A002ChesterWarnerValley.pdf
PDF 631 KB Posted
- Solicitation number
- DTFH68-13-B-00011
About this file
Amendment A002 makes changes to sections 107 and 157 changes associated with the SWPPP and monitoring requirements. No extension due to this amendment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A001_Control_Road.pdf | ||
| FO_IFB_-_AZ_FLAP_64(3) _199(1) _288(3).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
jeremiah.rogers Typewritten Text
E-14
CA FLAP 312(2)
Chester Warner Valley Road
Section 107. - LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC
107.01 Laws to be Observed. Add the following:
“Good Housekeeping” Practices and Requirements.
Locate machinery servicing and refueling areas away from streambeds and washes to reduce the possibility and minimize the impacts of accidental spills or discharges.
Where the Contractor’s working area encroaches on a running or intermittent stream, construct and maintain adequate barriers to prevent the discharge of any contaminants into the stream.
Fording of running streams with construction equipment will not be permitted. Obtain approval from the CO to use temporary bridges or other structures whenever crossings are necessary.
Immediately clear ephemeral drainages, intermittent and perennial streams, lakes and reservoirs of all work items, debris or other obstructions inadvertently placed thereby or resulting from construction operations.
Section 401 and 404 of the Clean Water Act.
Comply with the terms and conditions of the 404 permit and with the terms and conditions, if any, specified in the 401 certification. Comply with the terms and conditions of any permits that are issued for the performance of work within the jurisdictional waters of the U.S.
National Pollutant Discharge Elimination System (NPDES) in California
Comply with the requirements of the California Construction General Permit (CGP) Order No.
2009-0009-DWQ as amended 07/17/2012. A copy of the permit is located at:
http://www.swrcb.ca.gov/water_issues/programs/stormwater/constpermits.shtml
Amend the Storm Water Pollution Prevention Plan SWPPP and site plan prior to submission of the Notice of Intent (NOI) by the Government.
(a) General. Designate the Erosion Control Supervisor according to Subsection 157.03 who will be responsible for implementing the Storm Water Pollution Prevention Plan (SWPPP). The Erosion Control Supervisor must be a Qualified SWPPP Practitioner (QSP) familiar with the CGP and the SWPPP procedures and practices.
(a) General. Designate an Erosion Control Supervisor that is familiar with the CA CGP and SWPPP procedures and practices and will be responsible for implementing the SWPPP. Provide an ECS that is scheduled to be on the jobsite during work hours. If the ECS is not a CA Qualified SWPPP Practitioner (QSP), the ECS must be trained and audited by a designated QSP. The QSP must be available to prepare required project documents for rain events.
Amendment A002 July 25, 2013
E-15
Obtain a separate NPDES permit associated with industrial activity for any mobile asphalt and concrete plants that provide material for the project. Provide a copy of the permit and acknowledgement letter to the CO for their records.
(b) Preparation of SWPPP. The Government has prepared a preliminary SWPPP for the project and determined the project is Risk Level 1 2. Designate a Qualified SWPPP Developer (QSD) certified by the State of California to update the preliminary SWPPP for the project or develop a new SWPPP and provide to the CO for review. When the SWPPP is approved and signed by the CO, QSD, and Contractor, it will be the document in force on the project. Provide an electronic copy of the approved SWPPP to the CO for inclusion in permit registration documents. Implement the SWPPP as required throughout the construction period.
Retain the QSD for the duration of the project to write and approve amendments to the SWPPP.
The QSD may modify the erosion and sediment control details and layout sheets included in the plans, as necessary, to address project site conditions and proposed construction operations.
Submit changes to CO for approval and include the changes in the SWPPP.
Register at least one person on the project with the Stormwater Multiple Application and Report Tracking System (SMARTS). Provide the registered person’s username information to the CO for designation as a data submitter for the project in the SMARTS system. Additional data submitters, such as laboratories, may also be provided to the CO, if necessary. Submit the Annual Report in the SMARTS system as required by the CGP by August 15 and at completion of the project.
(c) Permit Registration Documents. The Government will file these documents upon receipt of the approved SWPPP. Allow 21 calendar days for submittal and approval by the State Water Board. Post a copy of the NOI acknowledgement at the construction site bulletin board for the duration of the project. Do not perform any ground disturbing activities including clearing, grubbing, or earthwork until an acknowledgement letter is received from the State Water Board and the SWPPP has been approved and implemented.
(d) Inspections and Revisions to the SWPPP. Conduct inspections according to the CGP.
Document the inspections on forms provided in the SWPPP. Retain inspection forms onsite in the SWPPP notebook throughout the construction period. Submit monitoring reports in the SMARTS system when required by the CGP.
