Drawings N Whitehill Drive Drainage Improvement - FULL SET_SIGNED_Part1.pdf
PDF 41 MB Posted
- Solicitation number
- 59659
- Issued by
- Petersburg City, Virginia
About this file
The document is a set of drawings for the North Whitehill Drive Drainage Improvements Project-Phase 1 in Petersburg City, Virginia. The work involves the installation of grassy swales. This project is being undertaken by the City of Petersburg.
The drawings provide detailed specifications and plans for the drainage improvement work, including the placement and dimensions of the grassy swales. No information is provided regarding response dates, due dates, site visits, bidder's meetings, award dates, or the term of the contract. Pricing terms, set asides, incumbents, funding requirements, and other salient details are also not included in the drawings.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAINAGE NOTES
1. ALL PIPE JOINTS ARE TO BE WATERTIGHT ACCORDING TO VDOT STANDARDS AND
SPECIFICATIONS.
2. ALL STORM SEWER PIPES INDICATED ON PLANS SHALL MEET THE STANDARDS LISTED
BELOW, UNLESS NOTED OTHERWISE:
2.1. PERFORATED PVC PIPES SHALL BE 6-INCH RIGID SCHEDULE 40 PVC WITH 3/8-INCH
PERFORATIONS.
2.2. SOLID WALL (NON-PERFORATED) PVC PIPES SHALL BE 6-INCH RIGID SCHEDULE 40
PVC.
3. IF DURING CONSTRUCTION THE EXISTING STORM SEWER OR DITCH INVERT ELEVATIONS
SHOWN ON THESE PLANS ARE FOUND TO DIFFER SIGNIFICANTLY FROM THE ELEVATIONS
IN THE FIELD, NOTIFY THE ENGINEER IMMEDIATELY FOR AN ADJUSTMENT IN
ELEVATIONS.
4. ALL PIPE LENGTHS SHOWN ON PLANS ARE MEASURED FROM CENTER OF CHAMBER TO
CENTER OF CHAMBER, UNLESS NOTED OTHERWISE.
5. TRENCH BOXES SHALL BE USED WHERE EXCAVATIONS EXCEED 5 FEET DEEP.
GENERAL CONSTRUCTION NOTES
1. UTILITY LOCATION SHOWN ON THESE PLANS IS FOR REFERENCE ONLY. PRIOR TO
CONSTRUCTION THE CONTRACTOR SHALL VERIFY THE LOCATION AND ELEVATION OF
ALL UNDERGROUND UTILITIES SHOWN ON THE PLANS IN AREAS OF CONSTRUCTION.
2. CONTRACTOR SHALL COORDINATE WITH THE LOCAL UTILITY COMPANIES PRIOR TO
CONSTRUCTING PORTIONS OF WORK IMMEDIATELY ADJACENT TO UTILITY STRUCTURES.
THE CONTRACTOR IS RESPONSIBLE FOR REPAIRING ANY UNDERGROUND LINES,
FACILITIES, AND STRUCTURES DAMAGED AS A RESULT OF CONSTRUCTION ACTIVITY.
THE COSTS OF POLE AND/OR OTHER STRUCTURE STABILIZATION DURING WORK SHALL
BE BORNE BY THE CONTRACTOR AND INCLUDED IN THE BID FOR THE PROJECT.
3. THE CONTRACTOR SHALL CALL "MISS UTILITY" AT 1-800-552-7001 A MINIMUM OF 72
HOURS PRIOR TO CONSTRUCTION. CONTRACTOR SHALL VERIFY LOCATION AND
ELEVATION OF ALL UNDERGROUND UTILITIES SHOWN ON PLANS IN AREAS OF
CONSTRUCTION PRIOR TO STARTING WORK. CONTACT THE ENGINEER IMMEDIATELY IF
LOCATION OR ELEVATION IS DIFFERENT FROM THAT SHOWN ON THE PLAN, IF THERE
APPEARS TO BE A CONFLICT, AND UPON DISCOVERY OF ANY UTILITY NOT SHOWN ON
PLAN.
4. ALL GRADING SHALL PROVIDE SURFACE DRAINAGE THAT PREVENTS STANDING WATER
AND PROVIDES POSITIVE DRAINAGE TO THE STORM DRAINAGE INLETS, DITCHES, OR
OTHER POINTS OF STORMWATER DISCHARGE. ALL DISTURBED AREAS SHALL MEET
EXISTING GRADING WITH SMOOTH TRANSITIONS.
5. THE CONTRACTOR SHALL PAY FOR AND OBTAIN ALL REQUIRED PERMITS AND DELIVER
COPIES TO THE OWNER AT THE PRE-CONSTRUCTION MEETING.
6. THE CONTRACTOR SHALL HAVE A COMPLETE SET OF CONTRACT DOCUMENTS,
APPROVALS AND PERMITS, ON THE JOB SITE AT ALL TIMES.
7. CONTRACTOR SHALL NOTIFY PROPERTY OWNERS IN WRITING OF ANY WORK
SCHEDULED ADJACENT TO OR THROUGH THEIR PROPERTY A MINIMUM OF ONE WEEK IN
ADVANCE PRIOR TO THE COMMENCEMENT OF ANY STAKING OR CONSTRUCTION
ACTIVITY.
8. HORIZONTAL DATUM: NAD 83
VERTICAL DATUM: NAVD 88
9. NO CONSTRUCTION, EXCAVATION, OR DEMOLITION SHALL BEGIN UNTIL INITIAL EROSION
& SEDIMENT CONTROL (ESC) MEASURES ARE INSTALLED & APPROVED. ALL EROSION
CONTROL MEASURES SHALL BE IN ACCORDANCE WITH THE LATEST VERSION OF THE
VIRGINIA EROSION AND SEDIMENT CONTROL HANDBOOK .
10. ALL CONSTRUCTION ACTIVITIES SHALL PROCEED ACCORDING TO THE LATEST OSHA
REGULATIONS.
11. THIS PROJECT SHALL BE CONSTRUCTED IN ACCORDANCE WITH VDOT ROAD AND BRIDGE
STANDARDS DATED 2020, ROAD AND BRIDGE SPECIFICATIONS DATED 2020, REVISED
JULY 2022, WORK AREA PROTECTION MANUAL DATED 2011 (REVISION 2.1: NOVEMBER 1,
2020) AND AS AMENDED BY CONTRACT PROVISIONS.
12. THE CONTRACTOR SHALL MAINTAIN SAFE VEHICULAR AND PEDESTRIAN ACCESS TO ALL
PROPERTIES THROUGHOUT CONSTRUCTION. THE CONTRACTOR SHALL BE RESPONSIBLE
FOR THE INSTALLATION AND MAINTENANCE OF ANY AND ALL SAFETY CONTROL DEVICES
IN ACCORDANCE WITH THE PROVIDED MAINTENANCE OF TRAFFIC PLAN AND AS DEEMED
NECESSARY BY THE CITY AND THE ENGINEER.
13. NO MUD OR CONSTRUCTION DEBRIS SHALL BE ALLOWED TO ACCUMULATE ON ANY
PAVED STREET WHICH IS MAINTAINED BY THE STATE, COUNTY, CITY, OR VDOT.
14. ANY REQUIRED LANE AND/OR ROAD CLOSURES MUST BE APPROVED IN ADVANCE BY THE
CITY ENGINEER. A TEMPORARY EMERGENCY VEHICLE ACCESS ROUTE SHALL BE
INSTALLED AND APPROVED PRIOR TO ANY ROAD CLOSURE OF A STREET.
15. THE CONTRACTOR SHALL FOLLOW THE MAINTENANCE OF TRAFFIC PLANS AND NOTES
PROVIDED WITH THESE CONSTRUCTION DOCUMENTS.
16. SOIL STOCKPILES SHALL NOT BE PERMITTED ON-SITE. CONTRACTOR TO ENSURE ALL
EXCESS MATERIAL AND WASTE IS REMOVED OFFSITE DAILY. CONTRACTOR IS
RESPONSIBLE FOR LOCATING AND GAINING ALL REQUIRED PERMISSIONS & PERMITS
FOR PLACEMENT OF STOCKPILE OFFSITE.
17. THE CONTRACTOR SHALL PROVIDE ADDITIONAL TRAFFIC CONTROL AS DIRECTED BY THE
CITY ENGINEER AND/OR VDOT.
18. AT NO TIME SHALL CONSTRUCTION TAKE PLACE ON BOTH THE RIGHT AND LEFT SIDES
OF VEHICLES UNLESS SPECIFIED BY THE CITY, VDOT OR THE ENGINEER.
19. DUE TO THE SURROUNDING RESIDENTIAL PROPERTIES, NIGHT WORK WILL ONLY BE
PERMITTED FOR SPECIAL SITUATIONS. CITY APPROVAL IS REQUIRED PRIOR TO NIGHT
TIME OPERATIONS. ANY CONDITIONS REQUIRED BY THE CITY FOR NIGHT TIME
OPERATIONS SHALL BE ADHERED TO BY THE CONTRACTOR.
20. MAILBOXES AND STREET SIGNS SHALL BE REPLACED IMMEDIATELY AFTER AREA IS
BACKFILLED AND NO LATER THAN THE CLOSE OF EACH WORK DAY, EVEN IF
REPLACEMENT IS ONLY TEMPORARY.
21. EXCESS EXCAVATION TO BE LEGALLY DISPOSED AT AN APPROVED DISPOSAL SITE.
BORROW MATERIAL SHALL BE OBTAINED FROM AN APPROPRIATELY PERMITTED SITE.
22. STAKING FOR CONSTRUCTION, TO ASSURE PROPER LOCATION OF PROJECT
COMPONENTS, SHALL BE PERFORMED BY A CERTIFIED LAND SURVEYOR IN THE
COMMONWEALTH OF VIRGINIA.
23. ALL EXISTING PROPERTY MARKERS ARE TO REMAIN UNDISTURBED. IF DISTURBANCE
OCCURS, REPLACEMENT MUST BE PERFORMED BY A CERTIFIED LAND SURVEYOR AT
THE CONTRACTOR'S EXPENSE
24. PREVIOUSLY ARRANGED ACCESS EASEMENTS, STAGING AREAS, STORAGE AREAS, ETC.,
IF ANY, ARE SHOWN ON THE DRAWINGS. ADDITIONAL LAND USE RIGHTS SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR.
25. WORK AREAS SHALL BE KEPT AT ALL TIMES FREE OF DEBRIS AND HAZARDOUS
MATERIAL TO THE SATISFACTION OF THE INSPECTOR.
26. THE CONTRACTOR SHALL COORDINATE STORAGE OF MATERIALS, PARKING OF
VEHICLES, AND RESTRICTIONS OF WORK WITH THE INSPECTOR.
27. ALL DRIVEWAYS, SIDEWALKS, STREET SIGNS, YARD LIGHTS, MAILBOXES, SIGNS, AND
FENCES SO SPECIFIED ARE TO BE PRESERVED OR RESTORED AT THE CONTRACTOR'S
EXPENSE TO ORIGINAL CONDITION OR BETTER PER PLAN SHEETS, OR AS DIRECTED BY
THE CITY OF PETERSBURG REPRESENTATIVE TO THE SATISFACTION OF THE CITY'S
REPRESENTATIVE.
