Schedule of Values.pdf
PDF 79 KB Posted
- Solicitation number
- DTFASA-17-R-00784
About this file
Schedule of Values (pdf)
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Past Performance Questionnaire.pdf | ||
| Statement of Work.pdf | ||
| Specifications.pdf | ||
| 16 Sir DTFASA-17-R-00784 Rev1_Rwy ATL - 16Aug17.pdf | ||
| 3f Drawings_RWY ATL.pdf | ||
| Wage Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Schedule of Values
Title Establish RYW 10/28 PAPI systems Location Hartsfield-Jackson Atlanta International Airport
Atlanta, Georgia
DESCRIPTION QTYUNIT UNIT COST TOTAL
RWY 10 PAPI Cost Estimate 1 LS RWY 28 PAPI Cost Estimate 1 LS
Total Cost Estimate $0.00
�1
Title ATL Establish RWY 10 PAPI System Location Hartsfield Jackson International Airport
Atlanta, GA Project Engineer Nacho Brantley
DESCRIPTION QTYUNIT UNIT COST TOTAL
General Requirements & Mobilization Quality Control 1 MO
Site Prep Site Prep-PAPI foundations 1 LS Site Prep for PAPI P&C Rack 1 LS Site Prep for PAPI Maintenance Pad 1 LS Prefabricated LHA Foundation 4 EA Sod 1 LS Site Cleanup and Restoration 1 LS
Structural PAPI Power & Control Concrete Foundation 1 LS PAPI Power & Control Concrete Maintenance Area 1 LS
Site Electrical Counterpoise - Underground 1 LS Counterpoise - Aboveground 1 LS Power Cabling for LHA 1 thru LHA 4 to the PP&C Unit 1 LS Control Cabling from LHA 1 thru LHA 4 to the PP&C Unit 1 LS
Electrical PAPI Power Cable from PP&CR to Meter Rack 1 LS Install oversize LB for each LHA 1 LS
Ductbank Installation PAPI Ductbank from PAPI LHAs to PP&C 1 LS Install GFM Install LHA Breakaway Connectors 1 LS Install LHAs 4 EA Install PP&C Rack 1 LS
Total Direct Costs
General Requirements Field Overhead 1 LS Bonding and Insurance 1 LS Profit (Contingency) 1 LS Total Indirect Costs Total
�2
Title ATL Establish RWY 28 PAPI System Location Hartsfield Jackson International Airport
Atlanta, GA
DESCRIPTION QTYUNIT UNIT COST TOTAL
General Requirements & Mobilization Quality Control 1 MO
Site Prep Site Prep-PAPI foundations 1 LS Site Prep for PAPI P&C Rack 1 LS Site Prep for PAPI Maintenance Pad 1 LS Prefabricated LHA Foundation 4 EA Sod 1 LS Site Cleanup and Restoration 1 LS
Structural PAPI Power & Control Concrete Foundation 1 LS PAPI Power & Control Concrete Maintenance Area 1 LS Bollard 2 EA
Site Electrical Counterpoise - Underground 1 LS Counterpoise - Aboveground 1 LS Power Cabling for LHA 1 thru LHA 4 to the PP&C Unit 1 LS Control Cabling from LHA 1 thru LHA 4 to the PP&C Unit 1 LS
Electrical PAPI Power Cable from PP&CR to Meter Rack 1 LS Install oversize LB for each LHA 1 LS
Ductbank Installation PAPI Ductbank from PAPI LHAs to PP&C 1 LS Install GFM Install LHA Breakaway Connectors 1 LS Install LHAs 4 EA
Install PP&C Rack 1 LS
Total Direct Costs
General Requirements Field Overhead 1 LS Bonding and Insurance 1 LS Profit (Contingency) 1 LS Total Indirect Costs Total