Stormwater Pollution Prevention Plan s
For:
South of Big Sandy, MT DOT 236(1) Chouteau County, Montana
Federal Highway Administration, Western Federal Lands Highway Division
Project Engineer:-----------
General Contractor: ----------of
. SWPPP/ESCP
TAB 1: SWPPP/ESCP Narrative
TAB 2: NPDES Permit (Construction Gene1·al Permit or Corresponding State Permit)
TAB 3: NOI, EPA/State Acknowledgement, Other Applicable EPA/State Correspondence
TAB 4: Delegation of Authority
TAB 5: Maps
TAB 6: Erosion/Sediment Control Plan Sheets (plan set and BMP typical details)
TAB 7: Permanent Stabilization and Revegetation Plan(plan sets and details)
TAB 8: SWPPP Amendment Log
TAB 9: Erosion/Sediment Control Inspection Reports and Requirements
TAB 10: Corrective Action Log
TAB 11: Water Quality Monitoring, Reporting Requirements, and Reports
TAB 12: Training Log
TAB 13: Waste and/or Borrow Site Information
TAB 14: Grading and Stabilization.Log
TAB 15: Hazardous Spill Plan
TAB 16: Other Applicable Permits(§ 404, § 401, Oregon Remove-Fill Permit)
TAB 17: NPDES Quality Assurance Checklist
TAB 18: NPDES Notice of Termination (NOT)
CONTRACTOR:
Complete SWPPP narrative in accordance with contract 107.0lA(b).
Revise SWPPP narrative as needed throughout construction in accordance with contract 107.0-lA(f)
ALASKA, IDAHO AND WASHINGTON PROJECTS ONLY:
SWPPP narrative must be signed by General Contractor's responsible corporate officer as defined in CGP 1.11.2.
File approved SWPPP narrative i~ Tab 1.
For Construction Activities at:
Project Name:
Project Site Location:
City, County, State, Zip Code:
SWPPP Prepared for:
Organization Name:
Address:
Telephone Number:
SWPPP Prepared by:
Company/Organization:
Address:
Telephone Number:
MT 236 South of Big Sandy
HWY236
Big Sandy, Chouteau County, Mt 59520
FHWA, Western Federal Lands Highway Division
610 East Fifth Street
Vancouver, WA 98661-3801
360-619-7700
Hamed Hakimelahi, EIT, ENV SP
Parsons Brinckerhoff
851 SW Sixth A venue, P01tland, Oregon, 97204
(503) 417-9354
SWPPP Preparation Date: 03/02/2016
Estimated Project Dates:
Project Start Date: 06/06/2016 Project Completion Date: 09/18/2017
Estimated Revegetation Date: 10/15/2018
TAB 1:
TAB2:
TAB3:
TAB4:
TABS:
TAB6:
TAB7:
TABS:
TAB9:
TAB 10:
TAB 11:
TAB 12:
TAB 13:
TAB 14:
TAB 15:
TAB 16:
TAB 17:
TAB 18:
SWPPP TABs (SWPPP Inclusions)
SWPPP/ESCP Narrative
NPDES Permit (Construction General Permit or Corresponding State Permit)
NOi, EPA/State Acknowledgement, Other Applicable EPA/State Correspondence
Delegation of Authority
Maps
Erosion/Sediment Control Plan Sheets (plan set and BMP typical details)
Revegetation Plan (if applicable)
SWPPP Amendment Log
Inspection Reports
Corrective Action Log
Water Quality Monitoring, Reporting Requirements, and Reports (if applicable)
Training/Certification Log
Government-Selected Waste, Borrow, Staging Sites
Grading and Stabilization Log
Hazardous Spill Plan or SPCC
Threatened and Endangered Species and Historic Preservation (Section 106) Documentation
NPDES Quality Assurance Checklist
NP DES Notice of Termination (NOT)
SWPPP/ESCP NARRATIVE
SECTION 1: RESPONSIBLE PARTIES/CONTACT INFORMATION
1.1 Operator(s):
1.2 Construction Site SWPPP Contact(s):
1.3 SWPPP J>repared by:
1.4 NPDES Storn1\vater Permit
1.5 SWPPP Administrator
1.6 Permitting Authority for FHWA/WFLHD Projects
SECTION 2: PROJECT INFORMATION
2.1 Project Narne and Location
2.2 Project Site Characteristics
SECTION 3: NATURE OF CONSTRUCTION ACTIVITY
3.1 General Description of Project and Scope of Work:
3.2 Sequence and Estimated Dates of Construction Activities
3.3 Potential Sources of Pollutants
SECTION 4: SITE MAPS
SECTION 5: DISCHARGES
5.1 Allowable Non-Stormwater Discharges
5.2 Receiving Waters:
5.3 Water Quality Monitoring Requirements
SECTION 6: COMPLIANCE WITH OTHER APPLICABLE REQUIREMENTS
6.1 Endangered Species Protection
6.2 Historic Preservation
6.3 Safe Drinking Water Act Underground Injection Control Requirements
SECTION 7: EROSION AND SEDIMENT CONTROLS
7.1 Natural Buffers or Equivalent Sediment Controls
7 .2 Perimeter Controls
7 .3 Sediment Track-Out
7.4 Stockpiled Soil or Other Erodible Materials
7.5 Minimize Dust .................................................................. , [i]
7.6 Minhnize Disturbance of Steep Slopes
7.7 Topsoil Conservation
7 .8 Minin1ize Soil Compaction
7.9 Storm Drain Inlets and Culvert Inlets
7.10 Constructed Stormwater Conveyance Channels and Cu Ive rt Outlets
7 .11 Sediment Basins
7.12 Chemical Treatn1ent
7 .13 J)ewateriug P ractices
7 .14 Erosion Control and Stabilization
7.15 Removal of BMPs
7 .16 Post Construction Measures
SECTION 8: OPERATIONAL CONTROLS/GOOD HOUSEKEEPING MEASURES ... 33
8.1 IIazardous Spill Plan
8.2 Spills/Releases in Excess of Reportable Quantities
8.3 Equipment!V chicle Fueling and Maintenance Practices
8.4 Equipment!Vehicle Washing
8.5 Material Handling and Waste Managen1ent
8.6 Designate Concrete Washout Areas
SECTION 9: INSPECTIONS
9 .1 Inspection Frequency
9.2 Corrective Actions
SECTION 10: DELEGATIONS OF AUTHORITY
SECTION 11: Sl'AFF TRAINING
SECTION 12: CERTIFICATION AND NOTIFICATION
[ii]
1.1 Operator(s):
Organization Name:
Address:
Telephone Number:
Contractor and