28. ALL WORK SHALL BE SUBJECT TO INSPECTION BY STATE AND LOCAL INSPECTORS.
29. FINAL ACCEPTANCE BY THE OWNER AND STATE WILL NOT BE MADE UNTIL ALL WORK
SHOWN ON THE APPROVED CONTRACT DOCUMENTS IS COMPLETED, INCLUDING PAVING,
GRADING AND ALL ADJUSTMENTS.
30. THE CONTRACTOR SHALL MAINTAIN SAFE VEHICULAR AND PEDESTRIAN ACCESS TO ALL
PROPERTIES THROUGHOUT CONSTRUCTION. THE CONTRACTOR SHALL BE RESPONSIBLE
FOR THE INSTALLATION AND MAINTENANCE OF ANY AND ALL SAFETY CONTROL DEVICES
IN ACCORDANCE WITH THE PROVIDED MAINTENANCE OF TRAFFIC PLAN AND AS DEEMED
NECESSARY BY THE CITY AND THE ENGINEER.
31. THE CONTRACTOR IS RESPONSIBLE FOR PROVIDING FENCING AND/OR SIGNAGE AS
NECESSARY TO INFORM THE PUBLIC ABOUT AND TO PROTECT THE PUBLIC FROM
ACCESS TO THE CONSTRUCTION ACTIVITIES.
CONSTRUCTION SEQUENCE
1. CONSTRUCT PROJECT ACCORDING TO THE SEQUENCE OF CONSTRUCTION DESCRIBED
BELOW. THE CONTRACTOR SHALL NOT DEVIATE FROM THIS SEQUENCE UNLESS PRIOR
APPROVAL IS OBTAINED FROM THE CITY OF PETERSBURG DEPARTMENT OF PUBLIC
WORKS.
2. ACQUIRE ALL PERMITS PRIOR TO CONSTRUCTION. ALL FEES ASSOCIATED WITH PERMITS
SHALL BE PAID BY THE CONTRACTOR UNLESS OTHERWISE SPECIFIED.
3. VERIFY THE HORIZONTAL AND VERTICAL LOCATION OF ALL EXISTING UTILITIES PRIOR TO
THE START OF CONSTRUCTION.
4. AN ON-SITE PRE-CONSTRUCTION CONFERENCE SHALL BE HELD PRIOR TO ANY WORK
COMMENCING ON THE PROJECT. THE REQUEST TO SCHEDULE THE PRE-CONSTRUCTION
CONFERENCE SHALL BE MADE BY THE CONTRACTOR TO THE CITY A MINIMUM OF 48
HOURS PRIOR TO THE CONFERENCE DATE. A CERTIFIED RESPONSIBLE LAND DISTURBER
(CRLD) MUST BE PRESENT AT THE ON-SITE MEETING WITH THE CITY INSPECTOR.
5. THE CONTRACTOR SHALL DEVELOP A UTILITIES RELOCATION PLAN, AS NECESSARY.
SEQUENCE RELOCATION FOR THE MOST EFFICIENT CONSTRUCTION TO AVOID DELAYS.
NO ADDITIONAL COMPENSATION WILL BE ALLOWED FOR ANY DELAYS RESULTING FROM
THE CONTRACTOR'S FAILURE TO PROPERLY DETERMINE CONFLICTS WITH UTILITIES AND
ADJUSTING THE UTILITY IN ADVANCE OF THE WORK.
6. AFTER THE PRE-CONSTRUCTION MEETING, THE INITIAL EROSION AND SEDIMENT
CONTROL MEASURES (SAFETY FENCE, INLET PROTECTION) SHALL BE INSTALLED IN
ACCORDANCE WITH THE OVERALL EROSION AND SEDIMENT CONTROL PLAN (SEE SHEET
C3.2). LAND DISTURBANCE OUTSIDE THE PRELIMINARY LIMITS OF DISTURBANCE MAY
NOT OCCUR UNTIL THE INITIAL EROSION AND SEDIMENTATION CONTROL MEASURES
HAVE BEEN APPROVED BY THE CITY'S INSPECTOR.
7. PERFORM CONSTRUCTION SURVEY STAKEOUT FOR PROPOSED IMPROVEMENTS. ALL
SURVEYING OPERATIONS MUST BE PERFORMED BY A VIRGINIA LICENSED SURVEYOR.
8. VERIFY ALL TIE IN INVERTS PRIOR TO CONSTRUCTION AND NOTIFY THE ENGINEER
IMMEDIATELY SHOULD ANY INVERT ADJUSTMENTS BE REQUIRED.
9. CONSTRUCT GRASSED SWALE AS INDICATED ON THE PLANS.
10. THE CONTRACTOR SHALL SEED DISTURBED AREAS AS SPECIFIED FOR PERMANENT
STABILIZATION AT REGULAR INTERVALS AS CONSTRUCTION PROGRESSES. TEMPORARY
SEEDING SHALL BE USED IN DISTURBED AREAS THAT WILL REMAIN DORMANT FOR A
PERIOD OF TIME GREATER THAN 14 DAYS. THE CONTRACTOR IS TO WATER NEWLY
SEEDED AREAS DAILY TO ENSURE GERMINATION AND SUPPLY ADEQUATE MOISTURE
THEREAFTER UNTIL PROJECT HAS BEEN DEEMED COMPLETE BY THE CITY.
11. TEMPORARY EROSION CONTROL MEASURES SHALL BE MAINTAINED DURING
CONSTRUCTION ACCORDING TO THE LATEST VERSION OF THE VA EROSION AND
SEDIMENT CONTROL HANDBOOK.
11.1. IN GENERAL, ALL ESC MEASURES SHALL BE CHECKED DAILY AND AFTER EACH
RUNOFF PRODUCING EVENT.
11.2. ADDITIONAL ESC MEASURES SHALL BE INSTALLED AS REQUIRED OR DIRECTED BY
THE CITY OR ENGINEER. ALL PERMIT CONDITIONS SHALL BE MET.
12. EROSION CONTROL MEASURES SHALL BE REMOVED ONLY UPON APPROVAL FROM THE
CITY INSPECTOR.
13. ONCE ALL ESC MEASURES HAVE BEEN REMOVED AND THE SITE HAS BEEN RELEASED BY
THE CITY INSPECTOR, CONTRACTOR IS TO CONTACT THE ENGINEER TO COMPLETE THE
CITY'S SWM/BMP CERTIFICATION FORM. CONTRACTOR TO REMOVE ALL SEDIMENT OR
DEBRIS IN THE BMP PRIOR TO CERTIFICATION.
EXIST. STONE BASE
VARIABLE DEPENDING ON
EXTENT OF IMPACT
** 6" CRUSHER RUN
#26 AGGREGATE
AREA STONE REPLACEMENT DETAIL
GRAVEL DRIVE & GRAVEL PARKING
NO SCALE
EXIST. ROADWAY
W = VARIABLE WIDTH PER EXISTING CONDITIONS.
H = 3' PER SURVEYED FIELD CONDITIONS.
NOTE: CONTRACTOR TO REPLACE FENCE HEIGHT & GATE WIDTH IN KIND PER EXISTING CONDITIONS.
CONTRACTOR SHALL INSTALL HINGES SUCH THAT GATES OPEN INWARDLY TO PROPERTY, PER CITY OF
PETERSBURG CODE OF ORDINANCES SECTION 98-122.
REPLACEMENT DETAIL
CHAIN LINK FENCING & GATE
NO SCALE
LINE POST
CLASS A-3
CONCRETE
FOOTING
12"
3'
H
TOP RAIL
WIRE TIE
LINE POST CAP
TENSION
BAND
RAIL END
RAIL END BAND
GATE
FORK
LATCH
GATE POST CAP
GATE
POST
HOG RING TENSION WIRE
FASTENER (24" O.C.)
BOTTOM
TENSION
WIRE
TENSION
BAR
GATE POST
HINGE
GATE FRAME
HINGE
W
STEEL FABRIC
10' MAX
*FILTER FABRIC NOT SHOWN FOR CLARITY
OBSERVATION WELLS TO INCLUDE THE FOLLOWING:
1. ALL UNDERDRAIN AND CLEANOUT PIPING SHALL BE SCHEDULE 40 SMOOTH WALL PVC PIPE.
2. FOR AN UNDERGROUND FLUSH MOUNTED OBSERVATION WELL / CLEANOUT, PROVIDE A TUBE
MADE OF NON-CORROSIVE MATERIAL, SCHEDULE 40 OR EQUAL, WITH AN INSIDE DIAMETER OF AT
LEAST 6 INCHES.
3. THE TUBE SHALL HAVE A FACTORY ATTACHED CAST IRON OR HIGH IMPACT PLASTIC COLLAR
WITH RIBS TO PREVENT ROTATION WHEN REMOVING SCREW TOP LID. THE SCREW TOP LID
SHALL BE CAST IRON OR HIGH IMPACT PLASTIC THAT WILL WITHSTAND ULTRA-VIOLET RAYS.
4. THE DEPTH OF INVERT SHALL BE MARKED ON CAP.
5. ALL FITTINGS SHALL BE GASKETED.
6. FOR PERFORATED PIPE, A MINIMUM OF 4 ROWS OF PERFORATIONS SHALL BE PROVIDED AROUND
THE DIAMETER OF THE PIPE. PERFORATIONS SHALL BE PLACED 6-IN ON CENTER WITHIN EACH
ROW FOR THE ENTIRE LENGTH OF THE DRAINAGE LATERAL. PERFORATIONS SHALL BE 3/8-IN DIA.
VENTED PANELLA TYPE CLEANOUT WITH
COUNTERSUNK HEAD
SCREW TOP LID
FINISHED GRADE
DRY SWALE CLEANOUT DETAIL
NOT TO SCALE
DEPTH OF INVERT
MARKED ON TOP LID
45-DEGREE WYE
SOLID WALL, 6"X'6"X6"
FILTER MEDIA
SECTION
12"
MIN
45-DEGREE
ELBOW
(SOLID WALL)
CHOKING STONE
(#8 OR #89,
WASHED)
STONE LAYER
(#57, WASHED)
PERFORATED U/D
PVC PIPE
6" PVC CAP
PVC CLEANOUT
RISER
SOLID WALL PIPE
THROUGH MEDIA
** METHOD OF PAYMENT FOR STONE SHALL BE AS #26 CRUSHER RUN, AS SPECIFIED
JOB NO.
SHEET NO.
