AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
N/A
PAGE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)
A002 7/7/2014 N/A WY PLD GRTE 700(2), Grand
Teton Park Pathways, Phase III
6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A
Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.
X
DTFH70-14-R-00003
9B. DATED (SEE ITEM 11)
6/9/2014
10A. MODIFICATION OF CONTRACT/ORDER NO.
N/A
10B. DATED (SEE ITEM 13)
CODE: N/A FACILITY CODE: N/A
N/A
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
(_X_ ) is extended, ( _ ) is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN
ITEM 10A.
N/A
B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D OTHER (Specify type of modification and authority)
N/A
E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
WY PLD GRTE 700(2), Grand Teton Park Pathways, Phase III
See page 2 for revisions.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
N/A
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION NOT USABLE
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Amendment No. A002, dated 07/07/14 WY PLD GRTE 700(2) Solicitation No. DTFH70-14-R-00003 Grand Teton Park Pathways, Phase III
REVISIONS ARE AS FOLLOWS:
SF 1442, SOLICITATION, OFFER, AND AWARD (Pen & Ink change)
Page A-3, Block 13A. Revises proposal due date from 07/09/2014 to 07/11/2014.
BID SCHEDULE
Page A-9 Revises quantity for Item 20302-0300; Removal of curb and gutter, concrete Page A-11 Revises quantity for Item 60902-1000; Curb and Gutter, Concrete, 12-inch depth Page A-13 Revises quantity for Item 63302-0000; Sign system
CONTRACT CLAUSES
SPECIAL CONTRACT REQUIREMENTS
Page Section/Table Revision G-8 704.10 Select Granular Backfill Revises (a)(2) G-8 704.10 Select Granular Backfill Revises Table 704-4
PLANS
Plan sheet #B.1 Revises quantity for Item 20302-0300 Plan sheet #B.2 Revises quantity for Item 60902-1000 Plan sheet #B.3 Revises quantity for Item 63302-0000 Plan sheet #E.3 Revises quantities for Items 20302-0300 and 60902-1000 Plan sheet #M.1 Revises quantity for Item 63302-0000 Plan sheet #M.2 Revises description for Item 63401-0300 at 718+91.14 Plan sheet #M.4 Revises description for Item 63401-0300 at 718+91.14 Plan sheet #M.7 Revises Practice Rocks Parking Area Plan sheet #M.10 Revises pavement stall markings
ENCLOSURES
Pages:
A-7 through A-16 G-8
Notice to Offerers: Please submit revised pages A-7 through A-16 with your bid.
New proposal due date: 07/11/2014
Amendment No. A002, dated 07/07/14 WY PLD GRTE 700(2) Solicitation No. DTFH70-14-R-00003 Grand Teton Park Pathways, Phase III
Plan Sheets:
B.1 through B.3 E.3 M.1 through M.2 M.4 M.7 M.10
A - 7
Offeror please note: Before preparing the bid, carefully read the Solicitation Provisions.
Insert a unit bid price, in figures, for each pay item for which a quantity appears in the bid schedule. Multiply the unit price by the quantity for each pay item and show the amount bid. Should any mathematical check made by the Government show a mistake in the amount bid, the corrected unit price extension shall govern.
When the word "LPSM" (Lump Sum) appears as a unit bid price, insert an amount for each lump sum pay item.
When a sum based on a fixed rate appears for any pay item in the amount bid column, include the Government inserted amount bid for the item in the total bid amount.
Total all of the amounts bid for each pay item and show the total bid amount.
BRAND NAME OR EQUAL NOTIFICATION
If providing other than the brand name product listed in Section 725.24A, complete the following: (See FAR Provision 52.211-6, Brand Name or Equal)
For Section 563, Painting, which is incidental to pay item 25501-1000 Mechanically Stabilized Earth Wall, Welded Wire Face, our firm offers in lieu of the brand name in Subsection 725.24A Weathering Agent:
Brand: __________________________________________
Manufacturer's Name: _____________________________
Include with your bid all documents needed by the Government to determine if the proposed product meets the requirements listed in the appropriate Section. The determination as to the equality of the product offered is the responsibility of the Government and will be based on the information furnished by the bidder as well as other information reasonably available to the contracting office.
If proposed "equal" is determined by the government to be "not equal", bid will be considered nonresponsive.
