Bid_Tabs.pdf

PDF 573 KB Posted

Attached to
CA FTNP REDW PRES 1(14), Redwood National Park Bridge Preservation
Solicitation number
DTFH68-15-B-00004
Issued by

View the file

Other files

File Type Posted
Bid_Opening_Summary.pdf PDF
QA_REDW.docx DOCX document
QA_REDW.docx DOCX document
QA_REDW.docx DOCX document
QA_REDW.docx DOCX document
A001.pdf PDF
QA_REDW.docx DOCX document
PRAIRIE_CREEK_BRIDGE_-_AS_BUILT_PLANS.pdf PDF
Plans.pdf PDF
Invitation_for_Bid.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tabulation of Bids Report Date: 04/06/15

1 out of 5Source Selection Information - See FAR 2.101 & 3.104

Project No: CA FTNP REDW PRES 1(14)

Project Name: Redwood NP Bridge Pres

Schedule: A

Schedule Type: Base

Solcitation No:

Division: Central Federal Lands

State: CA County: Humboldt

Federal Land: Redwood NP Opened at: Lakewood, CO

Opened by: Michael Smith

Date: 04/02/15

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

DRP Construction Company $622,538.00 1093 Crest Drive Encinitas California 92024

TIMBERWORKS $681,480.55

509 S. Mt. Shasta Blvd.

Mt. Shasta California 96067

West Coast Contractors, Inc. $791,054.75 61050 Highway 101 Coos Bay Oregon 97420

McCullough Construction Inc. $987,350.00 57 Alder Grove Road Arcata, CA California 95521

Engineer's Estimate $474,600.00

2 out of 5Source Selection Information - See FAR 2.101 & 3.104

Project No: CA FTNP REDW PRES 1(14)

Project Name: Redwood NP Bridge Pres

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0100 15101-0000 MOBILIZATION

DRP Construction Company Lump Sum $77,000.00 TIMBERWORKS Lump Sum $86,741.42 West Coast Contractors, Inc. Lump Sum $78,000.00 McCullough Construction Inc. Lump Sum $130,000.00 Engineer's Estimate ALL LPSM Lump Sum $69,576.50

A0150 15215-2000 SURVEY AND STAKING, BRIDGE

DRP Construction Company $3,500.00 $3,500.00

TIMBERWORKS $2,332.00 $2,332.00

West Coast Contractors, Inc. $29,935.00 $29,935.00 McCullough Construction Inc. $3,500.00 $3,500.00 Engineer's Estimate 1 EACH $5,500.00 $5,500.00

A0200 15301-0000 CONTRACTOR QUALITY CONTROL

DRP Construction Company Lump Sum $6,300.00 TIMBERWORKS Lump Sum $3,264.80 West Coast Contractors, Inc. Lump Sum $61,000.00 McCullough Construction Inc. Lump Sum $15,000.00 Engineer's Estimate ALL LPSM Lump Sum $15,000.00

A0250 15401-0000 CONTRACTOR TESTING

DRP Construction Company Lump Sum $6,300.00 TIMBERWORKS Lump Sum $3,498.00 West Coast Contractors, Inc. Lump Sum $6,586.00 McCullough Construction Inc. Lump Sum $2,500.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00

A0300 15501-0000 CONSTRUCTION SCHEDULE

DRP Construction Company Lump Sum $5,600.00 TIMBERWORKS Lump Sum $979.44 West Coast Contractors, Inc. Lump Sum $2,500.00 McCullough Construction Inc. Lump Sum $500.00 Engineer's Estimate ALL LPSM Lump Sum $6,700.00

A0350 15701-0000 SOIL EROSION CONTROL

DRP Construction Company Lump Sum $5,600.00 TIMBERWORKS Lump Sum $7,812.20 West Coast Contractors, Inc. Lump Sum $5,500.00 McCullough Construction Inc. Lump Sum $1,500.00 Engineer's Estimate ALL LPSM Lump Sum $25,000.00

3 out of 5Source Selection Information - See FAR 2.101 & 3.104

Project No: CA FTNP REDW PRES 1(14)

Project Name: Redwood NP Bridge Pres

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0400 20304-1000 REMOVAL OF STRUCTURES AND OBSTRUCTIONS

DRP Construction Company Lump Sum $43,120.00 TIMBERWORKS Lump Sum $46,057.00 West Coast Contractors, Inc. Lump Sum $95,000.00 McCullough Construction Inc. Lump Sum $96,000.00 Engineer's Estimate ALL LPSM Lump Sum $65,000.00

A0450 40301-0000 HOT ASPHALT CONCRETE PAVEMENT

DRP Construction Company $700.00 $31,500.00

TIMBERWORKS $410.53 $18,473.85

West Coast Contractors, Inc. $358.00 $16,110.00 McCullough Construction Inc. $275.00 $12,375.00 Engineer's Estimate 45 TON $250.00 $11,250.00

A0500 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)

DRP Construction Company $2,660.00 $37,240.00

TIMBERWORKS $3,773.83 $52,833.62

West Coast Contractors, Inc. $4,600.00 $64,400.00 McCullough Construction Inc. $4,000.00 $56,000.00 Engineer's Estimate 14 CUYD $1,650.00 $23,100.00

A0550 55302-3700 PRECAST, PRESTRESSED CONCRETE DECKED BULB TEE GIRDERS

DRP Construction Company $1,008.00 $293,328.00

TIMBERWORKS $1,203.81 $350,308.71

West Coast Contractors, Inc. $1,000.00 $291,000.00 McCullough Construction Inc. $1,950.00 $567,450.00 Engineer's Estimate 291 LNFT $468.00 $136,188.00

