T A B U L A T I O N O F B I D S
Schedule A Total of Bid Items: 5,410,457.50$ 13.3% 6,131,456.55$ 34.4% 7,274,007.00$ Project No: CO FLAP CR77(5)
Project Name: Tarryall Creek Road
CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount Unit Price Amount
15101-0000
Line A0020 ALL LPSM 532,239.00$ 532,239.00$ 705,000.00$ 710,000.00$
15206-0000
Line A0040 241.070 STA 175.00$ 42,187.25$ 20,490.95$ 60,267.50$
15215-1000
Line A0060 17 EACH 725.00$ 12,325.00$ 10,200.00$ 14,450.00$
15215-3000
Line A0080 32 EACH 600.00$ 19,200.00$ 22,400.00$ 14,720.00$
15216-2000
Line A0100 482.140 STA 125.00$ 60,267.50$ 43,392.60$ 96,428.00$
15301-0000
Line A0120 ALL LPSM 75,000.00$ 75,000.00$ 70,000.00$ 95,000.00$
15401-0000
Line A0140 ALL LPSM 90,000.00$ 90,000.00$ 210,000.00$ 160,000.00$
15501-0000
Line A0160 ALL LPSM 10,000.00$ 10,000.00$ 22,000.00$ 35,000.00$
15705-0100
Line A0180 11,200 LNFT 2.00$ 22,400.00$ 22,400.00$ 42,224.00$
15705-1400
Line A0200 11,800 LNFT 5.50$ 64,900.00$ 35,400.00$ 47,200.00$
15706-0200
Line A0220 57 EACH 275.00$ 15,675.00$ 2,508.00$ 28,500.00$
15706-1600
Line A0240 3 EACH 2,400.00$ 7,200.00$ 4,500.00$ 6,000.00$
15802-0000
Line A0260 ALL LPSM 65,000.00$ 65,000.00$ 54,000.00$ 85,000.00$
20101-0000
Line A0280 35.0 ACRE 2,500.00$ 87,500.00$ 70,000.00$ 63,000.00$
20301-1900
Line A0300 27 EACH 1,000.00$ 27,000.00$ 40,500.00$ 10,800.00$
20304-1000
Line A0320 ALL LPSM 50,000.00$ 50,000.00$ 30,000.00$ 25,000.00$
20401-0000
Line A0340 38,000 CUYD 18.00$ 684,000.00$ 836,000.00$ 1,140,000.00$
20402-0000
Line A0360 1,000 CUYD 20.00$ 20,000.00$ 33,000.00$ 20,000.00$
20425-1000
Line A0380 120 LNFT 15.00$ 1,800.00$ 3,600.00$ 1,800.00$
21101-2000
Line A0400 135 SQYD 4.50$ 607.50$ 1,215.00$ 540.00$
25101-2000
Line A0420 90 CUYD 57.00$ 5,130.00$ 13,500.00$ 4,950.00$
25101-3000
Line A0440 40 CUYD 90.00$ 3,600.00$ 6,400.00$ 2,200.00$
Engineer's Estimate
160.00$ 55.00$
150.00$ 55.00$
9.00$ 4.00$
30.00$ 15.00$
33.00$ 20.00$
22.00$ 30.00$
30,000.00$ 25,000.00$
1,500.00$ 400.00$
2,000.00$ 1,800.00$
54,000.00$ 85,000.00$
1,500.00$ 2,000.00$
44.00$ 500.00$
3.00$ 4.00$
2.00$ 3.77$
22,000.00$ 35,000.00$
210,000.00$ 160,000.00$
70,000.00$ 95,000.00$
90.00$ 200.00$
250.00$
600.00$ 850.00$
A&S Construction Co. American Civil Constructors, Inc.