Bid Schedule
Project No:WY PLD GRTE 700(2)
Project Name:Grand Teton Park Pathways, Phase III
A - 8
Contract Quantity Pay Items
20101-0000 CLEARING AND GRUBBING
20302-0300 REMOVAL OF CURB AND GUTTER, CONCRETE
20302-2600 REMOVAL OF PAVEMENT MARKINGS (4-INCH SANDBLAST)
20303-1600 REMOVAL OF PAVEMENT, ASPHALT
20315-0000 SAWCUTTING PAVEMENT
21101-1000 ROADWAY OBLITERATION, METHOD 1
25501-1000 MECHANICALLY STABILIZED EARTH WALL, WELDED WIRE FACE
30502-0300 AGGREGATE-TOPSOIL COURSE, 2-INCH DEPTH
30502-0700 AGGREGATE-TOPSOIL COURSE, 4-INCH DEPTH
41301-1000 ASPHALT PAVEMENT MILLING, 4-INCH DEPTH
60101-0000 CONCRETE
61501-0500 SIDEWALK, EXPOSED AGGREGATE CONCRETE (VISITOR CENTER)
62405-0100 PLACING CONSERVED TOPSOIL, 2-INCH DEPTH
62406-0350 PLACING CONSERVED TOPSOIL, 5-INCH DEPTH
62501-0000 TURF ESTABLISHMENT
64704-1600 MITIGATION, STREAMBED CHANNEL RECONSTRUCTION
Amendment Item No. Pay Item No. Description Quantity Unit Unit Price Amount
A0020 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
A0040 15201-0000 CONSTRUCTION SURVEY AND STAKING
ALL LPSM $___LPSM_____ $____________
A0060 15301-0010 CONTRACTOR QUALITY CONTROL AND ASSURANCE
ALL LPSM $___LPSM_____ $____________
A0080 15401-0000 CONTRACTOR TESTING
ALL LPSM $___LPSM_____ $____________
A0100 15501-0000 CONSTRUCTION SCHEDULE
ALL LPSM $___LPSM_____ $____________
A0120 15702-1000 SOIL EROSION CONTROL, TEMPORARY DIVERSION CHANNEL (LOWER
DITCH CREEK)
ALL LPSM $___LPSM_____ $____________
A0140 15702-1000 SOIL EROSION CONTROL, TEMPORARY DIVERSION CHANNEL (UPPER
DITCH CREEK)
ALL LPSM $___LPSM_____ $____________
Bid Schedule Schedule:A Schedule Type:Base
A - 9
A0160 15702-2000 SOIL EROSION CONTROL, TURBIDITY MONITORING (UPPER DITCH CREEK)
ALL LPSM $___LPSM_____ $____________
A0180 15702-2000 SOIL EROSION CONTROL, TURBIDITY MONITORING (LOWER DITCH CREEK)
ALL LPSM $___LPSM_____ $____________
A0200 15705-0100 SOIL EROSION CONTROL, SILT FENCE
405 LNFT $____________ $____________
A0220 15705-1500 SOIL EROSION CONTROL, SEDIMENT WATTLE
2,730 LNFT $____________ $____________
A0240 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION ENTRANCE (TIMBER
MAT SYSTEM)
7 EACH $____________ $____________
A0260 15802-0000 WATERING FOR DUST CONTROL
ALL LPSM $___LPSM_____ $____________
A0280 20101-0000 CLEARING AND GRUBBING
5.3 ACRE $____________ $____________
A0300 20301-0100 REMOVAL OF BOLLARD
32 EACH $____________ $____________
A0320 20301-0700 REMOVAL OF DELINEATOR
30 EACH $____________ $____________
A0340 20301-2400 REMOVAL OF SIGN
1 EACH $____________ $____________
A002 A0360 20302-0300 REMOVAL OF CURB AND GUTTER, CONCRETE
27 LNFT $____________ $____________
A0380 20302-2600 REMOVAL OF PAVEMENT MARKINGS (4-INCH SANDBLAST)
210 LNFT $____________ $____________
A0400 20303-1600 REMOVAL OF PAVEMENT, ASPHALT
418 SQYD $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
A - 10
A0420 20310-1000 PLUG, EXISTING PIPE
1 EACH $____________ $____________
A0440 20315-0000 SAWCUTTING PAVEMENT
687 LNFT $____________ $____________
A0460 20401-0000 ROADWAY EXCAVATION
18,750 CUYD $____________ $____________
A0480 20465-0000 CONSERVE AND PLACE BOULDER
7 EACH $____________ $____________
A0500 20811-0000 SHORING AND BRACING
1,360 SQFT $____________ $____________
A0520 21101-1000 ROADWAY OBLITERATION, METHOD 1
58 SQYD $____________ $____________
A0540 25101-4000 PLACED RIPRAP, CLASS 4 (GOVERNMENT FURNISHED)
35 CUYD $____________ $____________
A0560 25125-0000 BOULDER (GOVERNMENT FURNISHED)
7 EACH $____________ $____________
A0580 25501-1000 MECHANICALLY STABILIZED EARTH WALL, WELDED WIRE FACE
2,127 SQFT $____________ $____________
A0600 30502-0300 AGGREGATE-TOPSOIL COURSE, 2-INCH DEPTH
5,890 SQYD $____________ $____________
A0620 30502-0700 AGGREGATE-TOPSOIL COURSE, 4-INCH DEPTH
1,246 SQYD $____________ $____________
A0640 30606-0000 MAGNESIUM CHLORIDE
40 TON $____________ $____________
