SIR/RFO DTFAAC-17-R-00001
Addendum Two
May 9, 2017
Attachment 23
Addendum Two forms a part of the Contract Documents and modifies the original bid documents. Items in this Addendum take precedence over the original documents. Addendum Two consists of the following:
Clarification to Addendum One, Question 66.
66. Page 32, 5.1.2 Assistant Project Manager states “The assistant project manager shall be on-site when any work is being performed at the Aeronautical Center”.
QUESTION: Is the intent of the Government to have an Assistant Project Manager 24 hours, 7 days per week at the Center?
ANSWER: No. Task 3 is 24/7 but does not require an APM to be present. An APM must be present during the normal core hours and when a large crew is present performing work. Examples: An emergency situation, with 1 or 2 employees, does not need an APM. Multiple contract employees on a regular or an emergency situation outside the normal core hours would require an APM unless otherwise approved by the appropriate COR.