85.00$
705,000.00$ 710,000.00$
MOBILIZATION
SLOPE, REFERENCE, AND CLEARING AND GRUBBING STAKE
SURVEY AND STAKING, APPROACH ROAD
REMOVAL OF STRUCTURES AND OBSTRUCTIONS
ROADWAY EXCAVATION
SUBEXCAVATION
CONTRACTOR TESTING
CONSTRUCTION SCHEDULE
SOIL EROSION CONTROL, SILT FENCE
SOIL EROSION CONTROL, SEDIMENT LOG
SOIL EROSION CONTROL, CHECK DAM
SOIL EROSION CONTROL, STABILIZED CONSTRUCTION ENTRANCE
DITCH, EXCAVATION
ROADWAY OBLITERATION, METHOD 2
PLACED RIPRAP, CLASS 2
PLACED RIPRAP, CLASS 3
SURVEY AND STAKING, GRADE FINISHING STAKES
CONTRACTOR QUALITY CONTROL
WATERING FOR DUST CONTROL
CLEARING AND GRUBBING
REMOVAL OF PIPE CULVERT
SURVEY AND STAKING, DRAINAGE STRUCTURE
700.00$ 460.00$
12/11/2015 Page 1 of 4
Project No: CO FLAP CR77(5)
Project Name: Tarryall Creek Road
CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount Unit Price Amount
Engineer's Estimate A&S Construction Co. American Civil Constructors, Inc.
25101-4000
Line A0460 135 CUYD 100.00$ 13,500.00$ 22,950.00$ 7,425.00$
25101-5000
Line A0480 77 CUYD 120.00$ 9,240.00$ 15,400.00$ 4,235.00$
25125-0000
Line A0500 4 EACH 230.00$ 920.00$ 880.00$ 1,100.00$
30103-0000
Line A0520 18,800 CUYD 50.00$ 940,000.00$ 977,600.00$ 1,312,240.00$
40101-5600
Line A0540 11,625 TON 95.00$ 1,104,375.00$ 883,500.00$ 1,621,687.50$
40105-3000
Line A0560 116 TON 175.00$ 20,300.00$ 24,360.00$ 24,360.00$
40920-1000
Line A0580 30 TON 780.00$ 23,400.00$ 27,000.00$ 21,750.00$
41103-0000
Line A0600 70,750 SQYD 0.90$ 63,675.00$ 84,900.00$ 70,750.00$
41105-0000
Line A0620 105 TON 60.00$ 6,300.00$ 9,450.00$ 10,500.00$
41201-1000
Line A0640 30 TON 850.00$ 25,500.00$ 30,000.00$ 23,370.00$
60103-0000
Line A0660 2 EACH 7,400.00$ 14,800.00$ 11,000.00$ 30,000.00$
60103-0700
Line A0680 2 EACH 9,000.00$ 18,000.00$ 22,000.00$ 40,000.00$
60201-0600
Line A0700 85 LNFT 100.00$ 8,500.00$ 11,900.00$ 8,415.00$
60201-0800
Line A0720 1,170 LNFT 110.00$ 128,700.00$ 187,200.00$ 193,050.00$
60201-1000
Line A0740 70 LNFT 150.00$ 10,500.00$ 16,100.00$ 12,250.00$
60201-1100
Line A0760 54 LNFT 190.00$ 10,260.00$ 17,820.00$ 10,260.00$
60202-0800
Line A0780 110 LNFT 200.00$ 22,000.00$ 52,800.00$ 24,750.00$
60210-0600
Line A0800 6 EACH 300.00$ 1,800.00$ 2,700.00$ 1,890.00$
60210-0800