A0660 30802-1000 ROADWAY AGGREGATE, METHOD 1
2,900 TON $____________ $____________
A0680 40301-0000 HOT ASPHALT CONCRETE PAVEMENT
2,450 TON $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
A - 11
A0700 40920-1000 FOG SEAL, EMULSIFIED ASPHALT GRADE CSS-1 OR CSS-1H, SS-1 OR SS-1H
23 TON $____________ $____________
A0720 41105-0000 BLOTTER
30 TON $____________ $____________
A0740 41201-1000 TACK COAT GRADE CSS-1, CSS-1H, SS-1, OR SS-1H
2.4 TON $____________ $____________
A0760 41301-1000 ASPHALT PAVEMENT MILLING, 4-INCH DEPTH
5,620 SQYD $____________ $____________
A0780 60101-0000 CONCRETE
20 CUYD $____________ $____________
A0800 60201-0100 4-INCH PIPE CULVERT
445 LNFT $____________ $____________
A0820 60201-0800 24-INCH PIPE CULVERT
40 LNFT $____________ $____________
A0840 60501-0000 STANDARD UNDERDRAIN SYSTEM
420 LNFT $____________ $____________
A0860 60706-0000 CLEANING DRAINAGE STRUCTURE
1 EACH $____________ $____________
A0880 60901-1000 CURB, CONCRETE, 12-INCH DEPTH (EXPOSED AGGREGATE)
22 LNFT $____________ $____________
A002 A0900 60902-1000 CURB AND GUTTER, CONCRETE, 12-INCH DEPTH
35 LNFT $____________ $____________
A0920 61501-0100 SIDEWALK, CONCRETE (4-INCH DEPTH)
230 SQYD $____________ $____________
A0940 61501-0500 SIDEWALK, EXPOSED AGGREGATE CONCRETE
350 SQYD $____________ $____________
A0960 61501-0500 SIDEWALK, EXPOSED AGGREGATE CONCRETE (VISITOR CENTER)
6 SQYD $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
A - 12
A0980 61509-0000 DETECTABLE WARNING PANELS
123 SQYD $____________ $____________
A1000 61701-2000 GUARDRAIL SYSTEM G4, TYPE 4, CLASS B WOOD POSTS
500 LNFT $____________ $____________
A1020 61709-4000 REMOVE AND RESET, TERMINAL SECTION
1 EACH $____________ $____________
A1040 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY
20 HOUR $____________ $____________
A1060 62201-0600 BACKHOE LOADER, 8 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET,
30-INCH WIDTH
20 HOUR $____________ $____________
A1080 62201-0850 WHEEL LOADER, 1 CUBIC YARD MINIMUM RATED CAPACITY
25 HOUR $____________ $____________
A1100 62201-1300 BULLDOZER, 160HP MINIMUM FLYWHEEL POWER
20 HOUR $____________ $____________
A1120 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE
40 HOUR $____________ $____________
A1140 62201-3000 HYDRAULIC EXCAVATOR (RUBBER-TRACKED, 4-7 CUBIC FOOT RATED
CAPACITY WITH THUMB ATTACHMENT)
40 HOUR $____________ $____________
A1160 62201-3500 LOADER, WHEEL, SKID STEER, 40HP MINIMUM
20 HOUR $____________ $____________
A1180 62301-0000 GENERAL LABOR
200 HOUR $____________ $____________
A1200 62405-0100 PLACING CONSERVED TOPSOIL, 2-INCH DEPTH
1,891 SQYD $____________ $____________
A1220 62406-0350 PLACING CONSERVED TOPSOIL, 5-INCH DEPTH
2.3 ACRE $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
A - 13
A1240 62407-0000 PLACING CONSERVED TOPSOIL (18-INCH DEPTH)
1,210 CUYD $____________ $____________
A1260 62501-0000 TURF ESTABLISHMENT
0.5 ACRE $____________ $____________
A1280 63301-1000 SIGN SYSTEM, GOVERNMENT FURNISHED SIGN (TYPE II)
1 EACH $____________ $____________
A1300 63301-1000 SIGN SYSTEM, GOVERNMENT FURNISHED SIGN (TYPE I)
8 EACH $____________ $____________
A002 A1320 63302-0000 SIGN SYSTEM
113 SQFT $____________ $____________
A1340 63316-1000 REMOVE AND RESET SIGN
6 EACH $____________ $____________
A1360 63318-1000 SNOWPOLE HOLDER (TYPE III)
28 EACH $____________ $____________
A1380 63318-1000 SNOWPOLE HOLDER (TYPE II)
38 EACH $____________ $____________
A1400 63318-1000 SNOWPOLE HOLDER (TYPE I)
6 EACH $____________ $____________
A1420 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID (WHITE, 24-INCH)
236 LNFT $____________ $____________
A1440 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID (WHITE, 4-INCH)
6,435 LNFT $____________ $____________
A1460 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID (YELLOW, 4-INCH)