SCALE
DESIGNED BY
CHECKED BY
D A T E
DRAWN BY
DATE
R E V I S I O
N D
E S C R I P T I O
N
T h e s e p la n s a n d a s s o c ia te d d o c u m e n ts a re t h e e x c lu s iv e p ro p e rt y o f T
IM
M
O N
S G
R O
U P a n d m a y n o t b e r e p ro d u c e d i n w h o le o r in p a rt a n d s h a ll n o t b e u s e d f o r a n y p u rp o s e w h a ts o e v e r, i n c lu s iv e b u t n o t lim it e d t o c o n s tr u c ti o n b id d in g a n d /o r c o n s tr u c ti o n s ta k in g w it h o u t th e e x p re s s w ri tt e n c o n s e n t o f
T
IM
M O
N S
G R
O U
P
04/28/2023
N W
H I T E H
I L L D
R I V E D
R A I N
A G
E I
M P R O
V E M
E N
T C I T Y O
F P
E T E R S B U
R G
V
I R G
I N
I A
51547
L
\5
-W h it e h ill
D r\
D W
G \S w a le
P h a s e \S h e e t\
C D
\5 C
-1 .0
-N T
D T
.d w g P lo tt e d o n
/8 /2
:5 P
M b y K e ls e y R e d m a n
C1.0
C O
N S T R U
C T I O
N N
O T E S
K. REDMAN
S. REEVES
M. CLAUD
AS SHOWN
VDOT ROAD AND BRIDGE STANDARD DETAILS
NYLOPLAST (OR APPROVED EQUAL) DETAILS
*OR APPROVED EQUAL
*OR APPROVED EQUAL
*OR APPROVED EQUAL
*OR APPROVED EQUAL
HDPE TO MANHOLE ADAPTER DETAIL
*OR APPROVED EQUAL
*OR APPROVED EQUAL
*OR APPROVED EQUAL
6" SUMP
DEPTH
36"
STR. U7
36"
36"
10"
6" NO. 26 CRA
BEDDING
NO.
6 REBAR
JOB NO.
SHEET NO.
SCALE
DESIGNED BY
CHECKED BY
D A T E
DRAWN BY
DATE
R E V I S I O
N D
E S C R I P T I O
N
T h e s e p la n s a n d a s s o c ia te d d o c u m e n ts a re t h e e x c lu s iv e p ro p e rt y o f T
IM
M
O N
S G
R O
U P a n d m a y n o t b e r e p ro d u c e d i n w h o le o r in p a rt a n d s h a ll n o t b e u s e d f o r a n y p u rp o s e w h a ts o e v e r, i n c lu s iv e b u t n o t lim it e d t o c o n s tr u c ti o n b id d in g a n d /o r c o n s tr u c ti o n s ta k in g w it h o u t th e e x p re s s w ri tt e n c o n s e n t o f
T
IM
M O
N S
G R
O U
P
04/28/2023
N W
H I T E H
I L L D
R I V E D
R A I N
A G
E I
M P R O
V E M
E N
T C I T Y O
F P
E T E R S B U
R G
V
I R G
I N
I A
51547
L
\5
-W h it e h ill
D r\
D W
G \S w a le
P h a s e \S h e e t\
C D
\5 C
-1 .0
-N T
D T
.d w g P lo tt e d o n
/8 /2
:5 P
M b y K e ls e y R e d m a n
C1.1
C O
N S T R U
C T I O
N D
E T A I L S
K. REDMAN
S. REEVES
M.CLAUD
NO SCALE
S A N
S A N
S A N
S A N
S A N
S A N
S A N
S A N
" R
C P
12" RCP
W W
W W
W W
W W
W W
W W
W W
W
W W
W W
W W
W W
W W
W
WWWWW
S A N
S A N
S A N
S A N
S A N
S A N
S A N
S A N
S A N
S A N
S A N
S A N
S A N
S A N
S A N
S A N
X
X
X
X
OHU
OHU
O H U
OHU
OHU
OHU
OHU
O H U
X
OHU
G
X
X
OHU OHU OHU OHU
O H U
O H U
O H U
O H U
O H U
OHU
O H U
OHU
OHU
X
X
X X
OHU
OHU
O H U
OHU
X
O H U
O H U
O H U
O H U
OHU
OHU
G G
G G
G
W W
W W
WWWW
W W
W
G G
G
LIMITS OF DETAILED SURVEY
JOB NO.
SHEET NO.
SCALE
DESIGNED BY
CHECKED BY
D A T E
DRAWN BY
DATE
R E V I S I O
N D
E S C R I P T I O
N
T h e s e p la n s a n d a s s o c ia te d d o c u m e n ts a re t h e e x c lu s iv e p ro p e rt y o f T
IM
M
O N
S G
R O
U P a n d m a y n o t b e r e p ro d u c e d i n w h o le o r in p a rt a n d s h a ll n o t b e u s e d f o r a n y p u rp o s e w h a ts o e v e r, i n c lu s iv e b u t n o t lim it e d t o c o n s tr u c ti o n b id d in g a n d /o r c o n s tr u c ti o n s ta k in g w it h o u t th e e x p re s s w ri tt e n c o n s e n t o f
T
IM
M O
N S
G R
O U
P
04/28/2023
N W
H I T E H
I L L D
R I V E D
R A I N
A G
E I
M P R O
V E M
E N
T C I T Y O
F P
E T E R S B U
R G
V
I R G
I N
I A
51547
L
\5
-W h it e h ill
D r\
D W
G \S w a le
P h a s e \S h e e t\
C D
\5 C
-2 .0
-K E
Y P
.d w g P lo tt e d o n
/8 /2
:0 P
M b y K e ls e y R e d m a n
C2.0
K E Y P
L A N
K. REDMAN
S. REEVES
M. CLAUD
AS SHOWN
NAD 83
SCALE 1"=20'
40'20'
SHEETS C2.1, C3.2, C4.0
NOTE:
PLANIMETRIC DATA SHOWN ON THIS SHEET, INCLUDING PARCELS, BUILDING FOOTPRINTS, RIGHT OF WAY, ETC, TAKEN FROM CITY OF PETERSBURG GIS DATA AND SHALL BE CONSIDERED APPROXIMATE.
TOPOGRAPHY SHOWN IS A COMPOSITE SURFACE DEVELOPED FROM 2014 VGIN LIDAR AND SURVEY DATA
S A N
S A N
S A N
S A N
S A N
S A N
S A N
S A N
S A N
S A N
S A N
X
X X
X
XX
XXX
XX XX
O H U
OHU
OHU
OHU
OHU
OHU
O H U
O H U
OHU
OHU
XXX
XX
OHU OHU OHU OHU OHU OHU OHU
X
X
X X
X
X X
X X
X
OHU
OHU
OHU
OHU
OHU
OHU
O H U
O H U
O H U
OHU
X
OHU
O H U
O H U
O H U
T
O P
O G
R A
P H
IC
S
U R
V E
Y
2021 TOPOGRAPHIC
SURVEY
T
O P
O G
R A
P H
IC
S U
R V
E Y
T
O P
O G
R A
P H
IC
L
ID
A
R D
A T
A A
N D
G
IS
M A
P P
IN
G
2014 TOPOGRAPHIC LIDAR
DATA AND GIS MAPPING
T
O P
O G
R A
P H
IC
L
ID
A
R
D A
T A
A N
D G
IS
M
A P
P
IN
G
W W
W W
G G
G G
W W
W
W
WWWWWW
W
W W
W W
UGT
G G
G G
G
CAUTION:
OVERHEAD POWER
SEE UTILITY NOTE
REMOVE
24" TREE
SEE DEMOLITION
NOTE 1
CAUTION:
OVERHEAD POWER
SEE UTILITY NOTE
REMOVE 106 LF
OF 3' CHAIN LINK
FENCING & GATES
REMOVE 119 LF
OF 3' CHAIN LINK
FENCING
REMOVE GATE B
SEE NOTE 2
REMOVE GATE A
SEE NOTE 2
REMOVE GATE C
SEE NOTE 2
REMOVE GATE D
SEE NOTE 2
REMOVE &
STORE EX.
NEIGHBORHOOD
WATCH SIGN
UNDERGROUND UTILITY NOTES
1. SUE WORK COMPLETED BY TIMMONS GROUP IN MARCH OF 2022.
2. THERE ARE ABANDONED UNDERGROUND UTILITY LINES IN PROJECT LIMITS.
3. THERE MAY BE UNDERGROUND UTILITIES THAT ARE NON-CONDUCTIVE INSIDE THE PROJECT LIMITS.
4. ALL SIZES AND TYPES OF UNDERGROUND UTILITY LINES ARE TAKEN FROM REFERENCE MAPPING.
5. ALL UNDERGROUND UTILITIES LOCATED DEPICTED AS QLB UNLESS OTHERWISE NOTED.
UTILITY OWNERS:
- CITY OF PETERSBURG WATERLINE
- VERIZON TELEPHONE
- COLUMBIA GAS OF VIRGINIA NATURAL GAS
TOPOGRAPHICAL SURVEY NOTES:
1. TOPOGRAPHICAL SURVEY PREPARED BY TIMMONS GROUP UNDER THE DIRECT AND RESPONSIBLE CHARGE OF, GREG McGLOTHIN, L.S FROM AN ACTUAL GROUND SURVEY MADE 01-21-2022, 01-24-2022, AND 01-28-2022. THE MERIDIAN SOURCE OF THIS TOPOGRAPHIC
SURVEY IS BASED ON (VIRGINIA STATE PLANE COORDINATES, SOUTH ZONE, HORIZONTAL) NAD 83. ELEVATIONS ARE BASED ON NAVD 88.
DATUM ESTABLISHED BY RTK RTCM-REF 0568.
2. MAPPING (BUILDING FOOTPRINTS, SIDEWALK FOOTPRINTS, PARCEL LINES) LOCATED OUTSIDE OF THE LIMITS OF TOPOGRAPHIC
SURVEY IS TAKEN FROM CITY OF PETERSBURG GIS DATA AND SHALL BE CONSIDERED APPROXIMATE.
DEMOLITION NOTES
1. CONTRACTOR SHALL COORDINATE WITH DOMINION POWER TO ESTABLISH AN OVERHEAD UTILITY PROTECTION PLAN. CONTRACTOR SHALL
FOLLOW ALL REQUIREMENTS SET FORTH BY DOMINION POWER FOR UTILITY PROTECTION.
2. GATE PANEL HEIGHTS AND WIDTHS PER SURVEYED CONDITIONS AS SPECIFIED BELOW:
A. SINGLE PANEL, 3' HEIGHT x 3' WIDTH
B. TWO PANELS, 3' HEIGHT x 5.5' WIDTH EACH
C. SINGLE PANEL, 3' HEIGHT x 5' WIDTH
D. SINGLE PANEL, 3' HEIGHT x 3' WIDTH
E. SINGLE PANEL, 3' HEIGHT X 3' WIDTH
*SURVEYED INVERT ELEVATIONS
WERE ADJUSTED IN THE
HYDRAULIC MODELS TO
ESTABLISH POSITIVE DRAINAGE
THROUGH THE STORM SEWER
SYSTEM.
*41.20'
*41.25'
X
DEMOLITION LEGEND
REMOVE PIPE
REMOVE EX. CHAIN
LINK FENCE
JOB NO.
SHEET NO.
