About this file
This is a Request for Quotation (RFQ) issued by the State of Michigan Department of Environment, Great Lakes, and Energy for orphan well plugging and site restoration services in Newaygo and Mecosta Counties. The project involves plugging, drilling, re-drilling, and site restoration at two wells: the Troyer 1-7A (Mecosta County, Permit #60486) and the Daniels 1-1B (Newaygo County, Permit #56879), both operated by Wellmaster Production. Only vendors who have been awarded a contract through a prequalification process are eligible to submit proposals. A mandatory pre-proposal meeting will be held on Tuesday, November 10, 2026, at 12:00 noon Eastern at the Troyer 1-7A project site; attendance is required to submit a proposal. The deadline for bidder questions is Friday, November 13, 2026, at 3:00 p.m. Eastern, with answers posted on November 17, 2026. The proposal deadline is Tuesday, November 24, 2026, at 3:00 p.m. Eastern, with a pre-construction meeting and project start date to be determined. All proposals must be submitted electronically through www.michigan.gov/SIGMAVSS in modifiable formats with a maximum file size of 6 MB per document.
Technical evaluation will be based on four equally weighted criteria (25 points each): Key Personnel, Business Owned Equipment List, Company's Technical Experience and Ability, and Vendor Questions Worksheet, for a total of 100 points. Only proposals receiving 80 or more technical evaluation points will be considered for award. Bidders must provide pricing for all line items in the pricing matrix, submit a detailed project timeline broken down into Site Prep, Mobilization/Demobilization, Plugging, and Site Restoration phases, and include staffing information. The award will be based on best value to the state, not necessarily the lowest price. The winning bidder and all subcontractors must comply with Davis-Bacon prevailing wage requirements, as federal funds will be used for this project. Bidders are advised to inform subcontractors that pricing must include Davis-Bacon prevailing wage rates, and the state will not approve change orders related to improper bidding due to failure to include these rates. The state may also consider qualified disabled veterans/service-disabled veteran owned business (QDV/SDVOB) status under MCL 18.1261(8) during evaluation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF MICHIGAN
Department of Environment, Great Lakes, and Energy Wellmaster - Newaygo & Mecosta Orphan Well Plugging Project (Newaygo and Mecosta Counties) – 2 Wells
Direct Solicitation DS270000000007 Solicitation Manager Name: Lisa VanOstran Direct Phone: 517-599-7680 Email: vanostranl@michigan.gov
This is a Request for Quotation (RFQ) for:
Plugging, drilling, re-drilling, and site restoration at the Troyer 1-7A (Mecosta County) and the Daniels 1-1B (Newaygo County).
Only vendors who have been awarded a contract through the prequalification process are eligible to submit a proposal for these services. All terms, conditions, and specifications agreed upon during the RFQ process remain in effect for this project.
DS Timeline
| Event |
| Time |
| Date |
DS issue date
| Monday, October 26, 2026 |
| Pre-Bid Meeting |
| 12:00 noon Eastern |
| Tuesday, November 10, 2026 |
| Deadline for bidders to submit questions about this DS |
| 3:00 p.m. Eastern |
| Friday, November 13, 2026 |
| Anticipated date the State will post answers to bidder questions on www.michigan.gov/SIGMAVSS |
| Tuesday, November 17, 2026 |
| Proposal deadline* |
| 3:00 p.m. Eastern |
| Tuesday, November 24, 2026 |
| Pre-construction meeting |
TBD
Anticipated project begin date
TBD
*A bidder’s proposal received at 3:00:01 p.m. Eastern is late and subject to disqualification.
This DS is subject to change. Check www.michigan.gov/SIGMAVSS for current information.
MANDATORY PRE-PROPOSAL MEETING
A pre-proposal meeting will be held on Tuesday, November 10, 2026, at 12:00 noon Eastern. Only those Contractors who attend the meeting will be able to submit a proposal. The meeting will be held at the Troyer 1-7A project site:
From Grand Rapids, take US-131 north to the second Big Rapids exit (19 Mile Road). Go east 1.5 miles and turn north on Northland Drive. Go 3 miles north and turn west on 22 Mile Road. Go 3 miles west to Newcosta Avenue and turn north into the meeting location.
