PROJECT_DESCRIPTION_Tunanak.pdf
PDF 15 KB Posted
- Attached to
- AK DEN 2010(3), TUNUNAK COMMUNITY STREETS
- Solicitation number
- DTFH70-13-B-00013
About this file
Project Description
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A004_Tununak.pdf | ||
| A003__Tununak.pdf | ||
| Physical_Data_Request_Form_Tununak_A003.pdf | ||
| A002_Tununak.pdf | ||
| A001_Tununak.pdf | ||
| Physical_Data_Request_Form_Tununak.pdf | ||
| IFB_TUNUNAK_reduced.pdf | ||
| Plan_Request__Tununak.pdf | ||
| Tununak_Plan_Set_-_Final.pdf | ||
| Preliminary_Letter_AK_DEN_2010(3).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AK DEN 2010(3), TUNANAK COMMUNITY STREETS, BETHEL CENSUS
AREA, ALASKA.
The work consists of construction of timber board road, rip rap placement and other small items of work.
Project length: .50 Miles
Tentative Fixed Completion Date:
(Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)
Estimated Price Range: $1 million to $2 million
Location: Tununak, Alaska. The village is located on Nelson Island, which is approximately 115 miles northwest of Bethel, Alaska
DESCRIPTION OF WORK in US CUSTOMARY UNITS
O ne
S ch ed ul e Sc h N am e
A
DIVISION 150 – Project Requirements 152 Construction Survey & Staking (yes/no) Yes 153 Contractor Quality Control and Assurance
(yes/no) Yes
154 Contractor Sampling & Testing (yes/no) No 155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes 157 Soil Erosion Control Devices
Sediment Waddle 2,700 lnft
DIVISION 200 – Earthwork 201 Clearing & Grubbing 1.8 acre 202 Additional Clearing & Grubbing Roadside Cleanup 1.48 acre 204 Excavation & Embankment Embankment Construction
Backfill, granular 150 cuyd
1,300 cuyd 207 Earthwork Geotextiles (geotextiles) 2,500 sqyd DIVISION 250 – Slope Reinforcement and Retaining Walls 251 Riprap Class 3 Class 4
600 cuyd 1,300 cuyd
254 Crib Walls Treated Timber Retaining Wall 13,500 sqyd DIVISION 550 – Bridge Construction 557 Timber Structures Structural Timber and Lumber, Treated
Hardware, Prefabricated Aluminum Ramp 78 mfbm 3 each
DIVISION 600 – Incidental Construction 609 Curb & Gutter Curb Timber 2,225 lnft 623 General Labor 40 hour 625 Turf Establishment
Seeding Dry Method
.5 acre 637 Facilities & Services Residential Housing
Vehicle 1 each 1 each