING, TYPE 2
MICRO SURFACING, TYPE 3
GENERAL LABOR
SIGN SYSTEM
PAVEMENT MARKINGS (TYPE B)
CRACKS, CLEANING AND SEALING
ASPHALT CONCRETE PAVEMENT PATCH, TYPE 1
ASPHALT CONCRETE PAVEMENT PATCH, TYPE 2
ASPHALT CONCRETE PAVEMENT PATCH, TYPE 3
DUMP TRUCK, 5 CUBIC YARD MINIMUM CAPACITY
BACKHOE LOADER, 4 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 18-INCH WIDTH
Leeann.Bush Rectangle
A-9
B I D S C H E D U L E Account: ALL
Project No: WA NPS PRES 15(2)
Name: Pavement Preservation Olympic Phase II CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Schedule Total: ________________________
Submitted by: _________________________
63503-0700 Line A0950 93,000 LNFT $ $
63504-1000 Line A1000 300 SQFT $ $
63506-0600 Line A1050 200 HOUR $ $
63507-0800 Line A1100 30 DAY $ $
63509-1000 Line A1150 1,500 FXHR 56.00$ 84,000.00$
TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
TEMPORARY TRAFFIC CONTROL, FLAGGER
TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
TEMPORARY TRAFFIC CONTROL, PILOT CAR
B-1
Solicitation Provisions
Federal Acquisition Regulation
Representations, Certifications and Other Statements of Offeror
To the extent that any of the following Provisions may be in conflict with the Provisions in the IDIQ contract, the following Provisions will control.
The Offeror Makes the Following Representations and Certifications as a Part of its Offer.
52.203-98, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements-Representation (DEVIATION 2015-02) (Feb 2015)
(a) In accordance with section 743 of Division E, Title VII, of the Consolidated and Further Continuing Resolution Appropriations Act, 2015 (Pub. L. 113-235), Government agencies are not permitted to use funds appropriated (or otherwise made available) under that or any other Act for contracts with an entity that requires employees or subcontractors of such entity seeking to report fraud, waste, or abuse to sign internal confidentiality agreements or statements prohibiting or otherwise restricting such employees or subcontractors from lawfully reporting such waste, fraud, or abuse to a designated investigative or law enforcement representative of a Federal department or agency authorized to receive such information.
(b) The prohibition in paragraph (a) of this provision does not contravene requirements applicable to Standard Form 312, Form 4414, or any other form issued by a Federal department or agency governing the nondisclosure of classified information.
(c) Representation. By submission of its offer, the Offeror represents that it does not require employees or subcontractors of such entity seeking to report fraud, waste, or abuse to sign internal confidentiality agreements or statements prohibiting or otherwise restricting such employees or subcontractors from lawfully reporting such waste, fraud, or abuse to a designated investigative or law enforcement representative of a Federal department or agency authorized to receive such information.
52.204-8 Annual Representations and Certifications. (Apr 2016)
(a) (1) The North American Industry Classification (NAICS) code for this solicitation is 237310 – Highway, Street & Bridge construction.
(2) The small business size standard is $36.5 million.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
Completing FAR provision 52.204-8 Annual Representation and Certifications.
• This solicitation is issued under NAICS 237310 – Highway, Street & Bridge Construction with a small business size standard of $36.5 million. If your average annual gross receipts for the past 3 years are above $36.5 million you are a large business for this solicitation. If they are below $36.5 million you are a small business. Please complete the certification listed in paragraph (d).
• Before submitting bids, please ensure you have completed your annual representations and certifications electronically at the System for Award Management (SAM) website: https://www.sam.gov/portal/public/SAM/.
B-2
(b) (1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7 is not included in this solicitation, and the offeror is currently registered in the System for Award Management, and has completed the Representations and Certifications section of SAM electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:
[__] (i) Paragraph (d) applies.
[__] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c) (1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(iv) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(v) 52.209–2, Prohibition on Contracting with Inverted Domestic Corporations— Representation.
(vi) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(vii) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.
(viii) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(ix) 52.215-6, Place of Performance. This provision applies to solicitations…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .