16 SIR 16R00176_Atch 9_PPQ_Roof Miami - 27Aug16.pdf

PDF 263 KB Posted

Attached to
Roof Replacement at the Miami ARTCC, Miami, Florida
Solicitation number
DTFAEN-16-R-00176
Issued by

About this file

16 SIR 16R00176_Atch 9_PPQ_Roof Miami - 27Aug16 (pdf)

View the file

Other files

File Type Posted
16 SIR 16R00176_Atch 2_DWGS_ZMA-D-1404046 - 13May16.pdf PDF
16 SIR 16R00176_Atch 1_SPECS ZMA div 01-26 - 13May16.pdf PDF
16 SIR 16R00176_Atch 5_App A FAA-STD-019e_01 - 13May16.pdf PDF
16_SIR_Roof Miami Final - 27Aug16.pdf PDF
16 SIR 16R00176_Atch 6_App B ASO Asbestos Control Program - 13May16.pdf PDF
16 SIR 16R00176_Atch 8_Construction Breakdown_Roof Miami - 30Aug16.pdf PDF
21 SF30 Amend 0001 signed Roof Miami - 7Sep16.pdf PDF
16 SIR 16R00176_Atch 7_Bus Dec - 27Aug16.pdf PDF
16 SIR 16R00176_Atch 9_PPQ_Roof Miami - 27Aug16.pdf PDF
16 SIR 16R00176_Atch 4_ACM report - 13Jul16.pdf PDF
16 SIR 16R00176_Atch 3_WD FL20150027_Miami - 26Aug16.pdf PDF
16 SIR 16R00176_Atch 4_ACM report - 13Jul16.pdf PDF
16 SIR 16R00176_Atch 6_App B ASO Asbestos Control Program - 13May16.pdf PDF
16 SIR 16R00176_Atch 9_PPQ_Roof Miami - 27Aug16.pdf PDF
16 SIR 16R00176_Atch 1_SPECS ZMA div 01-26 - 13May16.pdf PDF
16 SIR 16R00176_Atch 3_WD FL20150027_Miami - 26Aug16.pdf PDF
16 SIR 16R00176_Atch 5_App A FAA-STD-019e_01 - 13May16.pdf PDF
16_SIR_Roof Miami Final - 27Aug16.pdf PDF
16 SIR 16R00176_Atch 2_DWGS_ZMA-D-1404046 - 13May16.pdf PDF
16 SIR 16R00176_Atch 8_Construction Breakdown_Roof Miami - 30Aug16.pdf PDF
16 SIR 16R00176_Atch 7_Bus Dec - 27Aug16.pdf PDF
16 SIR 16R00176_Atch 3_WD FL20150027_Miami - 26Aug16.pdf PDF
16 SIR 16R00176_Atch 1_SPECS ZMA div 01-26 - 13May16.pdf PDF
16 SIR 16R00176_Atch 6_App B ASO Asbestos Control Program - 13May16.pdf PDF
16 SIR 16R00176_Atch 4_ACM report - 13Jul16.pdf PDF
16 SIR 16R00176_Atch 2_DWGS_ZMA-D-1404046 - 13May16.pdf PDF
16 SIR 16R00176_Atch 8_Constrution Cost Breakdown - 26Aug16.pdf PDF
16 SIR 16R00176_Atch 5_App A FAA-STD-019e_01 - 13May16.pdf PDF
16 SIR 16R00176_Atch 7_Bus Dec - 27Aug16.pdf PDF
16_SIR_Roof Miami Final - 27Aug16.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OMB No. 2120-0595 DTFAEN-16-R-00176

Attachment 9

Past Performance Survey

Replacement of the roof at the Miami ARTCC (ZMA) and Wing stair roof, Miami, Florida

PAST PERFORMANCE SURVEY

Solicitation No.: DTFAEN-16-R-00176 Replacement of the roof at the Miami ARTCC (ZMA) and Wing stair roof, Miami, Florida

To: ____________________ (Point of Contact) ____________________ (Company) ____________________ (Phone) ____________________ (Fax)

The Federal Aviation Administration is currently evaluating and you were listed as a performance reference. It would be greatly appreciated if you would take 5 or 10 minutes to complete the following information and return to me via email (preferred) by September 28 , 2015 . Email: michael.hollis@faa.gov or Fax: 404-305-5774

If you have any questions or comments, feel free to contact me. Thank you in advance for your assistance.

Michael Hollis Contracting Officer, AAQ-510ATL Eastern Acquisitions Service Area Southern Region, Tel-404-305-5298

Please identify the project(s) that this company has performed for your organization, description, city, state, and approximate dollar value:

Respond to the following on a scale of 1 to 5, with 3 being Acceptable, and 5 being Outstanding.

1. Did the contractor commit adequate resources in timely fashion to the contract to meet the requirements and to successfully solve problems? 1 2 3 4 5

2. To what extent did the contractor respond positively and promptly to technical direction, contract change orders, etc.? 1 2 3 4 5

3. How reliably did the contractor follow through on commitments? 1 2 3 4 5

Replacement of the roof at the Miami ARTCC (ZMA) and Wing stair roof, Miami, Florida

4. To what extent did the contractor’s management system provide visibility into problems and risks? 1 2 3 4 5

5. How responsive do you think the contractor was to information requests, issues, or problems during the course of the contract? 1 2 3 4 5

6. How effective has the contractor been in identifying user requirements?

1 2 3 4 5

7. To what extent did the contractor have the ability to administer and manage the contract?

1 2 3 4 5

8. To what extent did the contractor issue professional correspondence?

1 2 3 4 5

9. How well did the contractor adhere to the Statement of Work? 1 2 3 4 5

10. What was your level of satisfaction with the contractor’s management and support staff?

1 2 3 4 5

11. What was your level of satisfaction with the contractor’s Supervisor(s)?

1 2 3 4 5

12. To what extent did the contractor submit required reports and documentation in a timely manner? 1 2 3 4 5

13. To what extent were the contractor’s reports and documentation accurate and complete?

1 2 3 4 5

14. To what extent was the contractor’s maintenance and problem tracking/reporting documentation timely, accurate and of appropriate content?

1 2 3 4 5

15. To what extent did the contractor comply with safety requirements?

1 2 3 4 5

16. What was your level of satisfaction with the contractor’s overall quality of service?

1 2 3 4 5

Replacement of the roof at the Miami ARTCC (ZMA) and Wing stair roof, Miami, Florida

17. To what extent was the contractor effective in interfacing with the Government staff?

1 2 3 4 5

18. What was your level of overall customer satisfaction? 1 2 3 4 5

19. To what extent were the contractor’s employees experienced and qualified?

1 2 3 4 5

Respond: Yes or No.

20. Were there any cure notices issued? Yes: ____ No: ____

21. Was contractor pro-active? Yes: ____ No: ____

22. Did contractor suggest cost-saving changes? Yes: ____ No: ____

23. Would you recommend this contractor? Yes: ____ No: ____

For Federal contracts:

24. Were there any Labor Department Investigations? Yes: ____ No: ____

24a. If yes, please describe reason and final outcome.

25. Were there any safety investigations? Yes: ____ No: ____

25a. If yes, please describe reason and final outcome.

26. Were there any security investigations? Yes: ____ No: ____

26a. If yes, please describe reason and final outcome.

27. Was there a partial or complete termination for default or convenience? Yes: ___ No: ___

Replacement of the roof at the Miami ARTCC (ZMA) and Wing stair roof, Miami, Florida

27a. If yes, please describe reason and final outcome.

28. Are there any pending terminations? Yes: ____ No: ____

29. What is/was the duration of the contract? _____________________

30. Were there any performance issues regarding the contractor’s work? If yes, please describe.

Please provide other comments:

Signature: ____________________________

Date: ____________________________