Revisions to the SWPPP by a QSD may be necessary during construction to make improvements or to respond to unforeseen conditions noted during construction or site inspections. For that purpose, specify in the SWPPP the mechanism whereby revisions may be proposed by the Contractor or the CO and incorporated into the plan, including review and approval of minor changes. Jointly approve and sign each revision to the SWPPP before implementation. Begin implementation of approved modifications within 72 hours following the inspection when deficiencies or necessary corrections were first noted.
E-16
Place the SWPPP and all updates in a three-ring binder so that completed inspection forms and other records may be inserted. Maintain a current copy of the SWPPP, including a copy of the permit, NOI, Waste Discharge Identification (WDID), and all associated records and forms at the job site throughout the duration of the project. Make the SWPPP available for public inspection and for use by the CO.
At the completion of the project, provide the CO with the complete SWPPP, including inspection forms, logs, monitoring reports, and any other information added during the project.
107.02 Protection and Restoration of Property and Landscape. Delete the sixth paragraph and substitute the following:
Before beginning work in an area, have all utilities located by contacting the Utility Locator Service by dialing 811. See www.call811.com for additional information.. Protect utilities from construction operations. Cooperate with utility owners to expedite the relocation or adjustment of their utilities to minimize interruption of service, duplication of work, and delays.
Add the following:
The locations of the utilities shown in the plans have been certified to a Quality Level C according to the CLFHD Utility Data Quality Certification requirements:
http://www.cflhd.gov/resources/surveymaprow/documents/RoW-UtilityCertification.doc
Status of Utilities:
Company Utility Type Contact Name Phone Number Status 1, 2, 3, or 4
Pacific Gas and Electric
Electric Laird Oelrichs 530-896-4258 4
Frontier Communications
Telecommunications Ron LaBella 530-251-4250 4
Status 1: The utilities are in conflict with the project and REQUIRE relocation by OTHERS DURING construction.
Status 2: The utilities are in conflict with the project and REQUIRE relocation by the Contractor DURING construction.
Status 3: The utilities are in conflict with the project and REQUIRE relocation BEFORE construction.
Status 4: The utilities are located within the project rights of way but require NO relocation.
107.03 Bulletin Board. Delete the text and substitute the following:
107.03 Bulletin Board. Furnish a weatherproof bulletin board of suitable size and construction for continuous display of posters and other information required by the contract. Erect and
E-49
(j) Add the following:
Limit the length of area affected as approved by the CO. See Subsection 108.01 for limitations on work.
Section 157. - SOIL EROSION CONTROL
Construction Requirements
157.03 General. Delete the Subsection and substitute the following:
157.03 General. Provide certified weed free permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction according to the contract erosion control plan, contract permits, Section 107, and this Section. Contract permits amend the requirements of this Section. Do not modify the type, size, or location of any control or practice without approval.
Standard erosion and sediment control devices are provided in the contract. Detail site-specific measures for controlling erosion and sediment as part of the Storm Water Pollution Prevention Plan (SWPPP). Submit the revised SWPPP to the CO for acceptance prior to implementation.
Provide working drawings and associated data. Allow 7 days for acceptance of the drawings or a return for corrections. Do not begin any ground disturbing work until the plan has been accepted and notification that the NOI has been accepted. Include all data and plan updates pertaining to erosion and sediment control in the SWPPP for the project. Include the following in the detailed design:
(a) Address contractual requirements for storm water runoff permits, environmental commitments and other permit requirements here or in Subsection 107.01 and 107.10.
(b) Location of each proposed erosion or sediment control measure.
(c) Type of each erosion or sediment control measure. If standard measures provided in the contract do not fit the field conditions, propose alternatives at least 30 days prior to installation.
(d) Quantities of proposed temporary erosion and sediment control devices to be implemented during construction.
(e) A schedule detailing coordination of erosion and sediment control measures with the various construction operations or stages. Include the furnishing, installation, maintaining, and removing of temporary devices and the installation of permanent erosion control features.
E-50
(f) A schedule outlining the proposed schedule of clearing and grubbing, excavation, embankment, and culvert operations such that the area of disturbed or erodible material is minimized. Schedule the work such that temporary and permanent erosion measures can be incorporated at the earliest practical time.
(g) Construction methods used in various items of work to minimize erosion.
When temporary erosion or sediment control measures are required due to the Contractor's negligence, carelessness, or failure to install permanent controls as part of the work in a timely manner, provide temporary measures at no cost to the Government.
When erosion control measures are not functioning as intended, immediately take corrective action.
At the preconstruction conference, designate in writing a California Qualified Erosion Control Supervisor (ECS) who is qualified and that is responsible for implementing the requirements of this Section and the CGP. Include a resume with previous erosion and sediment control experience, training, and certifications and education. Do not designate the project superintendent as the Erosion Control Supervisor.