FHWA, Western Federal Lands Highway Division (WFLHD 610 East Fifth Street Vancouver, WA 98661-3801 360-619-7700
Note: Fill in all incomplete information following contract award date and prior to start of construction
1.2 Construction Site SWPPP Contact(s):
FHWA Contact Name:
Title:
Address:
Telephone Number:
General Contractor, Company:
(complete for all States) Erosion Control Supervisor Name:
(complete for all States) Address:
Telephone Number:
Keith Wong
610 East Fifth Street, Vancouver, WA 98661 360-619-7547
TBD
TBD
TBD
TBD
1.3 SWPPP Prepared by:
Organization/Company:
Name, Position:
Role/Responsibility Telepllone Number:
Email:
Name, J>osition:
Role/Responsibility Telephone Number:
Email:
Hamed Hakimelahi, Civil/ Water Resources Designer
(593) 417-93 54 c Hakimelahih@pbworld.com
Naidu, Nagaraju Designer 206-826-8610 N aiduN"@pbworld.com
1.4 NPDES Stormwater Permit
The Applicable EPA/State NPDES Stormwater Pe1mit is located in TAB 2. The Project NOI and EPA/State Acknowledgement \Vith NPDES Tracking Number is located in TAB 3.
[I)
1.5 SWPPP Administrator
The General Contractor (section 1.2) is responsible for maintaining the project SWPPP of Record. The General Contractor will provide a qualified Erosion Control Supervisor, who is responsible for managing the installation, maintenance, inspection, and repo1iing for erosion and sediment control measures, shall maintain and update the project SWPPP of Record and prepare all documentation required by the project NPDES stormwater permit and SWPPP.
The Erosion Control Supervisor (ECS) is identified in section 1.2 and his/her qualifications are documented in TAB 12.
The FHW A/WFLHD Project Engineer (PE) is the duly authorized representative of the FHW A for the purpose of overseeing compliance with the NPDES storm water permit and SWPPP at the construction site. See Delegation of Authority TAB 4.
All SWPPP documentation, revisions/updates, and reports will be approved/signed by both the General Contractor's ECS and the FHWA PE.
1.6 Permitting Authority for FHW A/WFLHD Projects
Delivery Confirmation documentation of the NOI is located in TAB 3.
The applicable EPA/State NPDES permit is located in TAB 2
Idaho and Washington, Environmental Protection Agency EPA Region 10
Alaska Department of Environmental Conservation (ADEC)
Montana Department of Environmental Quality (.fytDEQ)
Oregon Department of Environmental Quality (ODEQ)
Wyoming Depm1ment of Environmental Quality (WDEQ)
State Permitting Authoritv Alaska • ADEC is permitting authority for most discharges within the state EXCEPT for:
• EPA is the permitting authority for the Denali National Park and Preserve and Metlakatla Indian Reservation .
Idaho • EPA is permitting authority for discharges within the state.
Montana • MDEQ is permitting authority for most discharges within the state EXCEPT for:
• EPA is the permitting authority for Indian Country lands within the state .
Oregon • ODEQ is permitting authority for most discharges within the state EXCEPT for:
• EPA is the pennitting authority for Indian Country lands within the state .
Washington • WOE is permitting authority for most discharges within the state EXCEPT for:
• EPA is permitting authority for Federal Operators and Indian Country lands within the state
Wyoming • WDEQ is permitting authority for most discharges within the state EXCEPT for:
• EPA is the permitting authority for lndian Country lands within the state
The NOi for Alaska projects (through the ADEC) can be filed electronically at Alaska Pollutant Discharge Elimination System Program website. The completed SWPPP will be submitted to either ADEC or the Municipality based on the project type and operator described in the ADEC CGP.
The NOi for projects in Idaho, Washington, Denali NP and Metlakatla Indian Reservation can be filed electronically at The EPA website.
The NOi for Montana can be filed through MDEQ following guidance at this website.
[21
Oregon DEQ authorizes FHW A/WFLHD projects under the programmatic 1200-CA permit, (expired in 12/31/2005, administratively extended)
The NOl for Wyoming can be filed electronically at this website.
[3]
Section 2: Project Information
2.1 Project Name and Location
This basic site information is used to file for National Pollutant Discharge Elimination System (NPDES) permit coverage. Pennit coverage is obtained by filing the Notice of Intent (NOI) after the SWPPP is complete.
Project Name: MT 236 South of Big Sandy
Project Site HWY 236 Location:
City, County, State, Zip Code:
Big Sandy, Chouteau County, Mt 59520
Latitude/Longitude (Using one of three possible fonnats) 1
Latitude: Longitude:
1. 48°00'27.66" N (degrees, minutes, seconds) 1. I 09°56'42" W (degrees, minutes, seconds)
2. 48°00. 46100' N (degrees, minutes, decimal) 2. 109°56. 70000' W (degrees, minutes, decimal)
3. 48.0076833° (decimal) 3. -I 09.9450000 ° (decimal)
The method used for determining latitude/longitude was: Other Website
Meridian: Montana Township: 24 N, 25N & 26N
Range: 14E & 15E
Section: Numerous ls the project located in Indian country? No
If yes, the name of Reservation is:
Name of Reservation:
Are you applying for permit coverage as a "federal operator?" No
The project Does Not discharge stormwater into a Municipal Separate Storm Sewer System?
