About this file

DIV 5 Master (pdf)

View the file

Other files

File Type Posted
Q A 14-R-00036.docx DOCX document
DIV 7 Master.pdf PDF
DIV 1 Master.pdf PDF
FAA Form 3900-18 04.16.2013.pdf PDF
TYS-1003480- Bid Drawings.pdf PDF
DIV 26 Master.pdf PDF
FAA-STD-019e.pdf PDF
DIV 2 Master.pdf PDF
DIV 7 Master.pdf PDF
FAA-STD-019e.pdf PDF
DIV 2 Master.pdf PDF
FAA Form 3900-18 04.16.2013.pdf PDF
DIV 26 Master.pdf PDF
TYS-1003480- Bid Drawings.pdf PDF
DIV 1 Master.pdf PDF
DIV 5 Master.pdf PDF
DIV 26 Master.pdf PDF
DIV 5 Master.pdf PDF
DIV 2 Master.pdf PDF
DIV 7 Master.pdf PDF
FAA-STD-019e.pdf PDF
FAA Form 3900-18 04.16.2013.pdf PDF
DIV 1 Master.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FEDERAL AVIATION ADMINISTRATION January, 2014

FAA-TYS-1003480

SECTION 05 52 13 - PIPE AND TUBE RAILINGS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

Steel pipe railings.

1.2 PERFORMANCE REQUIREMENTS

A. Delegated Design: Design railings, including comprehensive engineering analysis by a qualified professional engineer, using performance requirements and design criteria indicated.

B. Structural Performance: Railings shall withstand the effects of gravity loads and the following loads and stresses within limits and under conditions indicated:

1. Handrails and Top Rails of Guards:

a. Uniform load of 50 lbf/ ft. (0.73 kN/m) applied in any direction.

b. Concentrated load of 200 lbf (0.89 kN) applied in any direction.

c. Uniform and concentrated loads need not be assumed to act concurrently.

C. Control of Corrosion: Prevent galvanic action and other forms of corrosion by insulating metals and other materials from direct contact with incompatible materials.

1.3 SUBMITTALS

A. Product Data: For the following:

1. Manufacturer's product lines of mechanically connected railings.

2. Railing brackets.

3. Paint products.

B. Shop Drawings: Include plans, elevations, sections, details, and attachments to other work.

C. Delegated-Design Submittal: For installed products indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation.

PIPE AND TUBE RAILINGS 05 52 13 - 1

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements

1. Stainless-Steel Pipe Railings:

a. Kee Klamp

2.2 METALS, GENERAL

A. Brackets, Flanges, and Anchors: Cast or formed metal of same type of material and finish as supported rails unless otherwise indicated.

2.3 STEEL

A. Pipe: ASTM A 53/A 53M, No. 6 Galvanized Steel Pipe

B. Plates: ASTM A 36/A 36M.

2.4 MISCELLANEOUS MATERIALS

A. Fasteners: Provide the following:

1. Hot-Dip Galvanized Railings: Type 304 stainless-steel or hot-dip zinc-coated steel fasteners complying with ASTM A 153/A 153M or ASTM F 2329 for zinc coating.

B. Post-Installed Anchors: Simpson Titen HD screw anchors capable of sustaining, without failure, a load equal to four times the load imposed when installed in concrete, as determined by testing according to ASTM E 488, conducted by a qualified independent testing agency.

C. Welding Rods and Bare Electrodes: Select according to AWS specifications for metal alloy welded.

D. Etching Cleaner for Galvanized Metal: Complying with MPI#25.

E. Galvanizing Repair Paint: High-zinc-dust-content paint complying with SSPC-Paint 20 and compatible with paints specified to be used over it.

F. Shop Primer for Galvanized Steel: Cementitious galvanized metal primer complying with

MPI#26

G. Epoxy Intermediate Coat: Complying with MPI #77 and compatible with primer and topcoat.

H. Polyurethane Topcoat: Complying with MPI #72 and compatible with undercoat.

I. Bituminous Paint: Cold-applied asphalt emulsion complying with ASTM D 1187.

PIPE AND TUBE RAILINGS 05 52 13 - 2

2.5 FABRICATION

A. Cut, drill, and punch metals cleanly and accurately. Remove burrs and ease edges to a radius of approximately 1/32 inch (1 mm) unless otherwise indicated. Remove sharp or rough areas on exposed surfaces.

B. Form work true to line and level with accurate angles and surfaces.

C. Welded Connections: Cope components at connections to provide close fit, or use fittings designed for this purpose. Weld all around at connections, including at fittings.

1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals.

2. Obtain fusion without undercut or overlap.

3. Remove flux immediately.

4. At exposed connections, finish exposed surfaces smooth and blended so no roughness shows after finishing and welded surface matches contours of adjoining surfaces.

D. Nonwelded Connections: Connect members with concealed mechanical fasteners and fittings.

Fabricate members and fittings to produce flush, smooth, rigid, hairline joints.