9,880 LNFT $____________ $____________
A1480 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID (WHITE, 12-INCH)
420 LNFT $____________ $____________
A1500 63405-0050 PAVEMENT MARKINGS, SYMBOLS (ACCESSIBILITY PARKING AISLE)
2 EACH $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
A - 14
A1520 63405-0050 PAVEMENT MARKINGS, SYMBOLS (XING)
6 EACH $____________ $____________
A1540 63405-0050 PAVEMENT MARKINGS, SYMBOLS (BIKE SYMBOL)
6 EACH $____________ $____________
A1560 63405-0050 PAVEMENT MARKINGS, SYMBOLS (HWY XING)
8 EACH $____________ $____________
A1580 63405-0500 PAVEMENT MARKINGS, TYPE B, TURN ARROW
4 EACH $____________ $____________
A1600 63405-0550 PAVEMENT MARKINGS, TYPE B, STRAIGHT ARROW
4 EACH $____________ $____________
A1620 63405-0850 PAVEMENT MARKINGS, TYPE B, ACCESSIBILITY SYMBOL
6 EACH $____________ $____________
A1640 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
25 EACH $____________ $____________
A1660 63502-0900 TEMPORARY TRAFFIC CONTROL, CONE, TYPE 28-INCH
100 EACH $____________ $____________
A1680 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
30 EACH $____________ $____________
A1700 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
(GOVERNMENT FURNISHED)
2 EACH $____________ $____________
A1720 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
2 EACH $____________ $____________
A1740 63503-1000 TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE
470 LNFT $____________ $____________
A1760 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
430 SQFT $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
A - 15
A1780 63507-0700 TEMPORARY TRAFFIC CONTROL, TRAFFIC AND SAFETY SUPERVISOR
150 DAY $____________ $____________
A1800 63509-1000 TEMPORARY TRAFFIC CONTROL, FLAGGER
2,500 FXHR $38.00 $95,000.00
A1820 64501-0000 LOCATE UTILITIES
ALL LPSM $___LPSM_____ $____________
A1840 64603-0300 FIXTURE, BENCH
1 EACH $____________ $____________
A1860 64604-1000 FIXTURE, HANDRAIL (VISITOR CENTER)
12 LNFT $____________ $____________
A1880 64604-3000 FIXTURE, PEDESTRIAN RAILING
480 LNFT $____________ $____________
A1900 64703-3010 MITIGATION, ROCK WEIR
1 EACH $____________ $____________
A1920 64703-7000 MITIGATION, BAFFLE (8-FOOT)
1 EACH $____________ $____________
A1940 64703-7000 MITIGATION, BAFFLE (2-FOOT-5-INCH)
1 EACH $____________ $____________
A1960 64703-7000 MITIGATION, BAFFLE (2-FOOT-8-INCH)
15 EACH $____________ $____________
A1980 64703-7000 MITIGATION, BAFFLE (7-FOOT)
15 EACH $____________ $____________
A2000 64703-7000 MITIGATION, BAFFLE (3-FOOT)
1 EACH $____________ $____________
A2020 64704-1600 MITIGATION, STREAMBED CHANNEL RECONSTRUCTION
50 CUYD $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
A - 16
Submitted by:____________________________________ Schedule Total:____________
Bid Schedule Schedule:A Schedule Type:Base
G-8
Special Contract Requirements Project: WY PLD GRTE 700(2), Grand Teton Park Pathways, Phase III
(a) Quality requirements.
(1) Gradation Table 704-4
(2) 2 or more fractured faces, ASTM D 5821 90% min.
(3) Angle of internal friction 34° min.
On the portion passing the No. 10 sieve, AASHTO T 236
Note: Direct shear tests for angle of internal friction are not required when the percent passing the No. 4 sieve is less than 50 percent and the percent passing the No. 40 sieve is less than 25 percent. Compact samples for AASHTO T 236 to 95 percent of the maximum dry density determined according to AASHTO T 99, method C or D.
(4) Sodium sulfate soundness loss (5 cycles), 15% max.
AASHTO T 104
(5) Plasticity index, AASHTO T 90 6 max.
(b) Electrochemical requirements.
(1) Resistivity, AASHTO T 288 3000 ohm-cm min.
(2) pH, AASHTO T 289 5.0 to 10.0
(3) Sulfate content, AASHTO T 290 200 ppm max.
(4) Chloride content, AASHTO T 291 100 ppm max.
Note: Tests for sulfate and chloride content are not required when resistivity is greater than 5000 ohm-cm.