SCALE
DESIGNED BY
CHECKED BY
D A T E
DRAWN BY
DATE
R E V I S I O
N D
E S C R I P T I O
N
T h e s e p la n s a n d a s s o c ia te d d o c u m e n ts a re t h e e x c lu s iv e p ro p e rt y o f T
IM
M
O N
S G
R O
U P a n d m a y n o t b e r e p ro d u c e d i n w h o le o r in p a rt a n d s h a ll n o t b e u s e d f o r a n y p u rp o s e w h a ts o e v e r, i n c lu s iv e b u t n o t lim it e d t o c o n s tr u c ti o n b id d in g a n d /o r c o n s tr u c ti o n s ta k in g w it h o u t th e e x p re s s w ri tt e n c o n s e n t o f
T
IM
M O
N S
G R
O U
P
04/28/2023
N W
H I T E H
I L L D
R I V E D
R A I N
A G
E I
M P R O
V E M
E N
T C I T Y O
F P
E T E R S B U
R G
V
I R G
I N
I A
51547
L
\5
-W h it e h ill
D r\
D W
G \S w a le
P h a s e \S h e e t\
C D
\5 C
-2 .0
-E X
S T
.d w g P lo tt e d o n
/8 /2
:0 P
M b y K e ls e y R e d m a n
C2.1
E X I S T I N
G C
O N
D I T I O
N S
D E M
O L I T I O
N P
L A N
K. REDMAN
S. REEVES
M. CLAUD
AS SHOWN
NAD 83
SCALE 1"=20'
40'20'
EROSION CONTROL NARRATIVE
PROJECT DESCRIPTION
THIS PROJECT IS LOCATED IN THE LAKEMONT NEIGHBORHOOD IN THE CITY OF PETERSBURG AND
EXTENDS ALONG NASH STREET. THE PURPOSE OF THIS PROJECT IS TO PROVIDE WATER QUALITY
TREATMENT WITH THE CONSTRUCTION OF A DRY SWALE RETROFIT ALONG NASH ST. PROJECT EXTENTS
TERMINATE AT SOUTH WHITEHILL AVE, EAST OF THE INTERSECTION OF NASH STREET, WHERE THE
PROPOSED SWALE WILL TIE BACK IN TO THE EXISTING STORM SEWER. THE TOTAL DISTURBED AREA
WITHIN THIS PROJECT IS 0.09 AC.
EXISTING SITE CONDITIONS
THE PROJECT SITE IS LOCATED WITHIN THE CITY OF PETERSBURG RIGHT-OF-WAY. LAND COVER WITHIN
THE SITE CONSISTS OF ASPHALT PAVEMENT, MANAGED GRASS AREAS, AND DRIVEWAY CONNECTIONS TO
THE ROADWAY. EXISTING TOPOGRAPHY WITHIN THE SITE IS CHARACTERIZED WITH FLAT SLOPES AND
WITH LONGITUDINAL SLOPES OF LESS THAN 0.5%. DRAINAGE FROM THE ROADWAY IS COLLECTED WITHIN
A STORM DRAIN SYSTEM AND WITHIN ROADSIDE SWALES.
ADJACENT AREAS
TEMPORARY CONSTRUCTION EASEMENT WILL BE REQUIRED ON PARCEL IDs 004290011 AND 004290001.
THE SURROUNDING PROPERTY FOR THE PROJECT IS RESIDENTIAL LAND, RESIDENTIAL STRUCTURES, AND
ROADS.
OFF-SITE AREAS
ANY OFF-SITE LAND-DISTURBING ACTIVITY ASSOCIATED WITH THE PROJECT MUST HAVE AN APPROVED
ESC PLAN. CONTRACTOR SHALL PROVIDE DOCUMENTATION OF THE APPROVED ESC PLAN FOR EACH
OFF-SITE LAND-DISTURBING ACTIVITY.
SOILS
ALL SOILS WITHIN THE PROJECT SITE AND CONTRIBUTING DRAINAGE AREA ARE CLASSIFIED AS FOLLOWS:
MAP UNIT: 7B
EMPORIA-URBAN LAND COMPLEX, 0 TO 6 PERCENT SLOPES, HYDROLOGIC SOIL GROUP C. EMPORIA SOILS
HAVE A USDA TEXTURE OF SANDY LOAM, ARE WELL DRAINED, PERMEABILITY IS MODERATELY SLOW TO
SLOW, AND SURFACE RUNOFF INDEX IS MEDIUM TO HIGH.
MAP UNIT: 20
UDORTHENTS, 0 TO 25 PERCENT SLOPES. HYDROLOGIC SOIL GROUP C. UDORTHENT SOILS ARE
MODERATELY WELL DRAINED. SHRINK SWELL POTENTIAL IS LOW. THIS SOIL IS NOT FLOODED. IT IS NOT
PONDED. THERE IS NO ZONE OF WATER SATURATION WITHIN A DEPTH OF 72 INCHES.
CRITICAL AREAS
THERE ARE NO IDENTIFIED ONSITE CRITICAL AREAS. HOWEVER, THE ULTIMATE OUTFALL FOR THE
STORMWATER CONVEYANCE SYSTEM IS HARRISON CREEK (IMPAIRED WATERWAY), EAST OF THE PROJECT
SITE. THERE ARE ALSO DELINEATED WETLAND AREAS SOUTH OF THE NEIGHBORHOOD. PROJECT IS
LOCATED WITHIN REGULATED CHESAPEAKE BAY PRESERVATION AREA (REGULATED URBAN AREA).
MAINTENANCE OF EROSION AND SEDIMENT CONTROL MEASURES IS CRITICAL FOR PREVENTING THE
DISCHARGE OF SEDIMENT TO THESE AREAS.
EROSION AND SEDIMENT CONTROL MEASURES
UNLESS OTHERWISE INDICATED, ALL VEGETATIVE AND STRUCTURAL EROSION AND SEDIMENT CONTROL
PRACTICES SHALL BE CONSTRUCTED AND MAINTAINED ACCORDING TO MINIMUM STANDARDS AND
SPECIFICATIONS OF THE VIRGINIA EROSION AND SEDIMENT CONTROL HANDBOOK (VESCH). THE MINIMUM
STANDARDS OF THE VESCH SHALL BE ADHERED TO UNLESS OTHERWISE WAIVED OR APPROVED BY A
VARIANCE BY LOCAL AUTHORITIES HAVING JURISDICTION.
1. SAFETY FENCE - 3.01
A PROTECTIVE BARRIER INSTALLED TO PREVENT ACCESS TO AN EROSION CONTROL MEASURE,
USED TO PROHIBIT UNDESIRABLE USE OF AN EROSION CONTROL MEASURE BY THE PUBLIC.
2. STORM DRAIN INLET PROTECTION - 3.07
THE INSTALLATION OF VARIOUS KINDS OF SEDIMENT TRAPPING MEASURES AROUND CURB
INLET STRUCTURES PRIOR TO PERMANENT STABILIZATION OF THE DISTURBED AREA; LIMITED
TO DRAINAGE AREAS NOT EXCEEDING ONE ACRE, AND NOT INTENDED TO CONTROL LARGE,
CONCENTRATED STORMWATER FLOWS.
3. TEMPORARY SEEDING - 3.31
TEMPORARY SEEDING SHALL BE USED ON ALL DISTURBED AREAS THAT WILL NOT BE BROUGHT
TO FINAL GRADE FOR MORE THAN 14 DAYS. TEMPORARY SEEDING SHALL ALSO BE USED ON ALL
CUT AND FILL SLOPES TO REMAIN EARTHEN. TEMPORARY SEEDING SHALL BE MAINTAINED UNTIL
PERMANENT SEEDING AND PERMANENT STABILIZATION IS ACHIEVED.
4. PERMANENT SEEDING - 3.32
PERMANENT SEEDING SHALL BE USED ON ALL CUT AND FILL SLOPES TO REMAIN EARTHEN TO
REDUCE EROSION AND DECREASE SEDIMENT YIELD FROM DISTURBED AREAS. PERMANENT
SEEDING WILL BE USED ON DISTURBED AREAS WHERE PERMANENT, LONG-LIVED VEGETATIVE
COVER IS NEEDED TO STABILIZE THE SOIL.
5. MULCHING - 3.35
APPLICATION OF PLANT RESIDUES OR OTHER SUITABLE MATERIALS TO THE SOIL SURFACE TO
PREVENT EROSION FROM RAINDROP IMPACT, AND TO FOSTER THE GROWTH OF VEGETATION BY
INCREASING AVAILBLE MOISTURE AND PROVIDING INSULATION AGAINST EXTREME HEAT AND
COLD.
6. SOIL STABILIZATION BLANKETS & MATTING - 3.36
INSTALLATION OF A PROTECTIVE COVERING (BLANKET) OR SOIL STABILIZATION MAT ON A
PREPARED PLANTING AREA OF A STEEP SLOPE, CHANNEL, OR SHORELINE TO AID IN EROSION
CONTROL ON CRITICAL AREAS. USE IN AREASE WHERE EROSION HAZARD IS HIGH OR IN
VEGETATED CHANNELS WHERE DESIGN VELOCITY EXCEEDS ALLOWABLE VELOCITY.
PERMANENT STABILIZATION
EXISTING LAND COVER IS PRIMARILY GRASSED RIGHT-OF-WAY, AS WELL AS GRAVEL AND ASPHALT. REFER
TO THE EROSION AND SEDIMENT CONTROL PLAN SHEET (SHEET 3.1) FOR MORE DETAILS.
ESC CONTROL MEASURE MAINTENANCE (REFER TO "MINIMUM STANDARDS"
FOR ADD. INFORMATION).
ALL ESC MEASURES SHALL BE MAINTAINED UNTIL PERMANENT STABILIZATION IS ACHIEVED IN
ACCORDANCE WITH THE CITY OF PETERSBURG ENVIRONMENTAL INSPECTOR.
1. SAFETY FENCE - 3.01:
1.1. SAFETY FENCE SHALL BE CHECKED REGULARLY FOR WEATHER-RELATED OR OTHER
DAMAGE. ANY NECESSARY REPAIRS MUST BE MADE IMMEDIATELY.
1.2. CARE SHOULD BE TAKEN TO SECURE ALL ACCESS POINTS AT THE END OF EACH WORKING
DAY. ALL LOCKING DEVICES MUST BE REPAIRED OR REPLACED AS NECESSARY.
2. STORM DRAIN INLET PROTECTION - 3.07: INLET PROTECTION MUST BE INSTALLED AT ALL INLETS
WITHIN THE PROJECT AREA AS NOTED ON THE PLANS.
2.1. THE STRUCTURE SHALL BE INSPECTED AFTER EACH RAIN AND REPAIRS MADE AS NEEDED.
2.2. SEDIMENT SHALL BE REMOVED AND THE TRAP RESTORED TO ITS ORIGINAL DIMENSIONS
WHEN THE SEDIMENT HAS ACCUMULATED TO ONE-HALF THE DESIGN DEPTH OF THE TRAP.
REMOVED SEDIMENT SHALL BE DEPOSITED IN A SUITABLE AREA AND IN SUCH A MANNER
THAT IT WILL NOT ERODE.
