QUESTIONS_AND_ANSWERS_Additional_Clarification_for_previous_question_8.6.13.pdf

PDF 83 KB Posted

Attached to
CA PFH 112-1(3) South Fork Smith River Road - George E Tyron Bridge Replacement Federal contract opportunity
Solicitation number
DTFH68-13-R-00010
Issued by
Department of Transportation Federal Highway Administration

About this file

QUESTIONS AND ANSWERS_Additional Clarification for previous question_8.6.13

View the file

Other files for this federal contract opportunity

Other files attached to CA PFH 112-1(3) South Fork Smith River Road - George E Tyron Bridge Replacement, newest first.
File Type Posted
QUESTIONS_AND_ANSWERS_8.6.13.pdf PDF
QUESTIONS_AND_ANSWERS_8.1.13.pdf PDF
CA_PFH_112-1(3)__Pre-proposal_Meeting_Notes_Sign_In_7.23.13.pdf PDF
APPENDIX_A_Continued..pdf PDF
APPENDIX_A.pdf PDF
DTFH68-13-R-00010_RFP_South_Fork_Smith_River_Road_7.1.16.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS AND ANSWERS

DTFH68-13-R-00010

SOUTH FORK SMITH RIVER

This question is being updated. Previous answer was only; yes.

1.Referring to bid item 55302-3300 (Pre-cast, pre-stressed concrete AASHTO girder), can the

Type I AASHTO girder be replaced with a Caltrans approved equal?

Answer: suggest bidders bid the girder shown and if they want to make substitutes that would be in the alternate technical concepts section. We would assume contractors would also consider lengthening the spans and propose a substitute girder in that section. We want contractors to price what we show on the drawings for the bid items and show any improvements elsewhere.