Line A0820 46 EACH 350.00$ 16,100.00$ 25,300.00$ 16,560.00$
60210-1000
Line A0840 2 EACH 680.00$ 1,360.00$ 1,800.00$ 1,500.00$
60210-1100
Line A0860 2 EACH 1,200.00$ 2,400.00$ 2,800.00$ 2,490.00$
60220-0600
Line A0880 55 LNFT 850.00$ 46,750.00$ 93,500.00$ 54,725.00$ 1,700.00$ 995.00$
1,400.00$ 1,245.00$
900.00$ 750.00$
550.00$ 360.00$
450.00$ 315.00$
480.00$ 225.00$
330.00$ 190.00$
230.00$ 175.00$
160.00$ 165.00$
140.00$ 99.00$
11,000.00$ 20,000.00$
5,500.00$ 15,000.00$
1,000.00$ 779.00$
90.00$ 100.00$
1.20$ 1.00$
900.00$ 725.00$
210.00$ 210.00$
76.00$ 139.50$
52.00$ 69.80$
220.00$ 275.00$
200.00$ 55.00$
170.00$ 55.00$
END SECTION FOR 42-INCH PIPE CULVERT
5 FEET SPAN, 4 FEET RISE PRECAST REINFORCED CONCRETE BOX CULVERT
BOULDER
AGGREGATE BASE
SUPERPAVE PAVEMENT, 1/2-INCH OR 3/4-INCH NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3 MILLION ESAL
ANTISTRIP ADDITIVE, TYPE 3
FOG SEAL, EMULSIFIED ASPHALT GRADE CSS-1 OR CSS-1H, SS-1 OR SS-1H
PLACED RIPRAP, CLASS 4
PLACED RIPRAP, CLASS 5
PRIME COAT
36-INCH PIPE CULVERT
42-INCH PIPE CULVERT
48-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT
END SECTION FOR 18-INCH PIPE CULVERT
END SECTION FOR 24-INCH PIPE CULVERT
END SECTION FOR 36-INCH PIPE CULVERT
BLOTTER
TACK COAT GRADE CSS-1, CSS-1H, SS-1, OR SS-1H
CONCRETE, HEADWALL
CONCRETE, HEADWALL FOR DOUBLE 48-INCH PIPE CULVERT (ARCH EQUIVALENT)
18-INCH PIPE CULVERT
24-INCH PIPE CULVERT
12/11/2015 Page 2 of 4
Project No: CO FLAP CR77(5)
Project Name: Tarryall Creek Road
CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount Unit Price Amount
Engineer's Estimate A&S Construction Co. American Civil Constructors, Inc.
60506-0000
Line A0900 500 LNFT 75.00$ 37,500.00$ 67,500.00$ 30,000.00$
60905-1000
Line A0920 22 LNFT 100.00$ 2,200.00$ 2,200.00$ 5,500.00$
61106-1000
Line A0940 1 EACH 6,000.00$ 6,000.00$ 13,000.00$ 10,000.00$
61701-1950
Line A0960 200 LNFT 21.00$ 4,200.00$ 6,800.00$ 8,600.00$
61702-0600
Line A0980 1 EACH 2,400.00$ 2,400.00$ 3,000.00$ 2,590.00$
61702-0800
Line A1000 1 EACH 2,500.00$ 2,500.00$ 3,000.00$ 3,120.00$
61901-0900
Line A1020 7,265 LNFT 3.25$ 23,611.25$ 36,325.00$ 29,060.00$
61902-1400
Line A1040 1 EACH 850.00$ 850.00$ 1,400.00$ 1,225.00$
61902-2500
Line A1060 4 EACH 500.00$ 2,000.00$ 4,400.00$ 4,200.00$
