This document contains drawings and specifications for the Cheboygan Dam Improvements Project, which is being managed by the Michigan Department of Technology, Management and Budget (DTMB) on behalf of the Michigan Department of Natural Resources (MDNR). The project involves repairs and renovations to the Cheboygan Dam facility located in Cheboygan, Michigan. The key components include replacing the existing dam gate actuators and controls, improving site access and soil erosion/sediment control, and conducting other miscellaneous repairs. The contract is being issued for bid, with a bid due date of August 24, 2023. Approved emailed submissions must be received prior to the 2:00 p.m. deadline to be considered responsive. The project is located primarily within Cheboygan County, with some work to be performed on the adjacent property of Great Lakes Tissue Company. The contract is expected to be awarded following the bid due date, but the specific award date is not provided. No information is given on the contract term or any renewal options.
Regarding pricing, the document does not specify any set-asides or the current incumbent contractor. It indicates that the project will be funded by the MDNR, but the exact funding amount is not disclosed. Contractors are required to provide unit pricing for the various bid items, and the overall contract will be awarded to the lowest responsive and responsible bidder.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum 1 17264.pdf | ||
| Specifications 17264.pdf | ||
| SESC Plan Review DTMB Approval PSC 17264.pdf | ||
| Advertisement 17264.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
\\geiconsulta B:\Working\DTMB\1904013 Cheboygan Lock Facility - Repair and Reno\CAD\Design\Working\Dam Drawings\COVER SHEET.dwg - 10/24/2022
CHEBOYGAN DAM IMPROVEMENTS PROJECT
MICHIGAN DEPARTMENT OF NATURAL RESOURCES
CHEBOYGAN, MI
DTMB FILE: 751/17264.ABG
THIS DOCUMENT, AND THE IDEAS AND DESIGNS INCORPORATED
HEREIN, IS AN INSTRUMENT OF PROFESSIONAL SERVICE, IS THE
PROPERTY OF GEI CONSULTANTS AND IS NOT TO BE USED, IN WHOLE
OR IN PART, FOR ANY OTHER PROJECT WITHOUT THE WRITTEN
AUTHORIZATION OF GEI CONSULTANTS.
STATE MAP
(NOT TO SCALE)
SITE LOCATION MAP
(NOT TO SCALE)
PREPARED FOR:
MICHIGAN DEPARTMENT OF TECHNOLOGY,
MANAGEMENT, AND BUDGET
440 N. STATE ST
SAINT IGNACE, MI 49781
(906)643-6181
GEI PROJECT NO. 1904013
SITE
SOURCE:
GOOGLE EARTH IMAGE
ISSUE FOR BID
NO. DATE ISSUE/REVISION APP
A 8/24/2023 ISSUE FOR BID SAE
Consultants
PREPARED BY:
GEI CONSULTANTS OF MICHIGAN, P.C.
109 W. BARAGA AVENUE
MARQUETTE, MI 49855
(906)451-4021
DWG. NO.
SHEET NO.
G-01
SITE
PROJECT OWNER:
MICHIGAN DEPARTMENT OF NATURAL
RESOURCES
120 A STREET
CHEBOYGAN, MICHIGAN 49721
(231)627-9011
P L U R I B U E
S U N U M
C I R C U M S P I C E
SI QU EREI S PENI NSUL AM AMOENAM
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
STATE OF MICHIGAN
ADAM P. LACH, RA, DIRECTOR
STATE FACILITIES ADMINISTRATION
DESIGN AND CONSTRUCTION DIVISION
SHEET INDEX
SHEET NO. DRAWING NO. SHEET TITLE
1 G-01 COVER SHEET
2 G-02 GENERAL NOTES AND LEGEND
3 G-03 SITE ACCESS PLAN
4 G-04 SOIL EROSION AND SEDIMENT CONTROL PLAN
5 C-01 EXISTING SITE PLAN
6 C-02 EXISTING DAM GATE CONTROLS
7 C-03 PROPOSED DAM GATE CONTROLS
APPROX = APPROXIMATE
CL = CENTERLINE
CLR = CLEAR
CNTR = CENTER
CONC = CONCRETE
DIA, Ø = DIAMETER
DIM = DIMENSION(S)
D/S = DOWNSTREAM
DWG, DWGS = DRAWING OR DRAWINGS
EA = EACH
EL., ELEV = ELEVATION
FT = FEET OR FOOT
GALV = GALVANIZED
GR = GRADE
HSS = HOLLOW STRUCTURAL STEEL
LLH = LONG LEG HORIZONTAL
LOC = LIMITS OF CONSTRUCTION
MAX = MAXIMUM
MIN = MINIMUM
NO = NUMBER
NTS = NOT TO SCALE
O.C. = ON CENTER
PL = PLATE
RA = RADIUS
REINF = REINFORCEMENT
REQ'D = REQUIRED
SPEC = SPECIFICATION(S)
TC = TURBIDITY CURTAIN
TYP = TYPICAL
U.N.O. = UNLESS NOTED OTHERWISE
U/S = UPSTREAM
VERT = VERTICAL
VIF = VERIFY IN FIELD
ABBREVIATIONS:
GENERAL LEGEND:
A S-01
A S-01
SECTION LOCATION. THE LETTER "A" REFERS TO THE SECTION
DESIGNATION. THE NUMBER "S-01" REFERS TO THE DRAWING NUMBER
WHERE THE SECTION IS SHOWN.