E. Form changes in direction by inserting prefabricated elbow fittings.

F. Bend members in jigs to produce uniform curvature without buckling or otherwise deforming exposed surfaces.

G. Close exposed ends of railing members with prefabricated end fittings.

H. Provide wall returns at ends of wall-mounted handrails unless otherwise indicated.

I. Brackets, Flanges, Fittings, and Anchors: Provide wall brackets, flanges, miscellaneous fittings, and anchors to interconnect railing members to other work unless otherwise indicated.

1. At brackets and fittings fastened to plaster or gypsum board partitions, provide crush-resistant fillers to transfer loads through wall finishes.

2.6 STEEL FINISHES

A. Galvanized Railings:

1. Hot-dip galvanize steel railings, including hardware, after fabrication.

2. Comply with ASTM A 123/A 123M for hot-dip galvanized railings.

3. Comply with ASTM A 153/A 153M for hot-dip galvanized hardware.

B. Preparing Galvanized Railings for Shop Priming: After galvanizing, thoroughly clean railings of grease, dirt, oil, flux, and other foreign matter, and treat with etching cleaner.

C. Primer Application: Apply shop primer to prepared surfaces of railings unless otherwise indicated. Comply with requirements in SSPC-PA 1, "Paint Application Specification No. 1:

Shop, Field, and Maintenance Painting of Steel," for shop painting.

PIPE AND TUBE RAILINGS 05 52 13 - 3

1. Do not apply primer to galvanized surfaces.

D. High-Performance Coating: Apply epoxy intermediate and polyurethane topcoats to prime-coated surfaces. Comply with coating manufacturer's written instructions and with requirements in SSPC-PA 1, "Paint Application Specification No. 1: Shop, Field, and Maintenance Painting of Steel," for shop painting. Apply at spreading rates recommended by coating manufacturer.

1. Color: As indicated by manufacturer's designations

PART 3 - EXECUTION

3.1 INSTALLATION

A. Set railings accurately in location, alignment, and elevation; measured from established lines and levels and free of rack.

1. Do not weld, cut, or abrade surfaces of railing components that have been coated or finished after fabrication and that are intended for field connection by mechanical or other means without further cutting or fitting.

2. Set posts plumb within a tolerance of 1/16 inch in 3 feet (2 mm in 1 m).

3. Align rails so variations from level for horizontal members and variations from parallel with rake of steps and ramps for sloping members do not exceed 1/4 inch in 12 feet (5 mm in 3 m).

B. Attach railings to wall with wall brackets. Use type of bracket with predrilled hole for exposed bolt anchorage.

C. Secure wall brackets and railing end flanges to building construction as follows:

1. For concrete, use Simpson Titen HD screw anchors

2. For steel-framed partitions, use toggle bolts installed through flanges of steel framing or through concealed steel reinforcements.

3.2 ADJUSTING AND CLEANING

A. Touchup Painting: Immediately after erection, clean field welds, bolted connections, and abraded areas of shop paint, and paint exposed areas with the same material as used for shop painting to comply with SSPC-PA 1 for touching up shop-painted surfaces.

B. Galvanized Surfaces: Clean field welds, bolted connections, and abraded areas and repair galvanizing to comply with ASTM A 780.

END OF SECTION 055213

PIPE AND TUBE RAILINGS 05 52 13 - 4

PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
Steel pipe railings.
1.2 PERFORMANCE REQUIREMENTS
A. Delegated Design: Design railings, including comprehensive engineering analysis by a qualified professional engineer, using performance requirements and design criteria indicated.
B. Structural Performance: Railings shall withstand the effects of gravity loads and the following loads and stresses within limits and under conditions indicated:
1. Handrails and Top Rails of Guards:
a. Uniform load of 50 lbf/ ft. (0.73 kN/m) applied in any direction.
b. Concentrated load of 200 lbf (0.89 kN) applied in any direction.
c. Uniform and concentrated loads need not be assumed to act concurrently.

C. Control of Corrosion: Prevent galvanic action and other forms of corrosion by insulating metals and other materials from direct contact with incompatible materials.

