A002-AK PRA DENA 10(31).pdf

PDF 645 KB Posted

Attached to
AK PRA DENA 10(31), PORCUPINE FOREST ROAD REPAIR
Solicitation number
DTFH70-11-B-00012
Issued by

About this file

Amendment A002

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

N/A

PAGE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)

A002 12/12/2011 N/A AK PRA DENA 10(31)

PORCUPINE FOREST ROAD REPAIR

6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A

Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.

X

DTFH70-11-B-00012

9B. DATED (SEE ITEM 11)

11/01/2011

10A. MODIFICATION OF CONTRACT/ORDER NO.

N/A

10B. DATED (SEE ITEM 13)

CODE: N/A FACILITY CODE: N/A N/A

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers ( ) is extended, ( X ) is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

N/A

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN

ITEM 10A.

N/A

B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

N/A

C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

N/A

D OTHER (Specify type of modification and authority) N/A

E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

AK PRA DENA 10(31) PORCUPINE FOREST ROAD REPAIR

Sheet F.1 Revises Quantities on Table

ENCLOSURES

Pages: F-1

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

N/A

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITION NOT USABLE

30-105 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

910910

To kl at R iv er barrier

Existing jersey

NOTE:

Staging Area

Equipment of existing sheet pile wall.

Approximate location material stockpile.

of government furnished

Approximate location stockpile site

Pitrun stockpile site

Aggregate surfacing st oc kp ile s it e

S el ec t bo rr ow sit esto ck pil eRe jec t

Scale in feet

50 100 150 200050

N

2.

1.

throughout construction.

Large stockpiles for mixing fines will be available will be determined by the CO.

The final location of all stockpiles and equipment staging

F.1

STATE PROJECT

NUMBER

SHEET

AK PRA-DENA 10(31)

d e fa .d g n

U

S I n t2

D

R J o h n s o n

C h e c k e d b y

W

M c

Q u is to n

D e s ig n e d b y

NPS Pkg. No. 100633 & 90935A NPS Drwg. No. 184/80269 by others.

Berm to be constructed

Sediment wattle

Sediment wattle sit e sto ck pil e

Rip ra p

Housing/office/trailer area

PLAN

OPERATION TOKLAT

QUANTITIES

ITEM DESCRIPTION QUANTITY REMARK

Aggregate surfacing convervsion factor: 1.90 ton/cuyd

(Aggregate Surfacing) .

Bentonite est’d at 1.5% of Item 31102 Stockpiled Aggregate

See Sheet E.6 for details.

31102-0000

31102-0000

31102-0000

30419-0000

15705-1500

3500 cuyd

2370 cuyd

5560 cuyd

158 ton

300 lnft

Stockpiled Aggregate (Riprap, class5)

Stockpiled Aggregate (Select Borrow)

Stockpiled Aggregate (Aggregate Surfacing)

Bentonite

Soil Erosion Control, Sediment Wattle

2 Amendment #002

1 Amendment #001

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
A002

File details come from the government source that posted it. Updated .