2.3. STRUCTURES SHALL BE REMOVED AND THE AREA STABILIZED WHEN THE REMAINING
DRAINAGE AREA HAS BEEN PROPERLY STABILIZED.
3. TEMPORARY SEEDING - 3.31
3.1. AREAS WHICH FAIL TO ESTABLISH VEGETATIVE COVER ADEQUATE TO PREVENT RILL
EROSION WILL BE RESEEDED AS SOON AS SUCH AREAS ARE IDENTIFIED.
4. PERMANENT SEEDING - 3.32
4.1. WHEN IT IS CLEAR THAT PLANTS HAVE NOT GERMINATED ON AN AREAS OR HAVE DIED,
THESE AREAS MUST BE RESEEDED IMMEDIATELY TO PREVENT EROSION DAMAGE.
5. MULCHING - 3.35
5.1. INSPECT PERIODICALLY AND AFTER RAINSTORMS TO CHECK FOR EROSION. WHERE
EROSION IS OBSERVED IN MULCHED AREAS, ADDITIONAL MULCH SHOULD BE APPLIED. IF
WASHOUTS OR BREAKAGE OCCUR OF NETS AND MATS, RE-INSTALL NETTING OR MATTING
AS NECESSARY AFTER REPAIRING DAMAGE TO THE SLOPE OR DITCH.
6. SOIL STABILIZATION BLANKETS & MATTING - 3.36
6.1. ALL SOIL STABILIZATION BLANKETS AND MATTING SHOULD BE INSPECTED PERIODICALLY
FOLLOWING INSTALLATION, PARTICULARLY AFTER RAINSTORMS TO CHECK FOR EROSION
AND UNDERMINING. ANY DISLOCATION OR FAILURE SHOULD BE REPAIRED IMMEDIATELY. IF
WASHOUTS OR BREAKAGE OCCURS, REINSTALL THE MATERIAL AFTER REPAIRING DAMAGE
TO THE SLOPE OR DITCH.
ESC CALCULATIONS
SEE SHEET C4.0 FOR DRY SWALE CHANNEL VELOCITIES.
STORMWATER MANAGEMENT CONSIDERATIONS
THE PROJECT WILL NOT INCREASE PEAK RUNOFF RATES. THE PROJECT INCLUDES DRY SWALE
CONSTRUCTION. THE PURPOSE OF THE DRY SWALE IS TO PROVIDE WATER QUALITY IMPROVEMENT AND
TO PROMOTE INFILTRATION. THIS PROJECT MEETS CONDITIONS OUTLINED IN 9VAC25-870-76 AND VA DEQ
GUIDANCE MEMO NO. 15-2003 AND IS THEREFORE NOT SUBJECT TO VSMP REGULATIONS.
EROSION & SEDIMENT CONTROL MINIMUM STANDARDS
MS-1: APPLY PERMANENT SOIL STABILIZATION TO DENUDED AREAS WITHIN SEVEN DAYS AFTER FINAL
GRADE IS REACHED ON ANY PORTION OF THE SITE. APPLY TEMPORARY SOIL STABILIZATION WITHIN
SEVEN DAYS TO DENUDED AREAS THAT MAY NOT BE AT FINAL GRADE BUT WILL REMAIN DORMANT
(UNDISTURBED) FOR LONGER THAN 14 DAYS. APPLY PERMANENT STABILIZATION TO AREAS THAT
ARE TO BE LEFT DORMANT FOR MORE THAN ONE YEAR.
MS-2: STABILIZE OR PROTECT TEMPORARY SOIL STOCKPILES WITH SEDIMENT TRAPPING MEASURES.
PROVIDE TEMPORARY PROTECTION AND PERMANENT STABILIZATION OF ALL SOIL STOCKPILES ON
SITE AS WELL AS SOIL TRANSPORTED FROM THE PROJECT SITE.
MS-3: ESTABLISH A PERMANENT VEGETATIVE COVER ON DENUDED AREAS NOT OTHERWISE
PERMANENTLY STABILIZED. PERMANENT VEGETATION SHALL NOT BE CONSIDERED ESTABLISHED
UNTIL A GROUND COVER IS ACHIEVED THAT IN THE OPINION OF THE ARCHITECT/ENGINEER, IS
UNIFORM, MATURE ENOUGH TO SURVIVE AND WILL INHIBIT EROSION.
MS-4: CONSTRUCT SEDIMENT BASINS AND TRAPS, PERIMETER DIKES, SEDIMENT BARRIERS AND OTHER
MEASURES INTENDED TO TRAP SEDIMENT AS A FIRST STEP IN ANY LAND-DISTURBING ACTIVITY AND
MAKE THESE MEASURES FUNCTIONAL BEFORE UP-SLOPE LAND DISTURBANCE OR TIMBERING TAKES
PLACE.
MS-5: APPLY STABILIZATION MEASURES TO EARTHEN STRUCTURES SUCH AS DAMS, DIKES AND
DIVERSIONS IMMEDIATELY AFTER INSTALLATION.
MS-6 DESIGN AND CONSTRUCT SEDIMENT TRAPS AND SEDIMENT BASINS BASED UPON THE TOTAL
DRAINAGE AREA TO BE SERVED BY THE TRAP OR BASIN.
a. DESIGN THE MINIMUM STORAGE CAPACITY OF THE SEDIMENT TRAP TO BE 134 CUBIC YARDS PER
ACRE OF DRAINAGE AREA AND THE MAXIMUM DRAINAGE AREA TO THE TRAP BE LESS THAN
THREE ACRES.
b. DESIGN THE SEDIMENT BASIN TO CONTROL SURFACE RUNOFF FROM DISTURBED AREAS
COMPRISED OF FLOW FROM DRAINAGE AREAS GREATER THAN OR EQUAL TO THREE ACRES.
ENSURE THE MINIMUM STORAGE CAPACITY OF THE SEDIMENT BASIN TO BE 134 CUBIC YARDS
PER ACRE OF DRAINAGE AREA. CONSTRUCT THE OUTFALL SYSTEM TO, AT MINIMUM, MAINTAIN
THE STRUCTURAL INTEGRITY OF THE BASIN DURING A 25-YEAR STORM OF 24-HOUR DURATION.
WHEN COMPLETING RUNOFF CALCULATIONS, APPLY RUNOFF COEFFICIENTS THAT
CORRESPOND TO A BARE EARTH CONDITION OR THOSE CONDITIONS EXPECTED TO EXIST WHILE
THE SEDIMENT BASIN IS UTILIZED.
MS-7: CONSTRUCT CUT AND FILL SLOPES IN A MANNER THAT WILL MINIMIZE EROSION. PROVIDE SLOPES
THAT ARE FOUND TO BE ERODING EXCESSIVELY WITHIN ONE YEAR OF PERMANENT STABILIZATION
WITH ADDITIONAL SLOPE STABILIZING MEASURES UNTIL THE PROBLEM IS CORRECTED.
MS-8: CONCENTRATED RUNOFF SHALL NOT FLOW DOWN CUT OR FILL SLOPES UNLESS CONTAINED WITHIN
AN ADEQUATE TEMPORARY OR PERMANENT CHANNEL, FLUME OR SLOPE DRAIN STRUCTURE.
MS-9: WHENEVER WATER SEEPS FROM A SLOPE FACE, PROVIDE ADEQUATE DRAINAGE OR OTHER
PROTECTION.
MS-10: PROTECT ALL STORM SEWER INLETS THAT ARE MADE OPERABLE DURING CONSTRUCTION SO THAT
SEDIMENT-LADEN WATER CANNOT ENTER THE CONVEYANCE SYSTEM WITHOUT FIRST BEING
FILTERED OR OTHERWISE TREATED TO REMOVE SEDIMENT.
MS-11: BEFORE STORMWATER CONVEYANCE CHANNELS ARE MADE OPERATIONAL, PROVIDE ADEQUATE
OUTLET PROTECTION AND ANY REQUIRED TEMPORARY OR PERMANENT CHANNEL LINING IN BOTH
THE CONVEYANCE CHANNEL AND THE RECEIVING CHANNEL.
MS-12: WHEN WORK IN A LIVE WATERCOURSE IS PERFORMED, TAKE PRECAUTIONS TO MINIMIZE
ENCROACHMENT, CONTROL SEDIMENT TRANSPORT AND STABILIZE THE WORK AREA TO THE
GREATEST EXTENT POSSIBLE DURING CONSTRUCTION. PROVIDE NON-ERODABLE MATERIAL FOR
THE CONSTRUCTION OF CAUSEWAYS AND COFFERDAMS. EARTHEN FILL MAY BE USED FOR THESE
STRUCTURES IF ARMORED BY NON-ERODABLE COVER MATERIALS.
MS-13: WHEN A LIVE WATERCOURSE MUST BE CROSSED BY CONSTRUCTION VEHICLES MORE THAN TWICE
IN ANY SIX-MONTH PERIOD, PROVIDE A TEMPORARY STREAM CROSSING CONSTRUCTED OF
NON-ERODABLE MATERIAL.
MS-14: MEET ALL APPLICABLE FEDERAL, STATE AND LOCAL REGULATIONS PERTAINING TO WORKING IN OR
CROSSING LIVE WATERCOURSES.
MS-15:STABILIZE THE BED AND BANKS OF A WATERCOURSE IMMEDIATELY FOLLOWING AFTER WORK IN
THE WATERCOURSE IS COMPLETED.
MS-16: UNDERGROUND UTILITY LINES SHALL BE INSTALLED IN ACCORDANCE WITH THESE STANDARDS IN
ADDITION TO OTHER APPLICABLE CRITERIA:
a. OPEN NO MORE THAN 500 LINEAR FEET OF TRENCH AT ONE TIME.
b. PLACE EXCAVATED MATERIAL ON THE UPHILL SIDE OF TRENCHES.
c. FILTER EFFLUENT FROM DEWATERING OPERATIONS OR PASS THROUGH AN APPROVED
SEDIMENT TRAPPING DEVICE, OR BOTH, AND DISCHARGE IN A MANNER THAT DOES NOT
ADVERSELY AFFECT FLOWING STREAMS OR OFFSITE PROPERTY.
d. PROPERLY COMPACT MATERIAL USED FOR BACKFILLING TRENCHES IN ORDER TO MINIMIZE
EROSION AND PROMOTE STABILIZATION.
e. ACCOMPLISH RESTABILIZATION IN ACCORDANCE WITH THIS CHAPTER.
f. COMPLY WITH ALL APPLICABLE SAFETY REGULATIONS.
MS-17: WHERE CONSTRUCTION VEHICLE ACCESS ROUTES INTERSECT PAVED PUBLIC ROADS, MAKE
PROVISIONS TO MINIMIZE THE TRANSPORT OF SEDIMENT BY VEHICULAR TRACKING ONTO
THE PAVED SURFACE. WHERE SEDIMENT IS TRANSPORTED ONTO A PUBLIC ROAD SURFACE,
CLEAN THE ROAD THOROUGHLY AT THE END OF EACH DAY. REMOVE SEDIMENT FROM THE
ROADS BY SHOVELING OR SWEEPING AND TRANSPORT TO A SEDIMENT CONTROL DISPOSAL AREA.