1 Detailed information on determining the site's latitude and longitude can be found at:
www.epa.gov/npdes/stormwater/latlong
[4]
2.2 Project Site Characteristics
The undeveloped site and features of the land that are incorporated into the final soil Erosion and Sediment Control plan sheets (TAB 6) , as well as natural resources that should be protected are described below:
Vegetation, trees, and sensitive areas, such as stream buffers, wetlands, highly erodible soils, and steep slopes at the site include:
Types:
Soils: Based on Geotechnical Engineering report on 2010, the road top surface is mainly mixed with clay and silt from the subgrade. No highly erodible soils are identified.
Project is located in rural area with no apparent environmentally sensitive areas. · Per USGS soil survey report the majority of soils are well drained Telstad-Joplin Loams with high contents of clay and silt fines. Majority of the site (55%) has slight erosion hazard and 6% of total project site area has severe erosion hazard.
Also, see TAB 6
Stonnwater currently drains from the site in the following manner, The Stormwater, sheet flows to both side of nom1al crown ofroadway into side swales and conveyed to nearest stream/creek crossings. Stream crossings are generally flowing from east to west and contributory to Eagle creek and Chip creek that are tributary to Missouri river.
There are seven (7) existing roadway cross culverts along the stream crossings within the project limits. Two major crossings each one on the Eagle Creek and Chip Creek and two minor culverts at Chip Creek and the other three culverts are located at the unnamed tributaries. See Tab 5 for Maps for cross culvert locations and pictures of each location. The size and length of cross culve1ts wpuld accommodate without requiring any modifications. Minor grading adjustments are anticipated the side slopes of the roadway and at culvert inlet and outlet locations.
All existing culverts will be protected by silt fence, sediment wattle, and turbidity barriers at outlet of stream crossings.
Also, see TAB 6
The location of discharge points or areas
Fallowing are list of outfalls where concentrated runoff outfalls to receiving waterbody
[5]
T}'l>t• l>i~drnrgc
Size (i)p.:n Munidp:tl Descl"ihe Fhm1rnth l{eccMng Otllfall (i1pJtt'D.'\ima1~ ''"'"""''· Storm Sewer (frnut iJu1fr1{l hJ munt"il h • .'t'i.:ivi1tg ~u{ttcc Witk:t if Surface Water 1 Number ~cn.·age fr<.'."ln pip~. mkL (Vcs/J\'u. ifyL~~ do\!~ not di~;,,·hargc thrci:Uy lntn tfh.~ nmni;.•d n~i-m~d t.ir;.frn;:agc d1}\\-1
:iht.! drnhtt'i:!.J :-;h-i.:.•t..·t. flow. prtP>i de l.;)i'at!or. of fl!\.'t:iv?ng :;ttrfaci: W-Jt('.f. indudi: um12mcd dmimigi:_.,i f1vm ,it~.) n-1hl!r- 1:tatitt!\it:
~pt:i:ifyt
001 Shee! NO Stormwater sheet Oows to existing culvert Unknown
Flow that crosses the road.
Site visit can provide more information on the drainage p<ittem
002 Shee1 NO Slormwater sheet flows lo existing culvert Eagle Creek Flow that crosses tho road.
Sile visit can provide more information on the drainage pattern
003 Shee! NO Stormwater sheet flows to existing culvert Unknown Flow that crosses tho road.
Site visit can pro\/ide more information on the drainage pattern
004 Sheei NO Stormwater sheet f!o·ws to existing culvert Unknown Flow that crosses the mad.
Site visit can provide more information on the
005 Sheet Stormwater sheet flows to existing culvert Chip Creek Flow that crosses the road.
Site visit 1;an provide more information on the
006 Sheet NO Chip Creek Flow
007 Sheet NO Chip Creek Flow
Also see TAB 6
The location of all waters, including wetlands, are shown on the site map located in
TABs 5 and 6.
Critical slopes and slope lengths include:
Locations: a small portion of the corridor has >5% longitudinal slopes with a potential to generate erosive velocities. Final design drawings shall identify such locations within the side swales and provide necessary counter measures such as rip-rap and rock check dams to prevent swale and side bank erosion
Soil type(s) of highly erodible soils and the soils' infiltration capacity are identified as,2
From Geotechnical report and USGS soil survey maps <6% of the soils are defined as highly erodible soils. All ground disturbing activity shall be contained with
Access the Natural Resources Conservation Service Web Soil Survey.
[6] perimeter silt fence to prevent sediment transport to downstream locations of the project.
Any past soil contamination at the site is identified as, No known soil contamination repo11s at the site.
The following natural features, including trees, streams, wetlands, slopes and other features to be protected includes:
Also see TAB 6
Protected Natural Features:
Project activities are primarily paving the existing gravel road with minor grade refinements. No impacts are proposed to any existing natural streams and wetlands nor a need for protecting existing steep slopes are identified within the project corridor.
Measures to protect these features:
NIA
Mean Annual Precipitation at the Project Site: 12.79 inches
The frequency, intensity, and duration of rainfall for the project site, which are the principal factors influencing erosion from a construction site, are described as, The 2-year, 24-hour storm event:3
0.18 inches
The I 0-year, 24-hour stonn event:
0.26 inches
The 25-year, 24-hour storm event:
0.34 inches
3 Precipitation frequency for Western States
[7]
Alaska Projects Only, Approximate Growing Season at the Project Site: Click here to enter text.