1.3 SUBMITTALS
A. Product Data: For the following:
1. Manufacturer's product lines of mechanically connected railings.
2. Railing brackets.
3. Paint products.
B. Shop Drawings: Include plans, elevations, sections, details, and attachments to other work.
C. Delegated-Design Submittal: For installed products indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Manufacturers: Subject to compliance with requirements
1. Stainless-Steel Pipe Railings:
a. Kee Klamp
2.2 METALS, GENERAL
A. Brackets, Flanges, and Anchors: Cast or formed metal of same type of material and finish as supported rails unless otherwise indicated.
2.3 STEEL
A. Pipe: ASTM A 53/A 53M, No. 6 Galvanized Steel Pipe
B. Plates: ASTM A 36/A 36M.
2.4 MISCELLANEOUS MATERIALS
A. Fasteners: Provide the following:
1. Hot-Dip Galvanized Railings: Type 304 stainless-steel or hot-dip zinc-coated steel fasteners complying with ASTM A 153/A 153M or ASTM F 2329 for zinc coating.
B. Post-Installed Anchors: Simpson Titen HD screw anchors capable of sustaining, without failure, a load equal to four times the load imposed when installed in concrete, as determined by testing according to ASTM E 488, conducted by a qualified indep...
C. Welding Rods and Bare Electrodes: Select according to AWS specifications for metal alloy welded.
D. Etching Cleaner for Galvanized Metal: Complying with MPI#25.
E. Galvanizing Repair Paint: High-zinc-dust-content paint complying with SSPC-Paint 20 and compatible with paints specified to be used over it.
F. Shop Primer for Galvanized Steel: Cementitious galvanized metal primer complying with MPI#26
G. Epoxy Intermediate Coat: Complying with MPI #77 and compatible with primer and topcoat.
H. Polyurethane Topcoat: Complying with MPI #72 and compatible with undercoat.
I. Bituminous Paint: Cold-applied asphalt emulsion complying with ASTM D 1187.
2.5 FABRICATION
A. Cut, drill, and punch metals cleanly and accurately. Remove burrs and ease edges to a radius of approximately 1/32 inch (1 mm) unless otherwise indicated. Remove sharp or rough areas on exposed surfaces.
B. Form work true to line and level with accurate angles and surfaces.
C. Welded Connections: Cope components at connections to provide close fit, or use fittings designed for this purpose. Weld all around at connections, including at fittings.
1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals.
2. Obtain fusion without undercut or overlap.
3. Remove flux immediately.
4. At exposed connections, finish exposed surfaces smooth and blended so no roughness shows after finishing and welded surface matches contours of adjoining surfaces.
D. Nonwelded Connections: Connect members with concealed mechanical fasteners and fittings. Fabricate members and fittings to produce flush, smooth, rigid, hairline joints.
E. Form changes in direction by inserting prefabricated elbow fittings.
F. Bend members in jigs to produce uniform curvature without buckling or otherwise deforming exposed surfaces.
G. Close exposed ends of railing members with prefabricated end fittings.
H. Provide wall returns at ends of wall-mounted handrails unless otherwise indicated.
I. Brackets, Flanges, Fittings, and Anchors: Provide wall brackets, flanges, miscellaneous fittings, and anchors to interconnect railing members to other work unless otherwise indicated.
1. At brackets and fittings fastened to plaster or gypsum board partitions, provide crush-resistant fillers to transfer loads through wall finishes.
2.6 STEEL FINISHES
A. Galvanized Railings:
1. Hot-dip galvanize steel railings, including hardware, after fabrication.
2. Comply with ASTM A 123/A 123M for hot-dip galvanized railings.
3. Comply with ASTM A 153/A 153M for hot-dip galvanized hardware.
B. Preparing Galvanized Railings for Shop Priming: After galvanizing, thoroughly clean railings of grease, dirt, oil, flux, and other foreign matter, and treat with etching cleaner.
C. Primer Application: Apply shop primer to prepared surfaces of railings unless otherwise indicated. Comply with requirements in SSPC-PA 1, "Paint Application Specification No. 1: Shop, Field, and Maintenance Painting of Steel," for shop painting.
1. Do not apply primer to galvanized surfaces.
D. High-Performance Coating: Apply epoxy intermediate and polyurethane topcoats to prime-coated surfaces. Comply with coating manufacturer's written instructions and with requirements in SSPC-PA 1, "Paint Application Specification No. 1: Shop, Fiel...
1. Color: As indicated by manufacturer's designations
PART 3 - EXECUTION
3.1 INSTALLATION
A. Set railings accurately in location, alignment, and elevation; measured from established lines and levels and free of rack.
1. Do not weld, cut, or abrade surfaces of railing components that have been coated or finished after fabrication and that are intended for field connection by mechanical or other means without further cutting or fitting.
2. Set posts plumb within a tolerance of 1/16 inch in 3 feet (2 mm in 1 m).
3. Align rails so variations from level for horizontal members and variations from parallel with rake of steps and ramps for sloping members do not exceed 1/4 inch in 12 feet (5 mm in 3 m).
B. Attach railings to wall with wall brackets. Use type of bracket with predrilled hole for exposed bolt anchorage.
C. Secure wall brackets and railing end flanges to building construction as follows:
1. For concrete, use Simpson Titen HD screw anchors
2. For steel-framed partitions, use toggle bolts installed through flanges of steel framing or through concealed steel reinforcements.
3.2 ADJUSTING AND CLEANING
A. Touchup Painting: Immediately after erection, clean field welds, bolted connections, and abraded areas of shop paint, and paint exposed areas with the same material as used for shop painting to comply with SSPC-PA 1 for touching up shop-painted su...
B. Galvanized Surfaces: Clean field welds, bolted connections, and abraded areas and repair galvanizing to comply with ASTM A 780.