The purpose of the pre-proposal meeting will be to inspect the site and discuss the work to be performed. Statements made by the Solicitation Manager or designee at a pre-proposal meeting are not considered modifications to the RFQ. If, however, the Solicitation Manager determines modifications to the RFP are warranted after the meeting, modifications will be posted in writing on www.michigan.gov/SIGMAVSS as explained in the Modifications section of this document.
The meeting will start promptly at 12:00 noon Eastern.
MODIFICATIONS
The State may modify this RFQ at any time. Modifications will be posted on www.michigan.gov/SIGMAVSS. This is the only method by which the RFQ may be modified.
QUESTIONS
Bidder questions about this RFQ must be emailed to the Solicitation Manager or posted on www.michigan.gov/SIGMAVSS no later than the time and date specified on the Cover Page. In the interest of transparency, only written questions are accepted. Answers to questions will be posted on www.michigan.gov/SIGMAVSS. Submit questions using the format below; a Microsoft Excel format or similar is suggested.
| Q # |
| Document and Section |
| Page # |
| Bidder Question |
DELIVERY OF PROPOSAL
Electronic – The bidder must submit its proposal, all attachments, and any modifications or withdrawals electronically through www.michigan.gov/SIGMAVSS. The bidder should submit all documents in a modifiable (native) format (examples include but are not limited to Microsoft Word or Excel and Google Docs or Sheets). In addition to submitting documents in a modifiable format, the bidder may also submit copies of documents in PDF. Attachment file size is limited to 6 MB per document. Bidder’s failure to submit a proposal as required may result in disqualification. The proposal and attachments must be fully uploaded and submitted prior to the proposal deadline. Do not wait until the last minute to submit a proposal, as the SIGMA VSS system requires the entry of certain information, in addition to uploading and submitting the materials. The SIGMA VSS system will not allow a proposal to be submitted after the proposal deadline identified in the solicitation Closing On/Closing Date fields (Summary view/Detail view), even if a portion of the proposal has been uploaded.
Questions on how to submit information or how to navigate in the SIGMA VSS system can be answered by calling (517) 284-0540 or (888) 734-9749. The Solicitation Manager will not provide assistance related to the submittal of the proposal and all attachments on the day of the proposal deadline. Responsibility for a complete submission lies with the bidder.
EVALUATION PROCESS
If all mandatory minimum requirements are met, the State will evaluate each proposal based on the following factors:
| Technical Evaluation Criteria |
| Weight |
| 1. |
| Key Personnel – (adequate personnel available to perform the work requested) |
| 25 |
| 2. |
| Business Owned Equipment List – (equipment adequate to perform the work requested) |
| 25 |
| 3. |
| Company’s Technical Experience and Ability – (experience/ability relative to the work requested) |
| 25 |
| 4. |
| Vendor Questions Worksheet (experience relative to the work requested) |
| 25 |
| Total |
| 100 |
Only those proposals receiving 80 or more technical evaluation points will be considered for award.
The State may utilize all bidder information, without regard to a proposal’s technical score, to determine fair market value for goods or services sought. The State is not obligated to accept the lowest price proposal. If applicable, the State’s evaluation will include consideration of a bidder’s qualified disabled veterans/service-disabled veteran owned business(QDV/SDVOB) status under MCL 18.1261(8). Additional information on the SDVOB preference is available at: Michigan.gov/SDVOB.
SCHEDULE A - STATEMENT OF WORK
Properly Plug and Abandon 2 Wells and Restore Locations in Newaygo & Mecosta Counties
| Well Name |
| Permit Number |
| Operator of Record |
| Comments |
| Troyer 1-7A |
| 60486 |
| Wellmaster Production |
| See attachment |
| Daniels 1-1B |
| 56879 |
| Wellmaster Production |
| See attachment |
Prior to mobilization, a pre-construction meeting will be conducted with the successful vendor to review and confirm items.