Table 704-4 Select Granular Backfill Gradation(1)
Sieve Size
Percent by Mass Passing Designated Sieve (AASHTO T 27 and T 11)
Grading Designation Type A
Grading Designation Type B
3 inch -- 100
1 1/2 inch 100 --
1 95 – 100 60 - 80
3/4 inch -- --
1/2 inch 25 - 60 --
No. 4 0 - 10
No. 8 0 – 5 --
No. 40 -- 0 – 60
No. 200 -- 0 – 10
Revised by Amendment A002
Sheet and Description
SECTION C SECTION D SECTION E SECTION F SECTION G SECTION H SECTION I SECTION J SECTION K SECTION L SECTION M SECTION N -
TYPICAL
SECTIONS
PLAN &
PROFILE
MISC
EROSION
CONTROL
MATERIAL
SOURCES
DRAINAGE MSE WALL
BLACKTAIL
POND
OVERLOOK
GUARDRAIL
TEMPORARY
TRAFFIC
CONTROL
PERMANENT
TRAFFIC
CONTROL
UTILITIES ALLOWANCE
Bid
Schedule
A0020 15101-0000 MOBILIZATION LPSM All ALL
A0040 15201-0000 CONSTRUCTION SURVEY AND
STAKING LPSM All ALL
A0060 15301-0010 CONTRACTOR QUALITY CONTROL
AND ASSURANCE LPSM All ALL
A0080 15401-0000 CONTRACTOR TESTING LPSM All ALL
A0100 15501-0000 CONSTRUCTION SCHEDULE LPSM All ALL
A0120 15702-1000 SOIL EROSION CONTROL,
TEMPORARY DIVERSION CHANNEL
(LOWER DITCH CREEK) LPSM All ALL
A0140 15702-1000 SOIL EROSION CONTROL,
TEMPORARY DIVERSION CHANNEL
(UPPER DITCH CREEK) LPSM All ALL
A0160 15702-2000 SOIL EROSION CONTROL,
TURBIDITY MONITORING (UPPER
DITCH CREEK) LPSM All ALL
A0180 15702-2000 SOIL EROSION CONTROL,
TURBIDITY MONITORING (LOWER
DITCH CREEK) LPSM All ALL
A0200 15705-0100 SOIL EROSION CONTROL, SILT
FENCE LNFT 385 20 405
A0220 15705-1500 SOIL EROSION CONTROL,
SEDIMENT WATTLE LNFT 2,603 127 2,730
A0240 15706-1600 SOIL EROSION CONTROL,
STABILIZED CONSTRUCTION
ENTRANCE (TIMBER MAT SYSTEM) EACH 7 7
A0260 15802-0000 WATERING FOR DUST CONTROL LPSM ALL
A0280 20101-0000 CLEARING AND GRUBBING Contract
ACRE 5.3 5.3 Quantity
A0300 20301-0100 REMOVAL OF BOLLARD EACH 32 32
A0320 20301-0700 REMOVAL OF DELINEATOR EACH 30 30
A0340 20301-2400 REMOVAL OF SIGN EACH 1 1
A002 A0360 20302-0300 REMOVAL OF CURB AND GUTTER, Contract
CONCRETE LNFT 27 27 Quantity
A0380 20302-2600 REMOVAL OF PAVEMENT MARKINGS Contract
(4-INCH SANDBLAST) LNFT 160 50 210 Quantity
A0400 20303-1600 REMOVAL OF PAVEMENT, ASPHALT Contract
SQYD 9 409 418 Quantity
A0420 20310-1000 PLUG, EXISTING PIPE EACH 1 1
MileStone: Amendment A002 Amendment Review Date: In Progress Report Date: 07/07/14
A M E N D
Line Item No.
Pay Item Number
SUMMARY OF QUANTITIES - Schedule A -J u l-
:5 A
M
Remarks and/or Determination of
Estimated Quantity
Pay Item Description Unit
Estimated Quantities
C
M yF ile s\
K im b er
's F ile s_
W
FL
H D
\E xp o rt s fr o m
P ro je ct
W is e\ [W
Y P
LD
G
R T E
(2
A E st im a te
.x ls m ]S h ee t
STATE PROJECT
PLD GRTE 700(2) B.1WY
NUMBER
SHEET
SECTION C SECTION D SECTION E SECTION F SECTION G SECTION H SECTION I SECTION J SECTION K SECTION L SECTION M SECTION N -
TYPICAL
SECTIONS
PLAN &
PROFILE
MISC
EROSION
CONTROL
MATERIAL
SOURCES
DRAINAGE MSE WALL
BLACKTAIL
POND
OVERLOOK
GUARDRAIL
TEMPORARY
TRAFFIC
CONTROL
PERMANENT
TRAFFIC
CONTROL
UTILITIES ALLOWANCE
Bid
Schedule
A0440 20315-0000 SAWCUTTING PAVEMENT Contract
LNFT 38 520 129 687 Quantity
A0460 20401-0000 ROADWAY EXCAVATION CUYD 17,854 896 18,750
A0480 20465-0000 CONSERVE AND PLACE BOULDER EACH 7 7
A0500 20811-0000 SHORING AND BRACING SQFT 1,294 66 1,360
A0520 21101-1000 ROADWAY OBLITERATION, METHOD 1 Contract
SQYD 58 58 Quantity
A0540 25101-4000 PLACED RIPRAP, CLASS 4
(GOVERNMENT FURNISHED) CUYD 29 6 35
A0560 25125-0000 BOULDER (GOVERNMENT FURNISHED) EACH 7 7
A0580 25501-1000 MECHANICALLY STABILIZED EARTH Contract
WALL, WELDED WIRE FACE SQFT 2,127 2,127 Quantity
A0600 30502-0300 AGGREGATE-TOPSOIL COURSE, Contract
2-INCH DEPTH SQYD 5,890 5,890 Quantity