[8]
3: re
3.1 General Description of Project and Scope of Work:
(i.e. highway construction, roadway realignment, highway and bridge reconstruction, etc.) is described below:
The project consist of reconstruction of an existing 14 miles of gravel road. The project includes adding two lanes with shoulders; improving horizontal and vertical curve; upgrading guardrail, pavement marking, signing and fencing.
The type or function of the project is: Road Construction
Construction Support Activities: If applicable, describe any construction support activities such as dedicated concrete or asphalt batch plants, dedicated aggregate sites, equipment staging yards, material storage areas, borrow, or disposal sites (government-selected sites):
It is expected to have asphalt batch, equipment staging yard and material storage area on site, as design progresses potential staging areas will be identified and the contractor shall obtain all necessary permits and responsible to update SWPPP activity log.
Minimal cut and fill activity is anticipated. No disposal site is expected for this project, because the cut material is limited and shall be reused for minor filling activity
NOTE: All Contractor-selected sources and support sites are the sole responsibility of the General Contractor. The SWPPP and NPDES permitting for Contractor-selected sites and sources are separate from this documentation (SCR 107.0lA(h)).
Support activities are located on the general vicinity map and/or site map in 5 6.
Size of the Construction Project:
(Including all Government-selected support sites such as staging, b01Tow, waste, access roads, etc.)
Estimated Area
Total project area (within ROW or Construction limits):
Construction site area to be disturbed:
Percent Impervious Area BEFORE Construction: 0.00 %
Runoff Coefficient BEFORE Construction: 0.8
Percent Impervious Are AFTER Construction:
Runoff Coefficient AFTER Construction:
[9]
100 %
0.9
[ 10]
3.2 Sequence and Estimated Dates of Construction Activities
The intended construction sequencing and timing of major construction activities is detailed here, including the phased grading and stabilization activities used to minimize overall amount of disturbed soil.
Phase: TBD
' Construction seguence descri~tion: Duration of seguence: BMPs associated with this seguence: Stabilization measures:
Erosion Control BMPS such as Silt
Project Construction 180 days 1 Fence, Construction Entrance, TBD ' Wattles, turbidity barriers, compost berms.
Phase:
Construction seguence descri~tion: Duration of seguence: BMPs associated with this seguence: Stabilization measures:
to enter text enter lCXL
Phase:
Construction seguence descri.Qtion: Duration of seguence: BMPs associated with this seguence: Stabilization measures:
[I I]
I I l
I I
I I i l I
I l
I to enter text. text.
Phase:
Construction sequence description: Duration of sequence: BMPs associated with this sequence: Stabilization measures:
here to enter enter text.
[12] g c ·:::
"J::
<.J
"C ..
ti ...
tJ')
[g]
[g] rgj rgj
3.3 Potential Sources of Pollutants
The follow table identifies all potential sources (checked activities in column 1) of sediment and other sources of pollution, which may reasonably be expected to affect the quality of stormwater discharges from the construction site.
Potential Construction Site Pollutants
Construction Activity "' ,S "' - i:: "' "" .:!l .:!l <.> :;;;: ~ ~ "' "' o\1 "C = ·c "' "' E ·5 .: oO:l .:: ·- ~ ... .... -,,., ,_ > ., :::>
:0 " ..~ "' "' .:: = ... i "' ::c 0 .... '"' '"' "' - 0 tJ') ~ 0. ,.... Cl c... ::c Oi:i.
Clearing, excavating, and grading x x Fill of roadway embankment, backfill at structures x x Vehicle/equipment fueling and maintenance x x x Vehicle/equipment use and storage x x Sanitary/septic waste x x [§j Dewatering operations x x Drilling and blasting operations x x rgj
.8l
Concrete washout and waste x x Structure construction/painting/cleaning x x x Demolition and debris disposal x x x Solid waste (trash and debris) x Hazardous waste or contaminated spills x Paving operations x x Landscaping operations x x x Mining, rock extraction, crushing x x x
Contractor and PE
Note: Fill in all incomplete infonnation following contract award date and prior to start of construction
Construction and waste material expected to be stored on-site includes:
Material
TBD by Contractor
[ 13]
Storage Location x x x x x x
Section 4: Maps
Vicinity maps are located in TAB 5. Site maps and erosion and sediment control plan maps are located in TAB 6.
[14]
Industrial stormwater discharges associated with industrial activity other than construction at the site (including dedicated asphalt plants and dedicated concrete plants that are covered by this permit) include:
NOTE: An Industrial Activity Multi-Sector General Permit may be required for some activities.
2.
3.
Industrial Activity
1. NIA
Stormwater Discharge Location
5.1 Allowable Non-Stormwater Discharges
Multi-Sector General Permit Number (if applicable)
Non-stormwater discharges used at the construction sited are identified below, along with control measures used to eliminate or reduce the discharges and BMPs used to prevent stormwater contamination.
Applicable to this Project
(check all that apply)
D
D D D
• D
• D
Potential Non-Stormwater Discharges
Waters used to wash vehicles where detergents are not used
Water used to control dust
Potable water including uncontaminated water line flushings
Construction dewatering (uncontaminated)
Ground water or spring water (uncontaminated)
Routine external building wash down that does not use detergents
Pavement wash waters where spills or leaks of toxic or hazardous materials have not occurred (unless all spilled material has been removed) and where detergents are not used
• Foundation or footing drains where flows are not contaminated with process materials such as solvents
• Landscape irrigation
(15]
Control Measures
Process water shall be treated to remove hazardous chemicals including hydrocarbons and cleaning chemicals prior to discharging to state waters. See Tab 2 CGP permit for appropriate counter measures.
Water sprinkler tankers shall spray water as needed during construction activities as needed. Runoff from site is not anticipated due to this activity.
NIA
NIA
NIA
NIA
Secondary containment must be used for any hazardous chemicals storage.
