MT DOT 236(1)

MT 236 South of Big Sandy

# General Technical Question Answer Date 1 x For item 62405‐0400 – where does this material come from? Is it already in a stockpile somewhere?

No, See Section 204 in FP‐14 8/3/16

2 x

Is the volume of conserved topsoil to be removed from embankment foundation sections (in‐slopes) measured and paid as Roadway Excavation as per 204.05 and 204.16(a)(1)(e)?

Conserved topsoil is paid for under 62405‐

8/11/16

3 x

Does the quantity of Unclassified Borrow in the bid schedule include replacement of the topsoil conserved from embankment sections? No

8/11/16

4 x

Is the Topping (A‐1 or A‐2‐4) required for the top 12” of embankment just for the section directly below the Aggregate Base? yes

8/11/16

5 x

Would item 20101 – clear and grubbing of 42 acres also include stripping and pile topsoils to be replaced under item 62405? no

8/12/16

Check General or Technical