A0620 30502-0700 AGGREGATE-TOPSOIL COURSE, Contract
4-INCH DEPTH SQYD 1,246 1,246 Quantity
A0640 30606-0000 MAGNESIUM CHLORIDE TON 40 40
A0660 30802-1000 ROADWAY AGGREGATE, METHOD 1 TON 2,601 31 268 2,900
A0680 40301-0000 HOT ASPHALT CONCRETE PAVEMENT TON 1,010 1,212 3 225 2,450
A0700 40920-1000 FOG SEAL, EMULSIFIED ASPHALT
GRADE CSS-1 OR CSS-1H, SS-1
OR SS-1H TON 21 2 23
A0720 41105-0000 BLOTTER TON 30 30
A0740 41201-1000 TACK COAT GRADE CSS-1,
CSS-1H, SS-1, OR SS-1H TON 2.4 2.4
A0760 41301-1000 ASPHALT PAVEMENT MILLING, Contract
4-INCH DEPTH SQYD 5,620 5,620 Quantity
A0780 60101-0000 CONCRETE Contract
CUYD 20 20 Quantity
A0800 60201-0100 4-INCH PIPE CULVERT LNFT 424 21 445
A0820 60201-0800 24-INCH PIPE CULVERT LNFT 34 6 40
A0840 60501-0000 STANDARD UNDERDRAIN SYSTEM LNFT 400 20 420
A0860 60706-0000 CLEANING DRAINAGE STRUCTURE EACH 1 1
A0880 60901-1000 CURB, CONCRETE, 12-INCH DEPTH
(EXPOSED AGGREGATE) LNFT 18 4 22
A002 A0900 60902-1000 CURB AND GUTTER, CONCRETE,
12-INCH DEPTH LNFT 27 8 35
A0920 61501-0100 SIDEWALK, CONCRETE (4-INCH
DEPTH) SQYD 209 21 230
-J u l-
:5 A
M
MileStone: Amendment A002 Amendment Review Date: In Progress Report Date: 07/07/14
C
M yF ile s\
K im b er
's F ile s_
W
FL
H D
\E xp o rt s fr o m
P ro je ct
W is e\ [W
Y P
LD
G
R T E
(2
A E st im a te
.x ls m ]S h ee t (2
SUMMARY OF QUANTITIES - Schedule A
A M E N D
Line Item No.
Pay Item Number
Pay Item Description Unit
Estimated Quantities Remarks and/or
Determination of Estimated Quantity
STATE PROJECT
PLD GRTE 700(2) B.2WY
SECTION C SECTION D SECTION E SECTION F SECTION G SECTION H SECTION I SECTION J SECTION K SECTION L SECTION M SECTION N -
TYPICAL
SECTIONS
PLAN &
PROFILE
MISC
EROSION
CONTROL
MATERIAL
SOURCES
DRAINAGE MSE WALL
BLACKTAIL
POND
OVERLOOK
GUARDRAIL
TEMPORARY
TRAFFIC
CONTROL
PERMANENT
TRAFFIC
CONTROL
UTILITIES ALLOWANCE
Bid
Schedule
A0940 61501-0500 SIDEWALK, EXPOSED AGGREGATE
CONCRETE SQYD 80 224 46 350
A0960 61501-0500 SIDEWALK, EXPOSED AGGREGATE Contract
CONCRETE (VISITOR CENTER) SQYD 6 6 Quantity
A0980 61509-0000 DETECTABLE WARNING PANELS SQYD 115 8 123
A1000 61701-2000 GUARDRAIL SYSTEM G4, TYPE 4,
CLASS B WOOD POSTS LNFT 493 7 500
A1020 61709-4000 REMOVE AND RESET, TERMINAL
SECTION EACH 1 1
A1040 62201-0250 DUMP TRUCK, 10 CUBIC YARD
MINIMUM CAPACITY HOUR 20
A1060 62201-0600 BACKHOE LOADER, 8 CUBIC FOOT
MINIMUM RATED CAPACITY
BUCKET, 30-INCH WIDTH HOUR 20
A1080 62201-0850 WHEEL LOADER, 1 CUBIC YARD
MINIMUM RATED CAPACITY HOUR 25
A1100 62201-1300 BULLDOZER, 160HP MINIMUM
FLYWHEEL POWER HOUR 20
A1120 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM
BLADE HOUR 40
A1140 62201-3000 HYDRAULIC EXCAVATOR
(RUBBER-TRACKED, 4-7 CUBIC
FOOT RATED CAPACITY WITH
THUMB ATTACHMENT) HOUR 40
A1160 62201-3500 LOADER, WHEEL, SKID STEER,
40HP MINIMUM HOUR 20
A1180 62301-0000 GENERAL LABOR HOUR 200
A1200 62405-0100 PLACING CONSERVED TOPSOIL, Contract
2-INCH DEPTH SQYD 1,891 1,891 Quantity
A1220 62406-0350 PLACING CONSERVED TOPSOIL, Contract
5-INCH DEPTH ACRE 2.3 2.3 Quantity
A1240 62407-0000 PLACING CONSERVED TOPSOIL
(18-INCH DEPTH) CUYD 1,210 1,210
A1260 62501-0000 TURF ESTABLISHMENT Contract
ACRE 0.5 0.5 Quantity
A1280 63301-1000 SIGN SYSTEM, GOVERNMENT
FURNISHED SIGN (TYPE II) EACH 1 1
A1300 63301-1000 SIGN SYSTEM, GOVERNMENT
FURNISHED SIGN (TYPE I) EACH 8 8
A002 A1320 63302-0000 SIGN SYSTEM SQFT 97 16 113
-J u l-
:5 A
M
MileStone: Amendment A002 Amendment Review Date: In Progress Report Date: 07/07/14
C
M yF ile s\
K im b er
's F ile s_
W
FL
H D
\E xp o rt s fr o m
P ro je ct
W is e\ [W
Y P
LD
G
R T E
(2
A E st im a te
.x ls m ]S h ee t (3
SUMMARY OF QUANTITIES - Schedule A
A M E N D
Line Item No.