See Tab2 CGP permit for appropriate . counter measures.
• D • Discharges from emergency fire-fighting activities
• D • Fire hydrant tlushings
• [?SJ • Uncontaminated air conditioning or compressor NIA condensate
NOTE: The likely locations of these discharges are identified on the site map TAB 5 and/or
TAB6
5.2 Receiving Waters:
Are there any surface waters located within 50 feet of the construction disturbance? Yes
Name(s) of the first surface water that receives stormwater directly from your site and/or from the MS4
I .Eagle Creek
2.Chip Creek
3.
4.
Impaired Waters/TDMLs:
Answer the following for each surface water listed in Table 1:
What pollutant(s) is water listed as causing the been "impaired?" impairment? completed?
Yes D No lZl Yes D No lZl
!··--········r····-·-
N O !Zl
YesD NoO
Pollutant(s) for which there is a TDML
Source used to determine whether or not your project discharges into an impaired water:
Click here to enter text.
Tier 2, 2.5 or 3 Waters Answer the following for each surface water listed in Table 1:
Is this surface water designated as Tier 1,2 or 3?
1. Yes D No !Zl
2. Yes D No lZl
3. YesD NoO
If yes, specify which Tier.
Choose an item.
Choose an item.
Choose an item.
[16]
If applicable, documentation of consultation with State or Federal TMDL authorities on consistency of SWPPP conditions with the approved TMDL is found in TAB 11. The control measures required to ensure that discharge of pollutants from the site are consistent with the assumptions and requirements of the EPA-established or approved TMDL, including any specific waste-load allocations are included in that documentation.
5.3 Water Quality Monitoring Requirements
Provisions in Permit Conditions of the applicable NPDES stormwater permit, as well as the associated §401 certification or other special conditions, define additional monitoring and reporting requirements. Details about water quality monitoring and reporting requirements applicable to this project are included in TAB 11.
Samples and measurements taken for the purpose of monitoring will be representative of the monitored activity. Records of all monitoring information will be retained in TAB 11, including all calibration and maintenance records and all original strip chart recordings for continuous monitoring instrumentation.
Records of monitoring information will include:
1. The date, exact place, and time of sampling or measurements;
The individual(s) who performed the sampling or measurements;
3. The date(s) analyses were performed
4. The individual(s) who performed the analyses;
5. The analytical techniques or methods used; and
6. The results of such analyses.
[I 7]
Section 6: Compliance Other Applicable Requirements
6.1 Endangered Species Protection
Under which criterion is project eligible for Endangered Species coverage under the NPDES permit (EPA)?
~A e c Do DE
Criterion A.
Criterion B.
Criterion C
Criterion D.
No federally-listed threatened or endangered species or their designated critical habitat(s) are likely to occur in your site's "action area" as defined in Appendix A of EPA permit.
The construction site's discharges and discharge-related activities were already addressed in another operator's valid certification of eligibility for your action area under eligibility Criterion A, C, D, E, or F and there is no reason to believe that federally-listed species or federally-designated critical habitat not considered in the prior certification may be present or located in the "action area". To certify your eligibility under this Criterion, there must be no lapse ofNPDES permit coverage in the other operator's certification.
By certifying eligibility under this Criterion, you agree to comply with any effluent limitations or conditions upon which the other operator's certification was based. You must include in your NOI the tracking number from the other operator's notification of authorization under this permit. If your certification is based on another operator's certification under Criterion C, you must provide EPA with the relevant supp01iing information required of existing dischargers in Criterion C in the EPA NOI fonn.
Federally-listed threatened or endangered species or their designated critical habitat(s) are likely to occur in or near your site's "action area," and your site's discharges and discharge-related activities are not likely to adversely affect listed threatened or endangered species or critical habitat. This determination may include consideration of any stormwater controls and/or management practices you will adopt to ensure that your discharges and discharge-related activities are not likely to adversely affect listed species and critical habitat. To make this certification, you must include the following in your NOI: 1) any federally listed species and/or designated habitat located in your "action area"; and 2) the distance between your site and the listed species or designated critical habitat (in miles). You must also include a copy of your site map with the
NOI.
Coordination between you and the Services has been concluded. The coordination must have addressed the effects of your site's discharges and discharge-related activities on federally-listed threatened or endangered species and federally-designated critical habitat, and must have resulted in a written concurrence from the relevant Service(s) that your site's discharges and discharge-related activities are not likely to adversely affect listed species or critical habitat. You must include copies of the
[18]
Criterion E.
Criterion F.
correspondence between yourself and the Services in your SWPPP and
NOL
Consultation between a Federal Agency and the U.S. Fish and Wildlife Service and/or the National Marine Fisheries Service under section 7 of the ESA has been concluded. The consultation must have addressed the effects of the construction site's discharges and discharge-related activities on federally-listed threatened or endangered species and federally designated critical habitat. The result of this consultation must be either:
I. a biological opinion that concludes that the action in question (taking into account the effects of your site's discharges and discharge-related activities) is not likely to jeopardize the continued existence of listed species, nor the destruction or adverse modification of critical habitat; or
II. written concurrence from the applicable Service(s) with a finding that the site's discharges and discharge-related activities are not likely to adversely affect federally-listed species or federally-designated habitat.
You must include copies of the correspondence between yourself and the Services in your SWPPP and NOL
Your construction activities are authorized through the issuance of a permit under section 10 of the ESA, and this authorization addresses the effects of the site's discharges and discharge-related activities on federally listed species and federally-designated critical habitat. You must include copies of the correspondence between yourself and the Services in your SWPPP and NOi.
Support Documentation for Endangered Species criterion eligibility is filed in TAB 16.
6.2 Historic Preservation
1. Will the project involve installation of any of the following stormwater controls that entail subsurface earth disturbance? Yes
D Dike
Be1m
D Catch Basin
D Pond
D Ditch, trench, swale, perimeter drain, etc.