SCHEDULE B – PRICING MATRIX
Wellmaster - Newaygo & Mecosta Orphan Well Plugging Project (Newaygo and Mecosta Counties) – 2 Wells
SEE ATTACHED PRICING MATRIX FOR BID TABLE
BID AMOUNT (should be the same as Grand Total from Pricing Matrix)
Bidders should provide pricing for ALL items in the ‘Price per Unit’ column of the pricing matrix (even if not necessarily needed for this project). These ‘per unit’ prices are referred to as ‘rated items’ by EGLE staff in the event a change order or approved change to the scope of work is required to complete the project.
Should an award result from this DS, all rates quoted in response to this DS will be firm for the duration of the project. No price changes will be permitted.
Bidders must submit a project timeline in conjunction with their Schedule B - Pricing Matrix. The timeline must be broken down into a minimum of four categories as follows: Site Prep, Mobilization/Demobilization, Plugging, Site Restoration.
An example of a single well project timeline might look like this: 1 day to clear/grub the site, 1 day to mobilize to site, 1 day to rig up, 3 days to plug well and flush/abandon/remove flowline, 1 day to rig down, 2 days to restore site for a total of 9 days to plug the well and finish project.
An example of a multi-well and facility project might look like this: 3 days to clear/grub locations, 1 day to mobilize equipment to project area, 50 days to plug wells (includes time needed to mob between wells, and address flowlines), 15 days to decommission facilities, 5 days to restore sites, 1 day to demobilize equipment from project area for a total of 75 days to complete the project.
Also, please indicate if you are proposing to utilize multiple rigs simultaneously, rig availability, and describe why you believe your timeline is correct, and how many staff you anticipate utilizing on a daily basis (staff counts do not have to include sub-contracted services like cement/wireline, only staff that are directly employed by your company).
The state will review your estimated timeline, reasoning, staffing, and pricing to determine the winning bidder. The winning bidder will be the bidder that we determine provides the best value to the state.
The winning bidder and all of its subcontractors must adhere to Davis Bacon Prevailing Wages for this project. It is the responsibility of the winning bidder to ensure that its subcontractor’s pricing for this bid includes Davis Bacon Prevailing Wages.
Please make sure that when you obtain pricing for this bid. that you inform all subcontractors that they must adhere to Davis Bacon Prevailing Wages. The state will not approve a change order related to improper bidding due to the awarded contractor or its subcontractor failing to include Davis Bacon Prevailing Wage rates when calculating their bids.
Federal funds will be used on this project. The awarded Contractor must comply with the Davis-Bacon Act as agreed upon in the signed Contract (Master Agreement) within the Federal Provisions Addendum.
Davis-Bacon Act (Prevailing Wage) If this Contract is a prime construction contract in excess of $2,000, the Contractor (and its Subcontractors) must comply with the Davis-Bacon Act (40 USC 3141-3148) as supplemented by Department of Labor regulations (29 CFR Part 5, “Labor Standards Provisions Applicable to Contracts Covering Federally Financed and Assisted Construction”), and during performance of this Contract the Contractor agrees as follows:
1) All transactions regarding this contract shall be done in compliance with the Davis-Bacon Act (40 U.S.C. 3141- 3144, and 3146-3148) and the requirements of 29 C.F.R. pt. 5 as may be applicable. The contractor shall comply with 40 U.S.C. 3141-3144, and 3146-3148 and the requirements of 29 C.F.R. pt. 5 as applicable.
2) Contractors are required to pay wages to laborers and mechanics at a rate not less than the prevailing wages specified in a wage determination made by the Secretary of Labor.
3) Additionally, contractors are required to pay wages not less than once a week.
Print Name
Print Title
Signature
Date
WELLMASTER PRODUCTION PRE-BID LOCATION MAP
WELLMASTER PRODUCTION LOCATION MAP
WELLMASTER PRODUCTION LOCATION EXPANDED VIEWS
MISCELLANEOUS INFORMATION
Well Photo – Current Well Condition
Daniels 1-1B (56879) and the Troyer 1-7A (60486)