A0600 55401-2000 REINFORCING STEEL, EPOXY COATED

DRP Construction Company $5.60 $19,460.00

TIMBERWORKS $5.83 $20,259.25

West Coast Contractors, Inc. $9.33 $32,421.75 McCullough Construction Inc. $5.00 $17,375.00 Engineer's Estimate 3,475 LB $1.98 $6,880.50

A0650 55601-0900 BRIDGE RAILING, STEEL

DRP Construction Company $238.00 $51,884.00

TIMBERWORKS $258.55 $56,363.90

West Coast Contractors, Inc. $250.00 $54,500.00 McCullough Construction Inc. $275.00 $59,950.00 Engineer's Estimate 218 LNFT $265.00 $57,770.00

4 out of 5Source Selection Information - See FAR 2.101 & 3.104

Project No: CA FTNP REDW PRES 1(14)

Project Name: Redwood NP Bridge Pres

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0700 55901-2000 MEMBRANE WATERPROOFING, TYPE 2

DRP Construction Company $49.00 $8,036.00

TIMBERWORKS $104.76 $17,180.64

West Coast Contractors, Inc. $150.00 $24,600.00 McCullough Construction Inc. $25.00 $4,100.00 Engineer's Estimate 164 SQYD $35.00 $5,740.00

A0750 56401-1000 BEARING DEVICE, ELASTOMERIC

DRP Construction Company $630.00 $5,040.00

TIMBERWORKS $460.72 $3,685.76

West Coast Contractors, Inc. $724.00 $5,792.00 McCullough Construction Inc. $750.00 $6,000.00 Engineer's Estimate 8 EACH $550.00 $4,400.00

A0800 62201-0400 BACKHOE LOADER, 2 CUBIC F00T MINIMUM RATED CAPACITY BUCKET, 12-INCH WIDTH

DRP Construction Company $420.00 $4,200.00

TIMBERWORKS $128.26 $1,282.60

West Coast Contractors, Inc. $125.00 $1,250.00 McCullough Construction Inc. $80.00 $800.00 Engineer's Estimate 10 HOUR $240.00 $2,400.00

A0850 62301-0000 GENERAL LABOR

DRP Construction Company $210.00 $4,200.00

TIMBERWORKS $116.60 $2,332.00

West Coast Contractors, Inc. $90.00 $1,800.00 McCullough Construction Inc. $50.00 $1,000.00 Engineer's Estimate 20 HOUR $70.00 $1,400.00

A0900 63308-3000 OBJECT MARKER, TYPE 3

DRP Construction Company $210.00 $840.00

TIMBERWORKS $80.46 $321.84

West Coast Contractors, Inc. $60.00 $240.00 McCullough Construction Inc. $75.00 $300.00 Engineer's Estimate 4 EACH $150.00 $600.00

A0950 63309-0100 DELINEATOR, TYPE 1

DRP Construction Company $210.00 $3,570.00

TIMBERWORKS $57.96 $985.32

West Coast Contractors, Inc. $60.00 $1,020.00 McCullough Construction Inc. $50.00 $850.00 Engineer's Estimate 17 EACH $75.00 $1,275.00

5 out of 5Source Selection Information - See FAR 2.101 & 3.104

Project No: CA FTNP REDW PRES 1(14)

Project Name: Redwood NP Bridge Pres

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1000 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3

DRP Construction Company $420.00 $2,520.00

TIMBERWORKS $116.60 $699.60

West Coast Contractors, Inc. $500.00 $3,000.00 McCullough Construction Inc. $100.00 $600.00 Engineer's Estimate 6 EACH $120.00 $720.00

A1050 63502-0900 TEMPORARY TRAFFIC CONTROL, CONE, TYPE 28-INCH

DRP Construction Company $70.00 $700.00

TIMBERWORKS $20.99 $209.90

West Coast Contractors, Inc. $50.00 $500.00 McCullough Construction Inc. $30.00 $300.00 Engineer's Estimate 10 EACH $30.00 $300.00

A1100 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

DRP Construction Company $28.00 $4,200.00

TIMBERWORKS $15.73 $2,359.50

West Coast Contractors, Inc. $20.00 $3,000.00 McCullough Construction Inc. $15.00 $2,250.00 Engineer's Estimate 150 SQFT $22.00 $3,300.00

A1150 63610-2800 CONDUIT, 4-INCH, PVC

DRP Construction Company $25.20 $7,560.00

TIMBERWORKS $7.00 $2,100.00

West Coast Contractors, Inc. $23.00 $6,900.00 McCullough Construction Inc. $20.00 $6,000.00 Engineer's Estimate 300 LNFT $40.00 $12,000.00

A1200 63621-1000 UTILITY BOX, PULLBOX

DRP Construction Company $280.00 $840.00

TIMBERWORKS $466.40 $1,399.20

West Coast Contractors, Inc. $2,000.00 $6,000.00 McCullough Construction Inc. $1,000.00 $3,000.00 Engineer's Estimate 3 EACH $3,500.00 $10,500.00

Total Schedule - All Items

DRP Construction Company $622,538.00

TIMBERWORKS $681,480.55

West Coast Contractors, Inc. $791,054.75 McCullough Construction Inc. $987,350.00 Engineer's Estimate $474,600.00

File details come from the government source that posted it. Updated .