~ Culvert
D Other ground-disturbing st01mwater control Click here to enter text.
If the project involves no installation of earth-disturbing stonnwater controls, then no further historic preservation screening is necessary (for NPDES permitting purposes).
2. If answer to step 1 is Yes, have professional surveys or evaluations determined that historic properties do not exist (or have prior disturbances at the site precluded the existence of historic properties)? Yes
Provide documentation for the basis of this determination. Click here to enter text.
[191
3. If answer to step 2 is No, have professional surveys or evaluations determined that installation of stormwater controls will have no effect on historic properties?
Provide documentation for the basis of this determination. Click here to enter text.
4. Has the State Historic Preservation Officer (SHPO), Tribal Historic Preservation Office (THPO) or other tribal representative concurred with the dete1111inations of effects on historic properties? Yes
Provide the nature of their response. No Affected Properties
6.3 Safe Drinking Water Act Underground Injection Control Requirements
Will the project plan install any of the following controls? No
Check all that apply:
D Infiltration trenches (if stormwater is directed to any bored, drilled, driven shaft or dug hole that is deeper than is widest surface dimension, or has a subsurface fluid distribution system)
D Commercially manufactured pre-cast or pre-built proprietary subsurface detention vaults, chambers, or other devices designed to capture and infiltrate stormwater flow.
D Drywells, seepage pits, or improved sinkholes (if stormwater is directed to any bored, drilled, driven shaft or dug hole that is deeper than its widest surface dimension, or has a subsurface fluid distribution system)
If yes, provide documentation of communications with the EPA or applicable State agency.
Click here to enter text.
[20]
7:
Control measures at the construction site are selected, installed, implemented, and maintained to minimize pollutants in the discharge as necessary to meet applicable water quality standards.
The objectives of this SWPPP include:
• Stabilize the site as soon as possible (targeting the preparation and implementation of erosion and sediment controls to get the site to final grade, and either permanently or temporarily stabilize all bare soil areas as soon as possible).
• Perimeter controls will be installed before ground disturbing activities are initiated.
• Perimeter protection will remain in place until final stabilization has been achieved.
• Slopes and channels will be protected by conveying concentrated stormwater runoff around the top of slopes and stabilize slopes as soon as possible. A void disturbing natural channels and the vegetation along natural channels as much as possible.
• Divert stom1water coming on to the site by conveying it safely around, through, or under the work area. (Divert the clean water, trap the dirty water.)
• Protect receiving waters and other environmentally sensitive waters or areas adjacent to the site.
• Follow pollution prevention measures by providing proper containers for waste and garbage at the site. Store hazardous materials and chemicals so that they are not exposed to stormwater.
• Minimize the area and duration of exposed soils. Clear only land that will be under construction in the near future.
7.1 Natural Buffers or Equivalent Sediment Controls (Required for EPA CGP states only - ID, WA)
This section only applies if a surface water is located within 50 feet of the project's earth disturbing activities.
Are there any surface waters within 50 feet of the project's earth disturbances? Yes
If No, then no further documentation is required for the SWPPP.
NOTE: Reference EPA CGP appendix G for buffer guidance.
If Yes, check which natural buffer compliance alternative is used at the project site:
IX! The project will provide and maintain a 50-foot wide undisturbed natural buffer.
The location and width of natural buffers are shown on the Erosion and Sediment Control Plan sheets in TAB 6.
[21]
D The project will provide and maintain an undisturbed natural buffer that is less than 50 feet in width and is supplemented by additional erosion and sediment controls, which in combination achieves the sediment load reduction equivalent to a 50-foot undisturbed natural buffer.
The location of natural buffers are shown on the Erosion and Sediment Control Plan sheets in TAB 6.
Insert the width of the natural buffer to be retained Click here to enter text.
Insert description of additional erosion and sediment controls to be used in combination with the natural buffer: Click here to enter text.
Document the method used to determine that the above combination of natural buffer and sediment and erosion controls equal the estimated sediment removal capacity of a 50-foot undisturbed natural buffer: Click here to enter text.
D It is infeasible to provide and maintain an undisturbed natural buffer of any size, therefore, the project will implement erosion and sediment controls that achieve the sediment load reduction equivalent to a 50-foot undisturbed natural buffer.
Insert rationale for concluding that providing and maintaining a natural buffer of any size is infeasible: Click here to enter text.
Insert description of erosion and sediment controls to be used to achieve the sediment load reduction equivalent to a 50-foot undisturbed natural buffer: Click here to enter text.
D The project qualifies for one of the exceptions in EPA CGP Part 2. l .2.1.e
D For a "linear project'', site constraints (e.g. limited right of way) make it infeasible for the project to meet any of the CGP part 2.1.2.1.a compliance alternatives.
D Other exception (state type): Click here to enter text.
Document why it is infeasible to meet one of the buffer compliance alternatives: Click here to enter text.
Insert description of erosion and sediment controls to be used to achieve the sediment load reduction equivalent to a 50-foot undisturbed natural buffer: Click here to enter text.
[22]
7.2 Perimeter Controls
All Perimeter Sediment Controls will be installed prior to ground disturbing activities taking place. There will be no clearing or grubbing outside the physical clearance limits.
Locations and design specifications of BMPs are shown on the erosion and sediment control plan sheets in TAB 6.
The following perimeter controls will be implemented:
Control measure: Silt Fence
Implementation: The silt fence shall be functional before other land disturbing activities take place.
Maintenance requirements: Remove sediment before it has accumulated to one-half of the above-ground height of the silt fence. It is the Contractor's responsibility to upgrade erosion control measures as necessary if the sediment controls are ineffective and turbid water is observed discharging from the site.
Control measure: Straw Wattle
Implementation: The straw wattles shall be functional before other land disturbing activities take place.