STREET WASHING SHALL BE ALLOWED ONLY AFTER SEDIMENT IS REMOVED IN THIS MANNER.
MS-18: REMOVE ALL TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES WITHIN 30 DAYS AFTER
FINAL SITE STABILIZATION OR AFTER THE TEMPORARY MEASURES ARE NO LONGER NEEDED,
UNLESS OTHERWISE AUTHORIZED BY THE LOCAL AUTHORITY HAVING JURISDICTION.
PERMANENTLY STABILIZE TRAPPED SEDIMENT AND THE DISTURBED SOIL AREAS RESULTING FROM
THE DISPOSITION OF TEMPORARY MEASURES TO PREVENT FURTHER EROSION AND
SEDIMENTATION.
MS-19: PROPERTIES AND WATERWAYS DOWNSTREAM FROM DEVELOPMENT SITES SHALL BE PROTECTED
FROM SEDIMENT DEPOSITION, EROSION AND DAMAGE DUE TO INCREASES IN VOLUME, VELOCITY
AND PEAK FLOW RATE OF STORMWATER RUNOFF FOR THE STATED FREQUENCY STORM OF
24-HOUR DURATION IN ACCORDANCE WITH THE FOLLOWING STANDARDS AND CRITERIA:
a. CONCENTRATED STORMWATER RUNOFF LEAVING A DEVELOPMENT SITE SHALL BE DISCHARGED
DIRECTLY INTO AN ADEQUATE NATURAL OR MAN-MADE RECEIVING CHANNEL, PIPE OR STORM
SEWER SYSTEM. FOR THOSE SITES WHERE RUNOFF IS DISCHARGED INTO A PIPE OR PIPE
SYSTEM, DOWNSTREAM STABILITY ANALYSES AT THE OUTFALL OF THE PIPE OR PIPE SYSTEM
SHALL BE PERFORMED.
b. ADEQUACY OF ALL CHANNELS AND PIPES SHALL BE VERIFIED IN THE FOLLOWING MANNER:
(1) THE APPLICANT SHALL DEMONSTRATE THAT THE TOTAL DRAINAGE AREA TO THE POINT OF
ANALYSIS WITHIN THE CHANNEL IS ONE HUNDRED TIMES GREATER THAN THE CONTRIBUTING
DRAINAGE AREA OF THE PROJECT IN QUESTION; OR
(2) (a) NATURAL CHANNELS SHALL BE ANALYZED BY THE USE OF A TWO-YEAR FREQUENCY
STORM TO VERIFY THAT STORMWATER WILL NOT OVERTOP CHANNEL BANKS NOR CAUSE
EROSION OF CHANNEL BED OR BANKS.
(b) ALL PREVIOUSLY CONSTRUCTED MAN-MADE CHANNELS SHALL BE ANALYZED BY THE USE
OF A TEN-YEAR FREQUENCY STORM TO VERIFY THAT STORMWATER WILL NOT OVERTOP ITS
BANKS AND BY THE USE OF A TWO-YEAR STORM TO DEMONSTRATE THAT STORMWATER WILL
NOT CAUSE EROSION OF CHANNEL BED OR BANKS; AND
(c) PIPES AND STORM SEWER SYSTEMS SHALL BE ANALYZED BY THE USE OF A TEN-YEAR
FREQUENCY STORM TO VERIFY THAT STORMWATER WILL BE CONTAINED WITHIN THE PIPE
OR SYSTEM.
c. IF EXISTING NATURAL RECEIVING CHANNELS OR PREVIOUSLY CONSTRUCTED MAN-MADE
CHANNELS OR PIPES ARE NOT ADEQUATE, THE APPLICANT SHALL:
(1) IMPROVE THE CHANNELS TO A CONDITION WHERE A TEN-YEAR FREQUENCY STORM WILL NOT
OVERTOP THE BANKS AND A TWO-YEAR FREQUENCY STORM WILL NOT CAUSE EROSION TO
THE CHANNEL, THE BED, OR BANKS;
(2) IMPROVE THE PIPE OR PIPE SYSTEM TO A CONDITION WHERE THE TEN-YEAR FREQUENCY
STORM IS CONTAINED WITHIN THE APPURTENANCES
(3) DEVELOP A SITE DESIGN THAT WILL NOT CAUSE THE PRE-DEVELOPMENT PEAK RUNOFF RATE
FROM A TWO-YEAR STORM TO INCREASE WHEN RUNOFF OUTFALLS INTO A NATURAL
CHANNEL OR WILL NOT CAUSE THE PRE-DEVELOPMENT PEAK RUNOFF RATE FROM A
TEN-YEAR STORM TO INCREASE WHEN RUNOFF OUTFALLS INTO A MAN-MADE CHANNEL; OR
(4) PROVIDE A COMBINATION OF CHANNEL IMPROVEMENT, STORMWATER
DETENTION/RETENTION OR OTHER MEASURES WHICH IS SATISFACTORY TO THE VESCP
AUTHORITY TO PREVENT DOWNSTREAM EROSION.
d. THE APPLICANT SHALL PROVIDE EVIDENCE OF PERMISSION TO MAKE THE IMPROVEMENTS.
e. ALL HYDROLOGIC ANALYSES SHALL BE BASED ON THE EXISTING WATERSHED
CHARACTERISTICS AND THE ULTIMATE DEVELOPMENT CONDITION OF THE SUBJECT PROJECT.
f. IF THE APPLICANT CHOOSES AN OPTION THAT INCLUDES STORMWATER DETENTION, HE SHALL
OBTAIN APPROVAL FROM THE VESCP OF A PLAN FOR MAINTENANCE OF THE DETENTION
FACILITIES. THE PLAN SHALL SET FORTH THE MAINTENANCE REQUIREMENTS OF THE FACILITY
AND THE PERSON RESPONSIBLE FOR PERFORMING THE MAINTENANCE.
g. OUTFALL FROM A DETENTION FACILITY SHALL BE DISCHARGED TO A RECEIVING CHANNEL, AND
ENERGY DISSIPATERS SHALL BE PLACED AT THE OUTFALL OF ALL DETENTION FACILITIES AS
NECESSARY TO PROVIDE A STABILIZED TRANSITION FROM THE FACILITY TO THE RECEIVING
CHANNEL.
h. ALL ON-SITE CHANNELS MUST BE VERIFIED TO BE ADEQUATE.
i. INCREASED VOLUMES OF SHEET FLOWS THAT MAY CAUSE EROSION OR SEDIMENTATION ON
ADJACENT PROPERTY SHALL BE DIVERTED TO A STABLE OUTLET, ADEQUATE CHANNEL, PIPE OR
PIPE SYSTEM, OR TO A DETENTION FACILITY.
j. IN APPLYING THESE STORMWATER MANAGEMENT CRITERIA, INDIVIDUAL LOTS IN A RESIDENTIAL
SUBDIVISION DEVELOPMENT SHALL NOT BE CONSIDERED TO BE SEPARATE DEVELOPMENT
PROJECTS. INSTEAD, THE RESIDENTIAL SUBDIVISION DEVELOPMENT, AS A WHOLE, SHALL BE
CONSIDERED TO BE A SINGLE DEVELOPMENT PROJECT. HYDROLOGIC PARAMETERS THAT
REFLECT THE ULTIMATE SUBDIVISION DEVELOPMENT SHALL BE USED IN ALL ENGINEERING
CALCULATIONS.
k. ALL MEASURES USED TO PROTECT PROPERTIES AND WATERWAYS SHALL BE EMPLOYED IN A
MANNER WHICH MINIMIZES IMPACTS ON THE PHYSICAL, CHEMICAL AND BIOLOGICAL INTEGRITY
OF RIVERS, STREAMS AND OTHER WATERS OF THE STATE.
l. ANY PLAN APPROVED PRIOR TO JULY 1, 2014, THAT PROVIDES FOR STORMWATER MANAGEMENT
THAT ADDRESSES ANY FLOW RATE CAPACITY AND VELOCITY REQUIREMENTS FOR NATURAL OR
MAN-MADE CHANNELS SHALL SATISFY THE FLOW RATE CAPACITY AND VELOCITY
REQUIREMENTS FOR NATURAL OR MAN-MADE CHANNELS IF THE PRACTICES ARE DESIGNED TO
(I) DETAIN THE WATER QUALITY VOLUME AND TO RELEASE IT OVER 48 HOURS; (II) DETAIN AND
RELEASE OVER A 24-HOUR PERIOD THE EXPECTED RAINFALL RESULTING FROM THE ONE YEAR,
24-HOUR STORM; AND (III) REDUCE THE ALLOWABLE PEAK FLOW RATE RESULTING FROM THE 1.5, 2, AND 10-YEAR, 24-HOUR STORMS TO A LEVEL THAT IS LESS THAN OR EQUAL TO THE PEAK
FLOW RATE FROM THE SITE ASSUMING IT WAS IN A GOOD FORESTED CONDITION, ACHIEVED
THROUGH MULTIPLICATION OF THE FORESTED PEAK FLOW RATE BY A REDUCTION FACTOR
THAT IS EQUAL TO THE RUNOFF VOLUME FROM THE SITE WHEN IT WAS IN A GOOD FORESTED
CONDITION DIVIDED BY THE RUNOFF VOLUME FROM THE SITE IN ITS PROPOSED CONDITION,
AND SHALL BE EXEMPT FROM ANY FLOW RATE CAPACITY AND VELOCITY REQUIREMENTS FOR
NATURAL OR MAN-MADE CHANNELS AS DEFINED IN ANY REGULATIONS PROMULGATED
PURSUANT TO § 62.1-44.15:54 OR 62.1-44.15:65 OF THE ACT.
m. FOR PLANS APPROVED ON AND AFTER JULY 1, 2014, THE FLOW RATE CAPACITY AND VELOCITY
REQUIREMENTS OF § 62.1-44.15:52 A OF THE ACT AND THIS SUBSECTION SHALL BE SATISFIED BY
COMPLIANCE WITH WATER QUANTITY REQUIREMENTS IN THE STORMWATER MANAGEMENT ACT
(§ 62.1-44.15:24 ET SEQ. OF THE CODE OF VIRGINIA) AND ATTENDANT REGULATIONS, UNLESS
SUCH LAND-DISTURBING ACTIVITIES ARE IN ACCORDANCE WITH PROVISIONS FOR THE TIME
LIMITS ON APPLICABILITY OF APPROVED DESIGN CRITERIA IN 9VAC25-870-47 OR
GRANDFATHERING IN 9VAC25-870-48 OF THE VIRGINIA STORMWATER MANAGEMENT PROGRAM
(VSMP) REGULATION, IN WHICH CASE THE FLOW RATE CAPACITY AND VELOCITY REQUIREMENTS
OF § 62.1-44.15:52 A OF THE ACT SHALL APPLY, OR ARE EXEMPT PURSUANT TO § 62.1-44.15:34 C7
OF THE ACT.
n. COMPLIANCE WITH THE WATER QUANTITY MINIMUM STANDARDS SET OUT IN 9VAC25-870-66 OF
THE VIRGINIA STORMWATER MANAGEMENT PROGRAM (VSMP) REGULATIONS SHALL BE DEEMED
TO SATISFY THE REQUIREMENTS OF SUBDIVISION 19 OF THIS SUBSECTION.