Pay Item Number
Pay Item Description Unit
Estimated Quantities Remarks and/or
Determination of Estimated Quantity
STATE PROJECT
PLD GRTE 700(2) B.3WY
2%
Top of curbPathway
PATHWAY CURB CUT DETAIL
6' 6'
6"
10'
Bed course
18" ty p
CURB & GUTTER
EXPOSED AGGREGATE CONCRETE
PORTLAND CEMENT CONCRETE
top, back of curb
Place topsoil to
Finish grade of pathway or parking area beyond back of curb
Existing ground
1800+39.09 - Practice Rocks Connector
Practice Rocks pavement grade, Existing
NO SCALE
NPS PMIS. No. 198832 NPS Drwg. No. 136/112675
SHEET 3 OF 3
ROADWAY CROSSING DETAILS
LC
LC
be present way, fog line may Edge of traveled of roadway
Existing edge of asphalt surface top of field is flush with panel in Concrete, ensure Embed detectable warning
Install Sidewalk, Concrete warning panel
Detectable pathway
Proposed topsoil shoulder
Aggregate-
LC
surface top of field is flush with panel in Concrete, ensure Embed detectable warning
Install Sidewalk, Concrete warning panel
Detectable pathway
Proposed
1:12
1:
1:
m ax.
6' (t yp ty p.
end taper Curb and gutter, end taper Curb and gutter, NOTE:
See locations on sheet E.1.
Install per manufactured recommendations.
2.
1.
1'
0.5'
0.5'
1'
(1800+37.03)
INSTALLATION
DETECTABLE WARNING PANEL
curb (and gutter)
Existing or new concrete
Exposed aggregate concrete existing curbs Saw cut, Exposed aggregate concrete
(PHASE III)
INSTALLATION
DETECTABLE WARNING PANEL
Revised by Amendment A0022
E.3
STATE PROJECT
WY
PLD GRTE 700(2)
P
M
J u ly
U
S S u r ft
D c m y fi le s p w p r o d u c ti o n d g r te tk .d g n
D
S la n in a
K
M il le r
C h e c k e d b y
D e s ig n e d b y
M.1
STATE PROJECT
g r te s a .d g n
U
S S u r ft
D
S la n
C h e c k e d b y
M il e s ig n e d b y
NOTE:
FOOTNOTE:
Type I signs are informational/directional signs.
Post lengths to be approved by the CO.
as needed.
Stationing is approximate, field adjust with the CO approval
3.
2.
1.
NPS PMIS No. 198832 NPS Drwg. No. 136/112675
SHEET 1 of 3
QUANTITIES
PERMANENT TRAFFIC CONTROL
TABULATION OF
Location on Outside Highway.
indicated, see Sheet M.17.
Install Government Furnished Signs on wooden posts as condition. Verify condition with CO prior to re-installation.
Remove and salvage existing sign panel and reuse if in good
Place sign on West side of Outside Highway.
Location on Practice Rocks Access Road.
Provide non reflective sign.
Side reference relevant to Outside Highway.
Place sign on east side of the Outside Highway.
See Sheet M.17, W633-7 for permanent sign installation details.
Place sign as directed by the CO.
Revised by Amendment A0022
M.2 g r te s b .d g n
U
S S u r ft
D
S la n e c k e d b y
M il s ig n e d b y
NOTE:
FOOTNOTE:
needed.
Stationing is approximate, field adjust with CO approval as1.
NPS PMIS No. 198832 NPS Drwg. No. 136/112675 alignment, measure LNFT, not station to station.
Quantity takes into consideration the curve of the pathway
Verify in field number of parking stalls.
white bars. See Sheet M.12 for details.
Quantity represents crosswalk layout with 24-inch wide solid
Contract quantity.
of fog seal application as directed by the CO.
Phase II area 400+65.64 to 719+27.00, upon acceptance
Re-paint all existing pavement markings identified in the markings before application of fog seal.