61903-0900
Line A1080 2 EACH 23,000.00$ 46,000.00$ 56,000.00$ 80,000.00$
61920-2000
Line A1100 5 EACH 450.00$ 2,250.00$ 5,000.00$ 5,500.00$
61921-1000
Line A1120 625 LNFT 25.00$ 15,625.00$ 7,500.00$ 7,500.00$
62201-0100
Line A1140 140 HOUR 115.00$ 16,100.00$ 15,400.00$ 12,600.00$
62201-0350
Line A1160 140 HOUR 120.00$ 16,800.00$ 19,600.00$ 12,600.00$
62201-0750
Line A1180 140 HOUR 160.00$ 22,400.00$ 26,600.00$ 11,200.00$
62201-1450
Line A1200 110 HOUR 150.00$ 16,500.00$ 26,400.00$ 27,500.00$
62201-2050
Line A1220 160 HOUR 110.00$ 17,600.00$ 17,600.00$ 14,400.00$
62201-2850
Line A1240 160 HOUR 130.00$ 20,800.00$ 24,000.00$ 22,400.00$
62201-3100
Line A1260 110 HOUR 160.00$ 17,600.00$ 23,100.00$ 22,000.00$
62202-1000
Line A1280 ALL LPSM 40,000.00$ 40,000.00$ 74,000.00$ 20,000.00$
62301-0000
Line A1300 160 HOUR 50.00$ 8,000.00$ 8,800.00$ 6,400.00$
62302-1000
Line A1320 110 HOUR 130.00$ 14,300.00$ 25,300.00$ 13,200.00$
110.00$ 90.00$
240.00$ 250.00$
190.00$ 80.00$
140.00$ 90.00$
110.00$ 90.00$
12.00$ 12.00$
1,000.00$ 1,100.00$
28,000.00$ 40,000.00$
1,100.00$ 1,050.00$
1,400.00$ 1,225.00$
5.00$ 4.00$
3,000.00$ 3,120.00$
3,000.00$ 2,590.00$
34.00$ 43.00$
13,000.00$ 10,000.00$
100.00$ 250.00$
135.00$ 60.00$
SPECIAL LABOR, HIRED TECHNICAL SERVICES
REMOVE AND RESET GATE
REMOVE AND RESET FENCE
DUMP TRUCK, 6 CUBIC YARD MINIMUM CAPACITY
BACKHOE
WHEEL LOADER, 0.4 CUBIC YARD MINIMUM RATED CAPACITY
BULLDOZER, 350HP MINIMUM FLYWHEEL POWER
TERMINAL SECTION, TYPE FLARED
TERMINAL SECTION TYPE TANGENT
FENCE, BARBED WIRE, 4 STRAND
GATE, METAL, 16 FEET WIDTH
GATE, BARBED WIRE, 4-STRAND
CATTLE GUARD, 28 FEET
UNDERDRAIN SYSTEM
GUTTER, CONCRETE
FIRE HYDRANT, DRY
GUARDRAIL SYSTEM G4, TYPE 4, CLASS B STEEL POSTS
ROLLER
MOTOR GRADER, 12 FOOT MINIMUM BLADE
HYDRAULIC EXCAVATOR, 3.0 CUBIC YARD MINIMUM CAPACITY, 165HP MINIMUM FLYWHEEL POWER
MATERIALS TRANSFER VEHICLE
GENERAL LABOR
150.00$ 140.00$
74,000.00$ 20,000.00$
210.00$ 200.00$
230.00$ 120.00$
55.00$ 40.00$
12/11/2015 Page 3 of 4
Project No: CO FLAP CR77(5)
Project Name: Tarryall Creek Road
CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount Unit Price Amount
Engineer's Estimate A&S Construction Co. American Civil Constructors, Inc.