GENERAL EROSION AND SEDIMENT CONTROL NOTES
ES-1: UNLESS OTHERWISE INDICATED, CONSTRUCT AND MAINTAIN ALL VEGETATIVE AND STRUCTURAL
EROSION AND SEDIMENT CONTROL PRACTICES ACCORDING TO MINIMUM STANDARDS AND
SPECIFICATIONS OF THE VIRGINIA EROSION AND SEDIMENT CONTROL HANDBOOK AND VIRGINIA
REGULATIONS 9 VAC 25-840-40
ES-2: NOTIFY THE DEPARTMENT OF PUBLIC WORKS ONE WEEK PRIOR TO THE PRE-CONSTRUCTION
CONFERENCE, ONE WEEK PRIOR TO THE COMMENCEMENT OF LAND DISTURBING ACTIVITY, AND
ONE WEEK PRIOR TO THE FINAL INSPECTION.
ES-3: PLACE ALL EROSION AND SEDIMENT CONTROL MEASURES PRIOR TO OR AS THE FIRST STEP IN
CLEARING, GRADING, OR LAND DISTURBANCE.
ES-4: MAINTAIN A COPY OF THE APPROVED EROSION AND SEDIMENT CONTROL PLAN ON THE SITE AT ALL
TIMES.
ES-5: PRIOR TO COMMENCING LAND-DISTURBING ACTIVITIES IN AREAS OTHER THAN INDICATED ON
THESE PLANS (INCLUDING, BUT NOT LIMITED TO, OFFSITE BORROW OR WASTE AREA), THE
CONTRACTOR SHALL SUBMIT A SUPPLEMENTARY EROSION CONTROL PLAN TO THE
ARCHITECT/ENGINEER FOR REVIEW AND APPROVAL BY THE PLAN APPROVING AUTHORITY.
ES-6: PROVIDE ADDITIONAL EROSION CONTROL MEASURES NECESSARY TO PREVENT EROSION AND
SEDIMENTATION AS DETERMINED BY THE DPU INSPECTOR.
ES-7: ALL DISTURBED AREAS ARE TO DRAIN TO APPROVED SEDIMENT CONTROL MEASURES AT ALL
TIMES DURING LAND-DISTURBING ACTIVITIES AND DURING SITE DEVELOPMENT UNTIL FINAL
STABILIZATION IS ACHIEVED.
ES-8: DURING DEWATERING OPERATIONS, PUMP WATER INTO AN APPROVED FILTERING DEVICE.
ES-9: INSPECT ALL EROSION CONTROL MEASURES DAILY AND AFTER EACH RUNOFF-PRODUCING
RAINFALL EVENT. MAKE ANY NECESSARY REPAIRS OR CLEANUP TO MAINTAIN THE EFFECTIVENESS
OF THE EROSION CONTROL DEVICES IMMEDIATELY.
PROJECT AREA
SOILS MAP
SOURCE: NRCS WEB SOIL SURVEY
JOB NO.
SHEET NO.
SCALE
DESIGNED BY
CHECKED BY
D A T E
DRAWN BY
DATE
R E V I S I O
N D
E S C R I P T I O
N
T h e s e p la n s a n d a s s o c ia te d d o c u m e n ts a re t h e e x c lu s iv e p ro p e rt y o f T
IM
M
O N
S G
R O
U P a n d m a y n o t b e r e p ro d u c e d i n w h o le o r in p a rt a n d s h a ll n o t b e u s e d f o r a n y p u rp o s e w h a ts o e v e r, i n c lu s iv e b u t n o t lim it e d t o c o n s tr u c ti o n b id d in g a n d /o r c o n s tr u c ti o n s ta k in g w it h o u t th e e x p re s s w ri tt e n c o n s e n t o f
T
IM
M O
N S
G R
O U
P
04/28/2023
N W
H I T E H
I L L D
R I V E D
R A I N
A G
E I
M P R O
V E M
E N
T C I T Y O
F P
E T E R S B U
R G
V
I R G
I N
I A
51547
L
\5
-W h it e h ill
D r\
D W
G \S w a le
P h a s e \S h e e t\
C D
\5 C
-3 .0
-E C
N D
.d w g P lo tt e d o n
/8 /2
:0 P
M b y K e ls e y R e d m a n
C3.0
E R O
S I O
N
S E D
I M
E N
T C
O N
T R O
L N
O T E S
K. REDMAN
S. REEVES
M. CLAUD
AS SHOWN
council Sticky Note
SPECIFIC APPLICATION
2"X4" WOOD
SEDIMENT
*GRAVEL FILTER
WITH SEDIMENT
RUNOFF WATER
WIRE SCREEN
STUD
OVERFLOW
CURB INLET
FILTERED WATER
CURB INLET
WIRE SCREEN CONC. BLOCK
THIS METHOD OF INLET PROTECTION IS APPLICABLE AT CURB INLETS
WHERE OVERFLOW CAPABILITY IS NECESSARY TO PREVENT EXCESSIVE
PONDING IN FRONT OF THE STRUCTURE.
*GRAVEL SHALL BE VDOT #3, #357, OR #5 COARSE AGGREGATE.
NO SCALE
BLOCK AND GRAVEL CURB INLET SEDIMENT FILTER
PLATE 3.07-3
IP
ADAPTED FROM CONWED PLASTICS AND VDOT
ROAD AND BRIDGE STANDARDS
No Scale
SAFETY FENCESAF
PLATE 3.01-1
5' MIN.
6' MAX.
POLYETHYLENE FABRIC
(ATTACH TO POSTS WITH
METAL TIE WIRES.)
CONVENTIONAL METAL (T)
OR (U) POSTS
TABLE 3.32-E
(REVISED JUNE 2003)
PERMANENT SEEDING SPECIFICATIONS FOR COASTAL PLAIN AREA
LAND USE SPECIES APPLICATION PER ACRE
SEED¹
TALL FESCUE¹
or
BERMUDAGRASS¹
MINIMUM CARE LAWN
(COMMERCIAL OR RESIDENTIAL)
HIGH-MAINTENANCE LAWN
GENERAL SLOPE (3:1 OR LESS)
LOW-MAINTENANCE SLOPE
(STEEPER THAN 3:1)
TALL FESCUE¹
or
BERMUDAGRASS¹ (SEED)
or
BERMUDAGRASS¹ (BY OTHER VEGETATIVE
ESTABLISHMENT METHOD, SEE STD. &
SPEC. 3.34)
TALL FESCUE¹
RED TOP GRASS OR CREEPING RED FESCUE
SEASONAL NURSE CROP²
TALL FESCUE¹
BERMUDAGRASS¹
RED TOP GRASS OR CREEPING RED FESCUE
SEASONAL NURSE CROP²
SERICEA LESPEDEZA³
175 - 200 LBS.
128 LBS.
2 LBS.
20LBS.
TOTAL: 150 LBS.
93 - 108 LBS.
0 - 15 LBS.
2 LBS.
20 LBS.
20 LBS.
TOTAL: 150 LBS.
200-250 LBS.
1 - WHEN SELECTING VARIETIES OF TURFGRASS, USE THE VIRGINIA CROP IMPROVEMENT ASSOCIATION (VCIA)
RECOMMENDED TURFGRASS VARIETY LIST. QUALITY SEED WILL BEAR A LABEL INDICATING THAT THEY ARE
APPROVED BY VCIA. A CURRENT TURFGRASS VARIETY LIST IS AVAILABLE AT THE LOCAL COUNTY EXTENSION
OFFICE OR THROUGH VCIA AT 804-746-4884 OR AT
HTTP://SUDAN.CSES.VT.EDU/HTML/TURF/TURF/PUBLICATIONS/PUBLICATIONS2.HTML
2 - USE SEASONAL NURSE CROP IN ACCORDANCE WITH SEEDING DATES AS STATED BELOW:
FEBRUARY, MARCH - APRIL ......................... ANNUAL RYE
MAY 1ST - AUGUST ....................................... FOXTAIL MILLET
SEPTEMBER, OCTOBER - NOVEMBER 15TH ..... ANNUAL RYE
NOVEMBER 16TH - JANUARY ............................. WINTER RYE
3 - MAY THROUGH OCTOBER, USE HULLED SEED. ALL OTHER PERIODS, USE UNHULLED SEED. IF WEEPING
LOVEGRASS IS USED, INCLUDE IN ANY SLOPE OR LOW MAINTENANCE MIXTURE DURING WARMER SEEDING
PERIODS, INCREASE TO 30 - 40 LBS/ACRE.
FERTILIZER & LIME
· APPLY 10-20-10 FERTILIZER AT A RATE OF 500 LBS. / ACRE (OR 12 LBS. / 1,000 SQ. FT.)
· APPLY PULVERIZED AGRICULTURAL LIMESTONE AT A RATE OF 2 TONS/ACRE (90 LBS. / 1,000 SQ. FT.)
NOTE:
- A SOIL TEST IS NECESSARY TO DETERMINE THE ACTUAL AMOUNT OF LIME REQUIRED TO ADJUST THE SOIL pH
OF SITE.
- INCORPORATE THE LIME AND FERTILIZER INTO THE TOP 4 - 6 INCHES OF THE SOIL BY DISKING OR BY OTHER
MEANS.
- WHEN APPLYING SLOWLY AVAILABLE NITROGEN, USE RATES AVAILABLE IN EROSION & SEDIMENT CONTROL
TECHNICAL BULLETIN #4, 2003 NUTRIENT MANAGEMENT FOR DEVELOPMENT SITES AT
HTTP://WWW.DCR.STATE.VA.US/SW/E&S.HTM#PUBS
75 LBS.
40 LBS.(UNHULLED)
30 LBS. (HULLED)
TABLE 3.31-B
(REVISED JUNE 2003)
TEMPORARY SEEDING SPECIFICATIONS
QUICK REFERENCE FOR ALL REGIONS
APPLICATION DATES SPECIES APPLICATION RATES
SEED
50 -100 (lbs/acre)Sept. 1 - Feb. 15
60 - 100 (lbs/acre)
50 (lbs/acre)
Feb. 16 - Apr. 30
May 1 - Aug. 31
50/50 Mix of Annual Ryegrass (lolium multi-florum) & Cereal (Winter) Rye (Secale cereale)
Annual Ryegrass (lolium multi-florum)
German Millet
FERTILIZER & LIME
· Apply 10-10-10 fertilizer at a rate of 450 lbs / acre (or 10 lbs. / 1,000 sq. ft.)
· Apply Pulverized Agricultural Limestone at a rate of 2 tons / acre (or 90 lbs. / 1,000 sq. ft.)
