DTFASA-17-R-00074 AMENDMENT #0003.pdf
PDF 243 KB Posted
- Solicitation number
- DTFASA-17-R-00074
About this file
DTFASA-17-R-00074 AMENDMENT #0003 (pdf)
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OMB Control No. 2120-0595 (SF-30) FAA Template No. 11 (8/97)
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
1 3
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
0003 12/05/2016
6. ISSUED BY 7. ADMINISTRATED BY (If other than Item 6) Federal Aviation Administration Acquisition Management Branch, AAQ-530 1601 Lind Ave SW Renton, WA 98057
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
9A. AMENDMENT OF SOLICITATION NO.
DTFASA-17-R-00074
9B. DATED (SEE ITEM 11)
11/07/2016
10A. MODIFICATION OF CONTRACT/ORDER NO.
*TO BE COMPLETED BY VENDOR IF NOT COMPLETE 10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation on as amended, by one of the following methods:
(a) By completing Item 8 and 15, and returning 1 copies of the amendment; (b) acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDG- MENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hours and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS, IT MODIFIES THE CONTRACT/ORDER NO.
AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copy to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The above referenced solicitation for the MAJOR MECHANICAL SUSTAINMENT MODIFICATION (MMS) PROJECT AT THE SALT LAKE CITY ARTCC, UTAH is amended as follows:
1) Provide follow up Answers to Questions asked by potential Offerors (5 total questions).
2) Add missing clauses 3.6.2-44 Notification of Employee Rights Under the National Labor Relations Act (January 2012) and 3.10.1-19 Modification Cost Proposal – Price Breakdown (Construction) (July 1996) to Part II, Section I.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
ELAINA D. AUDETTE
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
(Signature of person authorized to sign)
BY
(Signature of Contracting Officer)
Amendment #0003
Additional Questions & Answers
Q&A # Question Answer
80 I do not feel that this was answered. Sheet C002 Please provide a drawing showing the pavilion including BBQ design, any gas lines or other utility lines running through this area and sidewalk as we will need to replace concrete and landscaping in this area when replacing the 12” CTS & CTR lines. The plans do not show the pavilion or any detail for the BBQ’s set up in the pavilion. It is likely that the CTS & CTR lines are going to go right under this area. We really need at least a description of what this is so we can figure what work will need to be done.
The observation is correct. Thickness of the slab was already provided in a previous question. We have no other information other than that which can be obtained from visual inspection.
81 I do not feel that this was answered. On sheet C001 note 3 indicates to replace existing 4” CTS/CTR lines but these lines run off the left hand side of the page at grid line E. Please provide a drawing showing where these lines will terminate (PSB Entrance). This question was answered for the 12” lines but the answer did not address the 4” line that trails off the page at grid line E. This is not continued on any other sheet.
Please clarify.
The 4” lines terminate immediately in the Power Services Building. Any detail beyond that has not yet been developed.
82 In the RFO it mentions that 2 chillers to be replaced, but on the drawings it shows 4 chillers being installed. Are 4 chillers being replaced?
Four (4) Chillers.
83 Has the owner selected a commissioning authority? What items or what is the scope for the commissioning agent?
Owner will provide Commissioning Agent. Expect Full Commissioning Process that will be executed but the contractor with owner provided commissions agent.
84 With the replacement on the access flooring and all the equipment needing to stay up
Means and methods to be discussed during the design assist phase.
Amendment #0003 and operating, are we to replace access flooring to the edge of the equipment and leave the existing access flooring under the equipment is to remain.