Maintenance requirements: Remove sediment before it has accumulated to one-half of the above-ground height of the straw wattles. It is the Contractor's responsibility to upgrade erosion control measures as necessary if the sediment controls are ineffective and turbid water is observed discharging from the site.
Add other measures as needed.
7 .3 Sediment Track-Out
The following methods will be implemented to minimize off-site vehicle tracking of sediment onto paved surfaces. If sediment escapes the construction site, off-site accumulations of sediment will be removed at a frequency sufficient to minimize off-site impacts.
Locations and design specifications of BMPs are shown on the erosion and sediment control plan sheets in TAB 6.
Not applicable to this project. Reason: Click here to enter text.
If applicable:
Control measure: Temporary construction access
Implementation: Temporary construction access will be installed at the beginning of construction and will provide access to and from the sites. Vehicle use will be restricted to designated construction entrances to minimize the tracking out of sediment.
[23]
Maintenance requirements: Where sediment has been tracked-out from the site onto the surface of off-site streets, other paved areas, and sidewalks, remove the deposited sediment by the end of the same work day in which the track-out occurs or by the end of the next work day if track-out occurs on a non-work day. Remove the track-out by sweeping, shoveling, or vacuuming these surfaces, or by using other similarly effective means of sediment removal. Hosing or sweeping tracked-out sediment into any stormwater conveyance (unless it is connected to a sediment basin, sediment trap, or similarly effective control), storm drain inlet, or surface water is prohibited.
Control measure: Click here to enter text.
Implementation: Click here to enter text.
Maintenance requirements: Click here to enter text.
Add other measures as needed.
7.4 Stockpiled Soil or Other Erodible Materials
Stockpile management includes measures to minimize surface erosion and sediment transport from soil stockpiles or other erodible materials.
Locate erodible stockpiles away from drainages including stom1 sewer inlets and culvert inlets.
Locations of stockpiles are shown on the erosion and sediment control plan sheets in TAB 6.
Not applicable to this project. Reason: Click here to enter text.
If applicable:
Control measure: Plastic sheets
Implementation: All the soil stockpiles or other erodible materials should be covered by plastic all the time.
Maintenance requirements: Contractor should check the plastic cover frequently to make sure the soil or other erodible material is covered all the time.
Control measure: Click here to enter text.
Implementation: Click here to enter text.
Maintenance requirements: Click here to enter text.
Add other measures as needed.
7 .5 Minimize Dust
Dust control includes practices used to reduce or prevent the surface and air transport of dust during construction
D Not applicable to this project. Reason: Click here to enter text.
[24]
If applicable:
Control measure: Water Tank Sprinkler
Implementation: The construction area should be wet during the contraction time. On weekends and when the construction is stopped the ground should be wet at least once a day. Spraying of potable water at a rate of 300 gallons per acre or less will be performed by a mobile pressure type distributor truck no more than three times a day during the months of May-September and once per day during the months of October-April or whenever the dryness of the soil wan-ants it
Maintenance requirements: No maintenance is required for this item.
Control measure: Click here to enter text.
Implementation: Click here to enter text.
Maintenance requirements: Click here to enter text.
Add other measures as needed.
7.6 Minimize Disturbance of Steep Slopes
Describe how disturbance of steep slopes will be minimized. Describe controls (e.g. erosion control blankets, tackifiers) that will be implemented to minimize sediment discharges from slope disturbances.
If applicable, describe how storm water run-on and run-off will be managed. Flows may be diverted from exposed soils by retaining/detaining flows or otherwise minimizing mnoff and the discharge of pollutants from exposed areas of the site. Placement of structural practices in floodplains will be avoided to the degree technologically and economically practicable and achievable.
IZl Not applicable to this project. Reason: Click here to enter text.
If applicable:
Control measure: Click here to enter text.
Implementation: Click here to enter text.
Maintenance requirements: Click here to enter text.
Control measure: Click here to enter text.
Implementation: Click here to enter text.
Maintenance requirements: Click here to enter text.
Control measure: Click here to enter text.
[25]
Implementation: Click here to enter text.
Maintenance requirements: Click here to enter text.
Add other measures as needed.
[26]
7.7 Topsoil Conservation
Describe how topsoil will be preserved, if feasible. If conservation of topsoil is infeasible, explain why, and describe alternate methods to be used to insure optimum vegetation survival and growth.
Erosion and sediment control measures for topsoil stockpiles (and other erodible materials) are shown in section 4.4.
Note: Contractor and PE complete this section as appropriate.
D Conservation of topsoil is Infeasible:
Reason: Click here to enter text.
Alternate method: Click here to enter text.
Conservation of topsoil is Feasible:
Conservation measure: Click here to enter text.
Implementation: Click here to enter text.
Maintenance requirements: Click here to enter text.
Conservation measure: Click here to enter text.
Implementation: Click here to enter text.
Maintenance requirements: Click here to enter text.
Add other measures as needed.
7 .8 Minimize Soil Compaction
Minimize soil compaction in areas where final vegetative stabilization will occur and where infiltration practices will be installed.
~ Not applicable to this project. Reason: Click here to enter text.
If applicable:
Control measure: Click here to enter text.
Implementation: Click here to enter text.
Maintenance requirements: Click here to enter text.
Control measure: Click here to enter text.
Implementation: Click here to enter text.
Maintenance requirements: Click here to enter text.
[27]
7.9 Storm Drain Inlets and Culvert Inlets
Applicable for stormwater drain inlets which are connected to separate storm sewer systems (usually in urban locations) AND for culvert inlets that discharge stormwater from the project into surface waters.
Locations and design specifications of BMPs are shown on the erosion and sediment control plan sheets in TAB 6.
D Not applicable to this project. Reason: Click here to enter text.