NOTE:
1. A soil test is necessary to determine the actual amount of lime required to adjust the soil pH of site.
2. Incorporate the lime and fertilizer into the top 4 - 6 inches of the soil by disking or by other means.
3. When applying Slowly Available Nitrogen, use rates available in Erosion & Sediment Control Technical Bulletin
#4, 2003 Nutrient Management for Development Sites at http://www.dcr.state.va.us/sw/e&s.htm#pubs
ON SHALLOW SLOPES, STRIPS OF
NETTING PROTECTIVE COVERINGS
MAY BE APPLIED ACROSS THE
SLOPE.
BERM
IN DITCHES, APPLY PROTECTIVE COVERING
PARALLEL TO THE DIRECTION OF FLOW. USE
CHECK SLOTS AS REQUIRED. AVOID JOINING
MATERIAL IN THE CENTER OF THE DITCH IF
AT ALL POSSIBLE.
ON STEEP SLOPES, APPLY
PROTECTIVE COVERING
PARALLEL TO THE DIRECTION OF
FLOW AND ANCHOR SECURELY.
BRING MATERIAL DOWN TO A LEVEL AREA
BEFORE TERMINATING THE INSTALLATION.
TURN THE END UNDER 4" AND STAPLE AT 12"
INTERVALS.
DITCH FLOW
4"
12"
WHERE THERE IS A BERM AT THE
TOP OF THE SLOPE, BRING THE
MATERIAL OVER THE BERM AND
ANCHOR IT BEHIND THE BERM.
STEEP SLOPE
SHALLOW
SLOPE
No Scale
SOIL STABILIZATION BLANKET - TYPICAL ORIENTATION OF TREATMENT I
PLATE 3.36-1
B/M
AT CORNERS
GATHER EXCESS
PERSPECTIVE VIEWS
2 x 4 WOOD
MIN.
1.5'
FRAME
SPECIFIC APPLICATION
WITH SEDIMENT
RUNOFF WATER
MIN.
3'
BURIED FABRIC
MIN.
1'
FRAME
WITH GRATE
DROP INLET
FABRIC ORIENTATION
ELEVATION OF STAKE AND
WATER
FILTERED
FABRIC
STAKES
THIS METHOD OF INLET PROTECTION IS APPLICABLE WHERE THE INLET DRAINS A
RELATIVELY FLAT AREA (SLOPES NO GREATER THAN 5%) WHERE INLET SHEET OR
OVERLAND FLOWS (NOT EXCEEDING 1 CFS) ARE TYPICAL. THE METHOD SHALL
NOT APPLY TO INLETS RECEIVING CONCENTRATED FLOWS, SUCH AS IN STREET
OR HIGHWAY MEDIANS.
NO SCALE
SILT FENCE DROP INLET PROTECTION
PLATE 3.07-1
IP
JOB NO.
SHEET NO.
SCALE
DESIGNED BY
CHECKED BY
D A T E
DRAWN BY
DATE
R E V I S I O
N D
E S C R I P T I O
N
T h e s e p la n s a n d a s s o c ia te d d o c u m e n ts a re t h e e x c lu s iv e p ro p e rt y o f T
IM
M
O N
S G
R O
U P a n d m a y n o t b e r e p ro d u c e d i n w h o le o r in p a rt a n d s h a ll n o t b e u s e d f o r a n y p u rp o s e w h a ts o e v e r, i n c lu s iv e b u t n o t lim it e d t o c o n s tr u c ti o n b id d in g a n d /o r c o n s tr u c ti o n s ta k in g w it h o u t th e e x p re s s w ri tt e n c o n s e n t o f
T
IM
M O
N S
G R
O U
P
04/28/2023
N W
H I T E H
I L L D
R I V E D
R A I N
A G
E I
M P R O
V E M
E N
T C I T Y O
F P
E T E R S B U
R G
V
I R G
I N
I A
51547
L
\5
-W h it e h ill
D r\
D W
G \S w a le
P h a s e \S h e e t\
C D
\5 C
-3 .0
-E C
N D
.d w g P lo tt e d o n
/8 /2
:0 P
M b y K e ls e y R e d m a n
C3.1
E R O
S I O
N
S E D
I M
E N
T C
O N
T R O
L D
E T A I L S
K. REDMAN
S. REEVES
M. CLAUD
AS SHOWN
G
G G
W W
W
W
WWWWWW
W
W W
W W
UGT
G G
G G
G
46 47
S A N
S A N
S A N
S A N
S A N
S A N
S A N
S A N
S A N
S A N
S A N
X
X X
X
XX
XXX
XX XX
O H U
OHU
OHU
OHU
OHU
OHU
O H U
O H U
OHU
OHU
XXX
XX
OHU OHU OHU OHU OHU OHU OHU
X
X
X X
X
X X
X X
X
OHU
OHU
OHU
OHU
OHU
OHU
O H U
O H U
O H U
OHU
X
OHU
O H U
O H U
O H U
T
O P
O G
R A
P H
IC
S
U R
V E
Y
2021 TOPOGRAPHIC
SURVEY
T
O P
O G
R A
P H
IC
S U
R V
E Y
T
O P
O G
R A
P H
IC
L
ID
A
R D
A T
A A
N D
G
IS
M A
P P
IN
G
2014 TOPOGRAPHIC LIDAR
DATA AND GIS MAPPING
T
O P
O G
R A
P H
IC
L
ID
A
R
D A
T A
A N
D G
IS
M
A P
P
IN
G
U3
U2
6" PVC
U8
15" CLASS III RCP
U4
6" PVC
U6
6" PVCU10
15" HDPE
U1
SAFSAF
SAF
SAF SAF
SAF
SAF
SAF SAF
SAFSAFSAF
S A
F
IP
IP
SAF
B/M
B/M
PSPSLOD
LOD LOD LOD
LOD LOD LOD LOD LOD
LODLODLODLOD
LODLODLOD
IP
PS MU
TS
PS
MU
SOIL STABILIZATION BLANKETS
& MATTING: EC-2, TYPE 2
SAF SAFETY FENCE
INLET PROTECTION
TEMPORARY SEEDING
PERMANENT SEEDING
MULCHING
3.01
3.07
3.31
3.32
3.35
3.36
SYMBOLLABEL STDANDARD NAME SPEC.#
EROSION CONTROL LEGEND
SAF
IP
TS
PS
MU
B/M
QUANTITY
500 LF
3 EA
4.8 LB
14 LB
215 SY
165 SY
LIMITS OF DISTURBANCELOD 0.09 AC
JOB NO.
SHEET NO.
SCALE
DESIGNED BY
CHECKED BY
D A T E
DRAWN BY
DATE
R E V I S I O
N D
E S C R I P T I O
N
T h e s e p la n s a n d a s s o c ia te d d o c u m e n ts a re t h e e x c lu s iv e p ro p e rt y o f T
IM
M
O N
S G
R O
U P a n d m a y n o t b e r e p ro d u c e d i n w h o le o r in p a rt a n d s h a ll n o t b e u s e d f o r a n y p u rp o s e w h a ts o e v e r, i n c lu s iv e b u t n o t lim it e d t o c o n s tr u c ti o n b id d in g a n d /o r c o n s tr u c ti o n s ta k in g w it h o u t th e e x p re s s w ri tt e n c o n s e n t o f
T
IM
M O
N S
G R
O U
P
04/28/2023
N W
H I T E H
I L L D
R I V E D
R A I N
A G
E I
M P R O
V E M
E N
T C I T Y O
F P
E T E R S B U
R G
V
I R G
I N
I A
51547
L
\5
-W h it e h ill
D r\
D W
G \S w a le
P h a s e \S h e e t\
C D
\5 C
-3 .0
-E R
O S
.d w g P lo tt e d o n
/8 /2
:0 P
M b y K e ls e y R e d m a n
C3.2
E R O
S I O
N
S E D
I M
E N
T C
O N
T R O
L P
L A N
K. REDMAN
S. REEVES
M. CLAUD
AS SHOWN
NAD 83
SCALE 1"=20'
40'20'
G G
W W
W
W
WWWWWW
W
W W
W W
UGT
G G
G G
G
46 47
S A
N S
A N
S A
N S
A N
S A
N S
A N
S A
N S
A N
S A
N S
A N
S A
N
X
X X
X
XX
XXX
XX XX
O H
U
OHU
OHU
OHU
OHU
OHU
O H
U
O H
U
OHU
OHU
XXX
XX
OHU OHU OHU OHU OHU OHU OHU
X
X
X X
X
X X
X X
X
OHU
OHU
OHU
OHU
OHU
OHU
O H
U O
H U
O H
U
OHU
X
OHU
O H
U O
H U
O H
U
T
O P
O G
R A
P H
IC
S
U R
V E
Y
2021 TOPOGRAPHIC
SURVEY
T
O P
O G
R A
P H
IC
S U
R V
E Y
T
O P
O G
R A
P H
IC
L
ID
A
R D
A T
A A
N D
G
IS
M A
P P
IN
G
2014 TOPOGRAPHIC LIDAR
DATA AND GIS MAPPING
T
O P
O G
R A
P H
IC
L
ID
A
R
D A
T A
A N
D G
IS
M
A P
P
IN
G
USE CAUTION IN
VICINITY OF EXISTING
FIRE HYDRANT AND
WATER LINE
(DO NOT DISTURB)
UTILITY NOTE: CONTRACTOR SHALL COORDINATE WITH DOMINION POWER TO ESTABLISH AN OVERHEAD UTILITY PROTECTION
PLAN. CONTRACTOR SHALL FOLLOW ALL REQUIREMENTS SET FORTH BY DOMINION POWER FOR UTILITY PROTECTION
REPLACE 76 LF OF 3'
CHAIN LINK FENCING
& TOP RAIL
REPLACE 119 LF 3'
CHAIN LINK FENCING &
TOP RAIL
REPLACE GATE C
REPLACE
GATE B
REPLACE GATE A
REPLACE GATE D
CONTRACTOR TO
COORDINATE
WITH TELEPHONE
TO ADJUST UGT
REINSTALL EX.
NEIGHBORHOOD
WATCH SIGN PER
VDOT STP-1
SEE NOTE 1
REPLACE 260 SF
GRAVEL DRIVEWAY
U1
U2
6" PVC
U3
U6
6" PVC
U8
15" CLASS III RCP
10+00
10+50 11+00 11+50 12+00 12+50 12+91.17 U10
15" HDPE
S E
C T
IO
N
S E
C T
IO
N
U4
6" PVC
SWALE CENTERLINE PROFILE
U6
72' OF 6" PERFORATED PVC
@ 0.50% U10
38' OF 15" HDPE
@ 0.42%
9+90 10+00 10+50 11+00 11+50 12+00 12+50 12+90
DRY SWALE
SECTION B INVERT
DRY SWALE
SECTION A
INVERT
STA 11+42.36
END PERFORATED 6" PVC.
BEGIN SOLID WALL 6" PVC.
USE CAUTION IN
VICINITY OF EX.
FIRE HYDRANT
AND WATER LINE
STA 11+14.80
END PERFORATED 6" PVC.
BEGIN SOLID WALL 6" PVC.
U3
TOP 45.30
INV IN…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .