QUESTIONS_AND_ANSWERS_8.6.13.pdf

PDF 162 KB Posted

Attached to
CA PFH 112-1(3) South Fork Smith River Road - George E Tyron Bridge Replacement Federal contract opportunity
Solicitation number
DTFH68-13-R-00010
Issued by
Department of Transportation Federal Highway Administration

About this file

Questions and Answers_8.6.13

View the file

Other files for this federal contract opportunity

Other files attached to CA PFH 112-1(3) South Fork Smith River Road - George E Tyron Bridge Replacement, newest first.
File Type Posted
QUESTIONS_AND_ANSWERS_Additional_Clarification_for_previous_question_8.6.13.pdf PDF
QUESTIONS_AND_ANSWERS_8.1.13.pdf PDF
CA_PFH_112-1(3)__Pre-proposal_Meeting_Notes_Sign_In_7.23.13.pdf PDF
APPENDIX_A_Continued..pdf PDF
APPENDIX_A.pdf PDF
DTFH68-13-R-00010_RFP_South_Fork_Smith_River_Road_7.1.16.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS AND ANSWERS

DTFH68-13-R-00010

SOUTH FORK SMITH RIVER

1. Can the Temporary bridge be HS20 Loading?

Answer: The RFP does not specify the design criteria for the temporary bridge, but

HS20 is acceptable.

2. Clarification – Minimum 12-foot travel lane with barriers, for a minimum out to out width of 16ft.

a. Please clarify what you mean by out –to-out width.

Answer: The key dimension is a 12-foot travel lane. The out-to-out width was an assumption that can vary depending on the bridge type and use. There must be sufficient room between the two bridges to construct the permanent bridge.

3. Do you have an idea of how long (duration) the temp bridge will be install.

Answer: The duration of use depends on the contractor’s schedule for construction of the permanent structure. Since the new permanent bridge is on the same alignment as the existing bridge, it is anticipated that the temporary bridge is constructed first, then traffic is switched on the temp bridge while the existing bridge is removed and maintained on the temp bridge until the new bridge is open to traffic. However, the contractor may have another sequence in mind.

4. Referring to bid item 55201-TEMP (Temporary Bridge and Foundation and Removal):

A. Is the required traffic load design HS-20 or HL-93? HS-20 Acceptable B. Since the lane is only 12’-0 wide, is an alternating direction timed stop light required? Yes

5. Referring to bid item 55302-3300 (Pre-cast, pre-stressed concrete AASHTO girder), can the Type I AASHTO girder be replaced with a Caltrans approved equal? Yes

6. Please provide the Liquidated Damages for this contract. Page C-7 refers to ”See FP-03” and we cannot find this document to provide this information to the surety.

http://flh.fhwa.dot.gov/resources/pse/specs/