Q&A_12-20-17.pdf
PDF 127 KB Posted
- Attached to
- P6 Project Scheduling Services and Support
- Solicitation number
- DTFH6817R00001
About this file
On-going Q&A for the solicitation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_A001.pdf | ||
| Q&A_1-5-18.pdf | ||
| IDIQ_RFP_P6.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q&A for Primavera Scheduling Services IDIQ (P6)
12/20/2017
1. Is the proposal to be delivered in SF330 format?
a. No. Contractors can define their own formats, as long as it all is under the page count requirements.
2. How many FTEs by role are required in each of the four different locations?
a. TOPR#001 requires one Lead Scheduler and two Schedulers, for a total of 3 employees.
b. TOPR#002 requires two Schedulers, for a total of 2 employees.
c. Both TOPR#001 and TOPR#002 have a few hours for BI Report Writer and
Primavera Specialist but these positions are offsite and not full‐time.
d. There is currently no Task Order for the other two locations. Offers must submit pricing for these locations because they are anticipated to be needed over the life of the IDIQ contract.
3. The RFP requires that resumes of proposed staff to be sent along with the proposal. How many FTEs are required for each role on the contract? This information will help us understand how many resumes to send along with the proposal.
a. See question #2 above.
4. RFP questions are due 1/5 and the proposal must be mailed by 1/10 and routed to the
Office of Acquisition who must stamp it as received by 1/12 by 2 pm. In order to properly evaluate and incorporate the response to questions, we respectfully request submission by email on or before 1/12 at 2 PM MST, and follow up with a hard copy submission of our proposal mailed via overnight carrier for delivery to the facility on
1/13.
a. The proposals are due at 2:00pm Denver local time on the date specified. There is no plan to change this date or time.
5. Will DOT FHWA provide P6 licenses for assigned on‐site schedulers?
a. Yes.
6. Page 36 of 69 states “The Contractor shall be responsible for IT* security for all systems operated by or connected to a DOT network, regardless of location.” According to the scope the Contractor will be working in the role as an advisor, providing expertise in
Primavera software configuration, implementation, trouble‐shooting, etc. Will DOT
FWHA consider removing the responsibility for all IT* security for all systems operated by or connected to a DOT network, regardless of location from the RFP?
a. No.
7. Since the nature of the work is Primavera project scheduling and reporting and not IT, would DOT FWHA consider changing the NAICS to 541611?
a. <We are looking into this>
8. Throughout the RFP, there are requirements related to transition of incumbent personnel. Are there incumbent personnel performing work at each site? If so, could you provide the name of the incumbent contractor and number of personnel assigned to each site?
a. Lakewood, CO Incumbent: ASL Management, 3113 Colgate Dr, Longmont CO
80503. Currently has (3) employees on‐site.
b. Vancouver, WA Incumbent: PRIME: Stenstrom Group Inc., 170 E. Fair Harbor
Land, Grapeview, WA 98546 SUB: Schedule and Information Services, PO Box
174, Stevenson WA
9. Pages 2, 3, and 4 (of 69) provide rate schedules for each location with the labor categories of Lead Scheduler and Scheduler. However, TOPR#001 and TOPR#002 state work will be performed in Lakewood, CO and Vancouver, WA, respectively, with the labor categories of Lead Scheduler, Scheduler 1 and Scheduler 2. Would DOT FWHA please confirm the work locations and labor categories for each task order?
a. Pages 2, 3, and 4 is for contractors to input their pricing for all 4 locations which might have Task Orders issued for them under this IDIQ contract over the next 5 years.
b. TOPR#001 & TOPR#002 are being offered with the IDIQ because there is a need for services at those two locations currently.
i. See question 2, above, for more information.
c. There is not a need for services at the other two locations (Washington DC and
Stirling, VA) at this time, but it is anticipated that there could be over the 5‐year life of this contract.
10. Will the Cover pages, Table of Contents, List of Acronyms, and divider tabs be excluded from the page count?
a. No.
11. Does Volume II need to be in its own three‐ring binder? So, one binder for Volume I and one binder for Volume 2…or all together?
a. Please package Volume 1 and Volume 2 seperately.
12. Is there a preferred format or template for resumes, or can those be in general long‐ form format?
a. Formatting is up to the contractor, however the entire proposal must still be within the page count.
13. Do resumes count as part of the 50 page cap on Volume I?
14. Do project examples count as part of the 50 page cap on Volume I?
15. Is there any chance that the due date for this proposal will be postponed?
a. Not currently