157.06A Stabilized Construction Entrance. Before placing the geotextile fabric, clear the area of all trash and debris, grading and compacting the ground to a uniform plane. Overlap adjacent ends of geotextile fabric a minimum of 12 inches.
Maintain stabilized construction entrances to minimize tracking of soil and sediment onto existing public roads. Replenish or replace aggregate material as the aggregate becomes clogged with sediment.
157.12 Inspection and Reporting. Add the following:
Inspect all disturbed and temporarily stabilized areas of the project as required by the Construction General Permit (CGP). Provide copies of reports of all inspections and monitoring performed to the CO within 24 hours of the inspection. Refer to the CGP for current monitoring and inspection requirements.
Monitor the turbidity of waters adjacent to the project daily during the work shift. Take turbidity measurements immediately upstream of the work area and as required by the permit. Additional measurements may be required as directed by the CO. If the measurements show an increase of 10 NTU or more, immediately suspend operations in the vicinity of the problem area and modify the erosion and sediment control measures to eliminate the cause of the high turbidity. Include turbidity readings, locations, time, date, and actions taken, if any, in inspection reports. Also provide documentation of meter calibration.
Monitor for turbidity, pH, settable material and visible construction related pollutants as required by the CA 401 Water Quality Certification (WDID#5A32CR00111) and the National Pollutant
E-50a
Discharge General Permit for Storm Water Discharges Associated with Construction and Land Disturbance Activities Order No. 2009-0009-DWQ as amended by 2010-0014-DWQ & 2012- 006-DWQ (CGP) and Attachment D for Risk Level 2 Requirements. Submit all results to the CO within 24 hours of monitoring. If the measured values exceed tolerances allowed, report the results to the CO by the end of the same work day.
Place copies of all inspections, raw data, and monitoring reports in the official SWPPP binder.
157.14 Acceptance. Add the following:
| Untitled |
| AllAmendmentPages.pdf |
| plan sheets.pdf |
| B001 |
| Bsheet_01_SOQ-01-001.pdf |
| B020 |
| Bsheet_20_Surfacing-02-001.pdf |
| T028 |
| Tsheet_28-001.pdf |
| Text1: |
| Text2: |
| 0: 1 |
| 1: 7 |
| Text3: |
| 0: A002 |
| 1: 7/25/13 |
| 2: |
| 0: |
| 1: CA FLAP 312(2) |
| Text4: |
| 0: |
| 0: FEDERAL HIGHWAY ADMINISTRATION |
CENTRAL FEDERAL LANDS HIGHWAY DIVISION
12300 WEST DAKOTA AVENU, SUITE 360
LAKEWOOD, COLORADO 80228
ATTENTION: JEREMIAH RODGERS
1:
| 1: |
| 0: |
| Text6: |
| 0: DTFH68-13-B-00009 |
| 1: 6/27/13 |
| 2: |
| 3: |
| Check Box7: |
| 0: Yes |
| 2: Yes |
| 1: |
| 0: |
| 0: Off |
| 1: Off |
| 2: Off |
| Check Box9: |
| 1: Off |
| 2: Off |
| 0: |
| 0: Off |
| 1: Off |
| Text10: 0 * |
| Text11: |
| 0: |
| 1: |
| Text12: See Below * |
| Text13: |
Invitation for Bid- "E" Section Remove pages E-14 through E-16 of the IFB and replace with new E-14 through E-16. Changes were made to section 107.
Remove pages E-49 and E-50 of the IFB and replace with new E-49, 50, and 50a. Changes were made to section 157 to reflect the Risk Level 2 designation.
NOTE: When printing revised sheets, turn on 'Document and Markups' in the Print Properties menu to illustrate changes on hard copy print.
Refer to the Q&A section of CFLHD's website (http://www.cflhd.gov/contracting/construction/advertisedprojects.cfm) under the project name for further information.
*FAILURE TO ACKNOWLEDGE THIS AMENDMENT IN BLOCK 19 OF THE SF 1442 BY THE DESIGNATED DATE AND HOUR SPECIFIED IN THE SOLICITATION MAY RESULT IN REJECTION OF YOUR BID (REFER TO SF-1442, PAGE A-2, OF THE SOLICITATION)
| Text14: |
| 0: |
| 1: |
| Text15: |
| 1: |
| 0: |
| 1: |
| 0: |
| 0: |
| 1: |
| Text16: |
| 0: |
| 1: |
| Text17: |
| Text5: |
| 0: 6905001 |
| 1: |
| Check Box1: |
| 0: Yes |
| 1: Off |
File details come from the government source that posted it. Updated .