Field mark the location and type of all existing pavement
SHEET 2 of 3
QUANTITIES
PERMANENT TRAFFIC CONTROL
TABULATION OF
Revised by Amendment A0022
651565156515
6515 6515
P O
T
.0
P R
C
.5
P C
.4
4 M P
N
BEGIN PROJECT
718+65.00
WY PLD GRTE 700(2)
PATHWAYS PHASE III
GRAND TETON PARK
N
FOOTNOTE:
NPS PMIS No. 198832 NPS Drwg. No. 136/112675
W2-4L
LC
Pathway centerline stripe at
End solid yellow
723+50.00
.0 existing turnout
Extension of underpass
Pedestrian
Existing
NOTE:
Phase II Pathways construction contract.
718+91.18 were installed under the
Existing signs from 715+15.00 to1.
R O
A D
P A
R
T E
T O
N
715+00 to 727+50
SIGNING AND STRIPING
at Pedestrian underpass (retain)
Existing solid yellow stripe
El= 6498.418
E= 2459530.99
N= 1476892.94
(50')
Pathway centerline solid yellow stripe at
Remove existing
Install ANTELOPE FLATS ROAD X.X Mi.
719+90.00 RT
Install W2-4R
721+40 LT
Install APPROACHING TUNNEL X.X Mi.
725+00 LT
Line to be constructed centerline stripe at Pathway
Single solid yellow
719+05.00
Line to be constructed
HWY 89 (OUTSIDE HIGHWAY)
HWY 89 (OUTSIDE HIGHWAY)
(remove)
Existing
W1-1L sign (W1-1L). Install W2-4L
Remove existing
716+40
Install JENNY LAKE X.X Mi.
Install VISITOR CENTER X.X Mi.
719+90.00 LT
Dubois 73 mi.]
[Yellowstone 43 mi.
Remove and reset sign
726+41 LT
Install R1-2
718+90 LT
Install Yield line
718+91.14 LT
Government Furnished.
Revised by Amendment A0022
NO SCALE
M.4
STATE PROJECT
u ly
U
S S u r ft m y fi le s p w p r o d u c ti o n d g r te s d .d g n
S la n
M il
C h e c k e d b y
D e s ig n e d b
6525 6525
P T
.8
P C .7
PT 764+25.37
PC 765+19.91P
C
.0
P T
.0
P T .0
P C
C
.8
P R
C
.4
P C
.2
NPS PMIS No. 198832 NPS Drwg. No. 136/112675
Parking Area
Practice Rocks
Place sign on west side of Outside Highway.
Remove existing Practice Rocks approach road Stop sign.
Government furnished.
Place sign on east side of Outside Highway.
757+50 to 773+50
SIGNING AND STRIPING
Remove & reset sign
772+01 LT
Install W2-1
762+00 RT
Install JACKSON X.X Mi.
Install GROS VENTRE JUNCTION X.X Mi.
Install VISITOR CENTER X.X Mi.
763+00 LT
(On Practice Rocks road) Install W11-15 & W11-15P
763+00 LT
Install R1-1
764+86 RT
Install R1-1
764+48 RT
stripe at centerline Begin solid yellow 763+00 stripe at centerline End solid yellow 764+47.38 stripe at centerline Begin solid yellow 764+85.71
Line to be constructed
Install W2-1
766+75 LT
HWY 89 (OUTSIDE HIGHWAY)
HWY 89 (OUTSIDE HIGHWAY)
N N
Install crosswalk 764+52.38 to 764+80.71 centerline stripe at yellow End solid 766+00
Revised by Amendment A0022
M.7
STATE PROJECT
u ly
U
S S u r ft m y fi le s p w p r o d u c ti o n d g r te s g .d g n
S la n
M il
C h e c k e d b y
D e s ig n e d b
M.10 g r te s j.
d g n
U
S S u r ft
D
S la n e c k e d b y
M il s ig n e d b y
LEGEND:
A
NOTE:
PARKING AREA
PRACTICE ROCKS
SIGNING AND STRIPING PLAN
NO SCALE
Remove all conflicting striping.1.
N a t a ll ti m e s
M a in ta in o p e n t o t ra ff ic a n d r e cr e a ti o n a l b u si n e ss
T o P ri v a te R e si d e n ce
Existing sidewalk of pavement Existing edge
'-0
A
T o M o ra n J c t.
T o J a c k s o n
NPS PMIS No. 198832 NPS Drwg. No. 136/112675
1 Do not disturb.
FOOTNOTE:
concrete curb
Existing
Install JACKSON X.X Mi.
Install GROS VENTRE JUNCTION X.X Mi.
Install VISITOR CENTER X.X Mi.
763+00 LT
(On Practice Rocks road)
Install W11-15 & W11-15P
763+00 LT
Install R1-1
764+86 RT
Install R1-1
764+48 RT
Line to be constructed
Apply ADA access aisle markings, 10-foot wide aisle.
H W
Y
O U T S
ID
E H
IG
H W
A Y
NO BIKES/NO DOGS
Install R7-8 & R7-8P
1800+40
Install crosswalk
764+52.38 to 764+80.71
Revised by Amendment A0022
.5
2and 1 ADA stall to accomodate 9 stalls
Install pavement stall markings
| Bsheets A002.pdf |
| B1 |
| b2 |
| b3 |
| b4 |
| b5 |