PROJECT_DESCRIPTION_OR_PFH_163(19) _Historic_Columbia_River_Highway_Lindsey_Creek_to_Starvation_Creek_Trailhead_.pdf
PDF 25 KB Posted
- Attached to
- OR PFH 163(19), Historic Columbia River Highway Lindsey Creek to Starvation Creek Trailhead
- Solicitation number
- DTFH70-15-B-00012
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BidSum_HCRH.pdf | ||
| A004_HCRH.pdf | ||
| Q A.pdf | ||
| A003_HCRH.pdf | ||
| Q A.pdf | ||
| A002_HCRH.pdf | ||
| Q A.pdf | ||
| A001_HCRH.pdf | ||
| Q A.pdf | ||
| COMPLETE_PLAN_SET_HCRH.pdf | ||
| GR_12_14__Geotech_Report_Segment_D.pdf | ||
| Plan_Request_HCRH.pdf | ||
| GR_10-15_Rockfall_Report_Segments_A-D_(2).pdf | ||
| GR_11-14_Geotech_Report_Segment_A-E.pdf | ||
| of16319_XS.pdf | ||
| ESCP_-HISTORIC_COLUMBIA_RIVER_RD.pdf | ||
| of16319_earthwork.pdf | ||
| IFB__HCR.pdf | ||
| GM_20_15_HCRH_Seg_D_Station_198_Rockfall_Recom_Memo.pdf |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OR PFH 163(19) Historic Columbia River Highway Lindsey Creek to Starvation Creek Trailhead, Hood River County, Oregon.
The work consists of construction of a single span, 50-foot long precast voided slab bridge with cast-in-place concrete deck, and other small items of work.
Project length: 1.32 Miles
Tentative Fixed Completion Date: Fall 2016 (Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)
Estimated Price Range: $2 million to $3 million
Location: 7 Miles West of Hood River, Oregon
DESCRIPTION OF WORK in US CUSTOMARY UNITS
FP-14
O ne
S ch ed ul e Sc h N am e
DIVISION 150 – Project Requirements 152 Construction Survey & Staking (yes/no) Yes 153 Contractor Quality Control and Assurance
(yes/no) Yes 154 Contractor Sampling & Testing (yes/no) Yes 155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes 157 Soil Erosion & Sediment Control (erosion control devices) 5,500 Ln Ft
DIVISION 200 – Earthwork 201 Clearing & Grubbing 8 Acres 202 Additional Clearing & Grubbing (clearing & grubbing) 30 Each 203 Removal of Structures & Obstructions (structures, demolition) All 204 Excavation & Embankment 9,500 Cu Yd 207 Earthwork Geosynthetics 1,000 Sq Yd 208 Structure Excavation 250 Cu Yd
S ch ed ul e Sc h N
DIVISION 250 – Slope Reinforcement and Retaining Walls 251 Riprap 1,500 Cu Yd 252 Rockery, Special Rock Embankment, and Rock Buttress 1,100 Sq Ft 253 Gabions & Revet Mattresses 60 Cu Yd 255 Mechanically Stabilized Earth Walls (retaining walls) 4,200 Sq Ft 257 Contactor-Designed Retaining Walls (contractor completed designs) LPSM 258 Reinforced Concrete Retaining Walls (retaining walls) 840 Sq Ft 261 Reinforced Soil Slopes 350 Sq Ft
DIVISION 300 – Aggregate and Base Courses 302 Minor Crushed Aggregate 3,500 Ton
DIVISION 400 – Asphalt Pavements & Surface Treatments 403 Asphalt Concrete 1,750 Ton 414 Asphalt Pavement Crack Sealing & Filling 700 Ln Ft
DIVISION 500 – Rigid Pavement 501 Minor Concrete Pavement 250 Sq Yd
DIVISION 550 – Bridge Construction 552 Structural Concrete (concrete – major structures) 120 Cu Yd 553 Prestressed Concrete 140 Ln Ft 554 Reinforcing Steel 18,000 LB 556 Bridge Railing 140 Ln Ft 563 Painting (structures, painting) 4,000 Sq Ft
DIVISION 600 – Incidental Construction 601 Minor Concrete Structures (concrete – minor structures) 602 Culverts & Drains 250 Ln Ft
S ch ed ul e Sc h N
607 Cleaning, Relaying, & Repairing Existing Drainage Structures 2 Each 609 Curb & Gutter (concrete – minor structures) (indicate which) 180 Ln Ft 617 Guardrail 950 Ln Ft 618 Concrete Barriers & Precast Guardwalls 1,850 Ln Ft 619 Fences, Gates, Cattle Guards & Bollard Posts 700 Ln Ft 620 Stone Masonry 400 Ln Ft 621 Monuments & Markers (construction survey & staking) (yes/no) Yes 622 Rental Equipment (yes/no) No 623 General Labor (yes/no) No 633 Permanent Traffic Control (traffic control devices) 15 Sq Ft 634 Permanent Pavement Markings (traffic pavement markings) 300 Ln Ft 635 Temporary Traffic Control – Drums & Barricades 150 Each 635 Temporary Traffic Control – Signs 240 Sq Ft 635 Temporary Traffic Control – Supervisor 80 Days 636 Traffic Signal, Traffic Counter, Lighting, & Electrical Systems All 646 Roadside Development (bike rack) 5 Each 646 Roadside Development (pedestrian railing, steel ) 2,600 Ln Ft 646 Roadside Development (pedestrian railing, wood) 600 Ln Ft