62302-1100
Line A1340 110 HOUR 170.00$ 18,700.00$ 19,800.00$ 22,000.00$
62405-0200
Line A1360 106,700 SQYD 0.85$ 90,695.00$ 256,080.00$ 90,695.00$
62510-2000
Line A1380 21.1 ACRE 1,400.00$ 29,540.00$ 46,420.00$ 16,880.00$
62515-2000
Line A1400 21.1 ACRE 1,200.00$ 25,320.00$ 25,320.00$ 21,100.00$
62901-0600
Line A1420 2,300 SQYD 2.00$ 4,600.00$ 9,200.00$ 5,175.00$
63301-0000
Line A1440 32 EACH 750.00$ 24,000.00$ 17,600.00$ 19,200.00$
63308-2000
Line A1460 55 EACH 65.00$ 3,575.00$ 3,300.00$ 3,300.00$
63309-0100
Line A1480 380 EACH 25.00$ 9,500.00$ 7,600.00$ 8,360.00$
63316-1000
Line A1500 2 EACH 450.00$ 900.00$ 1,200.00$ 1,100.00$
63404-0200
Line A1520 450 GAL 70.00$ 31,500.00$ 27,000.00$ 17,100.00$
63501-1000
Line A1540 ALL LPSM 60,000.00$ 60,000.00$ 80,000.00$ 125,000.00$
63501-2000
Line A1560 ALL LPSM 40,000.00$ 40,000.00$ 22,000.00$ 30,000.00$
63502-0600
Line A1580 4 EACH 400.00$ 1,600.00$ 120.00$ 1,200.00$
63502-0900
Line A1600 2,000 EACH 12.00$ 24,000.00$ 22,000.00$ 60,000.00$
63502-1300
Line A1620 300 EACH 25.00$ 7,500.00$ 10,200.00$ 27,000.00$
63502-2000
Line A1640 2 EACH 13,000.00$ 26,000.00$ 24,000.00$ 6,200.00$
63503-0400
Line A1660 150 LNFT 65.00$ 9,750.00$ 9,000.00$ 3,300.00$
63504-1000
Line A1680 895 SQFT 15.00$ 13,425.00$ 13,425.00$ 15,215.00$
63505-1000
Line A1700 9.5 MILE 1,850.00$ 17,575.00$ 36,100.00$ 26,600.00$
63506-0500
Line A1720 6,000 HOUR 26.00$ 156,000.00$ 156,000.00$ 168,000.00$
63506-0600
Line A1740 2,000 HOUR 48.00$ 96,000.00$ 100,000.00$ 100,000.00$
64620-0400
Line A1760 1 EACH 630.00$ 630.00$ 700.00$ 600.00$
TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
TEMPORARY TRAFFIC CONTROL, FLAGGER
TEMPORARY TRAFFIC CONTROL, PILOT CAR
REMOVE AND RESET MAILBOX
TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
TEMPORARY TRAFFIC CONTROL, CONE, TYPE 28-INCH
TEMPORARY TRAFFIC CONTROL, DRUM
TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
TEMPORARY TRAFFIC CONTROL, CONCRETE BARRIER
TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
OBJECT MARKER, TYPE 2
DELINEATOR, TYPE 1
REMOVE AND RESET SIGN
PAVEMENT MARKINGS, TYPE B
TEMPORARY TRAFFIC CONTROL, TRAFFIC AND SAFETY SUPERVISOR
TEMPORARY TRAFFIC CONTROL, TRAFFIC SIGNAL SYSTEM
SPECIAL LABOR, HIRED SURVEY SERVICES
PLACING CONSERVED TOPSOIL, 3-INCH DEPTH
SEEDING, HYDRAULIC METHOD
MULCHING, HYDRAULIC METHOD
ROLLED EROSION CONTROL PRODUCT, TYPE 2.B
SIGN SYSTEM
2.40$ 0.85$
180.00$ 200.00$
1,200.00$ 1,000.00$
2,200.00$ 800.00$
550.00$ 600.00$
4.00$ 2.25$
20.00$ 22.00$
60.00$ 60.00$
60.00$ 38.00$
600.00$ 550.00$
22,000.00$ 30,000.00$
80,000.00$ 125,000.00$
11.00$ 30.00$
30.00$ 300.00$
12,000.00$ 3,100.00$
34.00$ 90.00$
15.00$ 17.00$
60.00$ 22.00$
26.00$ 28.00$
3,800.00$ 2,800.00$
700.00$ 600.00$
50.00$ 50.00$
12/11/2015 Page 4 of 4