If applicable:
The following BMPs are applicable to:
D Storm Drain Inlets
Culvert Inlets
Control measure: All existing culverts must be protected in place to maintain full functionality of existing drainage patterns. Storm water runoff from construction site must be passed through sediment control BMPs as indicated on erosion control plans, standard details, and compliant with NPDES-CGP permit.
Implementation: Insta11 perimeter silt fence to intercept construction stormwater before discharging to receiving waterbody.
Maintenance requirements: •Clean, or remove and replace, the protection measures as sediment accumulates, the filter fabric becomes clogged, and/or performance is compromised. Where there is evidence of sediment accumulation adjacent to the protection measure, Contractor must remove the deposited sediment by the end of the same work day in which it is found or by the end of the fo11owing work day if removal by the same work day is not feasible
Control measure: Click here to enter text.
Implementation: Click here to enter text.
Maintenance requirements: Click here to enter text.
Add other measures as needed.
7.10 Constructed Stormwater Conveyance Channels and Culvert Outlets
Describe velocity dissipation and/or erosion control devices to be installed at stormwater conveyance channels (such as roadside ditches) and culvert outlets. Includes permanent and temporary devices (specify).
Velocity dissipation devices will be placed at discharge locations and along the length of any outfall channel to provide a non-erosive flow velocity from the structure to a water course so that
[28] the natural physical and biological characteristics and functions are maintained and protected (e.g., no significant changes in the hydrological regime of the receiving water).
Locations and design specifications of BMPs are shown on the erosion and sediment control plan sheets in TAB 6.
~ Not applicable to this project.
If applicable:
Control measure: Click here to enter text.
Implementation: Click here to enter text.
Maintenance requirements: Click here to enter text.
Control measure: Click here to enter text.
Implementation: Click here to enter text.
Maintenance requirements: Click here to enter text.
Add other measures as needed.
7.11 Sediment Basins
If applicable, provide site design specifications and other details for design of sediment basins and ponds. This may also include sediment infiltration swales.
Locations and design specifications of BMPs are shown on the erosion and sediment control plan sheets in TAB 6.
At a minimum, sediment ponds must provide storage for either the calculated volume ofnmoff from the 2-year, 24-hour storm event or 3,600 cubic feet per acre drained. Sediment ponds must also use outlet structures that withdraw water from the surface, unless infeasible.
0 Not applicable to this project.
If applicable, type of sediment retention/infiltration used: Compost berms shall be used during construction phase of the project to trap sediments. Project site is has moderate slopes with approximately 3 to longitudinal slope with a small portion exceeding 5% slope. Erosive velocities are not expected at the site. Runoff will be collected by roadside swales and routed to undisturbed existing outfalls to creeks. Compost berms or wattles shall be installed in the swales to intercept sediments before discharging to corresponding creek.
Design description: Install Wattle/berms per standard details provided with design plans.
7.12 Chemical Treatment
If chemical sediment control (such as polymers) will be used, provide design specifications and other details considered when choosing treatment type and locations.
~ Not applicable to this project.
[29]
If applicable:
NOTE: If use of cationic treatment chemicals is planned, separate prior approval is required from EPA.
Locations of chemical treatment sites are shown on the erosion and sediment control plan sheets in TAB 6.
Describe/name treatment chemicals that will be used and why these chemicals are suited to site soil characteristics and other construction site conditions: Click here to enter text.
Describe treatment system specifications and dosage of chemicals to be used: Click here to enter text.
Describe storage of chemicals and other material safety data: Click here to enter text.
Special controls to be used for Cationic treatment chemicals: Click here to enter text.
Describe training that personnel handling/applying treatment chemicals have/will receive: Click here to enter text.
7.13 Dewatering Practices
Discharge of ground water or accumulated stormwater that is removed from excavations, trenches, foundations, etc. into surface waters is prohibited unless such waters are first effectively managed by appropriate sediment controls. Uncontaminated non-turbid dewatering water can be discharge without being routed to a control.
~ Not applicable to this project
If applicable:
Specific dewatering practice: Click here to enter text.
Implementation: Click here to enter text.
Maintenance: Click here to enter text.
Add other measures as needed.
7.14 Erosion Control and Stabilization
Commence temporary soil stabilization measures immediately if no further disturbance of an area of the site or stockpile is expected within the next 14 days. Complete temporary soil stabilization measures to disturbed sites or stockpiles within 14 days of last disturbance. Provide for temporary stabilization of all exposed soil prior to winter construction shut down,,.
Specify whether stabilization measure is temporary or permanent.
Temporary Measures:
(30]
Practice/Control measure: Following sediment & erosion control measures will be used to maintain site stabilization during construction; Silt Fence, Straw wattles, stabilized constmction entrance, Compost berm for sediment pond, Plastic Sheets & Plywood for stockpiles.
Implementation: TBD
Maintenance: Standard operation and maintenance per WFL standard drawings and specifications.
Practice/Control measure: Click here to enter text.
Implementation: Click here to enter text.
Maintenance: Click here to enter text.
[31]
Permanent Measures:
Practice/Control measure: Click here to enter text.
Implementation: Click here to enter text.
Maintenance: Click here to enter text.
Practice/Control measure: Click here to enter text.
Implementation: Click here to enter text.
Maintenance: Click here to enter text.
Add other measures as needed.
7.15 Removal of BMPs
Remove erosion and sediment control BMPs that are no longer needed and leave in good working order those BMPs that will remain at the construction site after close-out.
BMPs are no longer needed when the site that the BMP is protecting has reached final stabilization as defined in the applicable NPDES Stonnwater Pe1mit.
Final stabilization means:
• All ground disturbing activities at the site have been completed, AND
• Vegetation has been established that provides a uniform perennial vegetative cover with a density of 70% of the natural vegetative cover prior to construction.
• In arid (0-1 O" annual precipitation) or semiarid (10-20" annual…