S-01
DETAIL LOCATION. THE NUMBER "1" REFERS TO THE DETAIL
DESIGNATION. THE NUMBER "S-01" REFERS TO THE DRAWING NUMBER
WHERE THE DETAIL IS SHOWN.
SCALE: N.T.S.
DETAIL - XXXX1
S-01
SCALE: N.T.S.
SECTION - XXXXA
S-01
DETAIL TITLE. THE NUMBER "1" REFERS TO THE DETAIL DESIGNATION.
THE NUMBER "S-01" REFERS TO THE DRAWING NUMBER WHERE THE
DETAIL IS CALLED OUT.
SECTION TITLE. THE LETTER "A" REFERS TO THE DETAIL
DESIGNATION. THE NUMBER "S-01" REFERS TO THE DRAWING
NUMBER WHERE THE DETAIL IS CALLED OUT.
VERTICAL DATUM:
NORTH AMERICAN VERTICAL DATUM OF 1988 (NAVD88)
NOTE: EXISTING DRAWINGS IN IGLD55. TO CONVERT BETWEEN DATUMS:
594.09 (IGLD55) + 0.95 FT = 595.04 (NAVD88)
\\geiconsulta B:\Working\DTMB\1904013 Cheboygan Lock Facility - Repair and Reno\CAD\Design\Working\Dam Drawings\GENERAL NOTES AND LEGEND.dwg - 7/31/2023
MICHIGAN DEPARTMENT OF
TECHNOLOGY, MANAGEMENT AND
BUDGET
GEI Project 1904013
If this scale bar does not measure 1" then drawing is not original scale.
Attention: CHEBOYGAN DAM IMPROVEMENTS PROJECT
CHEBOYGAN, MI
GEI CONSULTANTS OF MICHIGAN, P.C.
109 W. BARAGA AVENUE
MARQUETTE, MI 49855
(906)451-4021
Consultants
0 1"
NO. DATE ISSUE/REVISION APP
A 8/24/2023 ISSUE FOR BID SAE
Designed:
Checked:
Drawn:
JEP
KAR
JEP
Approved By: SAE
SHEET NO.
DWG. NO.
OF 7
ISSUE FOR BID
HISTORICAL DRAWING SHEET INDEX
DATE DRAWING NO. SHEET TITLE
6/15/1967 523-02-1 CONSTRUCTION DETAILS
6/15/1967 523-03-1 GATE FABRICATION DETAILS
HORIZONTAL DATUM:
NORTH AMERICAN DATUM 1983 (NAD83)
GENERAL NOTES AND LEGEND
GENERAL NOTES:
1. THESE NOTES SUPPLEMENT THE PROJECT SPECIFICATIONS. ANY DISCREPANCY FOUND AMONG THE DRAWINGS, SPECIFICATIONS, THESE NOTES, AND THE SITE CONDITIONS SHALL BE REPORTED TO
THE OWNER'S REPRESENTATIVE (GEI), WHO SHALL CORRECT SUCH DISCREPANCY IN WRITING.
ANY WORK DONE BY THE CONTRACTOR AFTER DISCOVERY OF SUCH DISREPANCY SHALL BE
DONE AT CONTRACTOR'S RISK. THE CONTRACTOR SHALL VERIFY AND COORDINATE THE
DIMENSIONS AMONG ALL DRAWINGS PRIOR TO PROCEEDING WITH ANY WORK OF FABRICATION.
2. CONSTRUCTION IS SUBJECT TO THE RULES AND REGULATIONS OF THE MICHIGAN DEPARTMENT OF THE ENVIRONMENT, GREAT LAKES, AND ENERGY (EGLE) AND THE UNITED STATES ARMY CORPS OF ENGINEERS (USACE). SUBSTANTIVE CHANGES TO THE APPROVED DRAWINGS AND SPECIFICATIONS
MAY REQUIRE EGLE AND/OR USACE APPROVAL.
3. PRIMARY SITE ACCESS TO THE PROJECT IS PROVIDED AS FOUND ON SHEET G-03.
4. THE SUBSURFACE UTILITY INFORMATION IN THIS PLAN SHALL BE ASSUMED TO BE APPROXIMATE.
THE CONTRACTOR SHALL MAKE ANY NECESSARY INVESTIGATIONS AND COORDINATION WITH THE 811
MIS-DIG ONE CALL PRIOR TO COMMENCEMENT OF ANY WORK ACTIVITIES.
5. THE CONTRACTOR IS RESPONSIBLE FOR ALL TEMPORARY BRACING AND SHORING (SHOWN AND
NOT SHOWN ON THESE DRAWINGS) DURING CONSTRUCTION.
6. SHOP DRAWINGS FOR REINFORCING STEEL, AND STRUCTURAL STEEL SHALL BE SUBMITTED TO
THE OWNER'S REPRESENTATIVE (GEI) FOR REVIEW PRIOR TO FABRICATION. SUBMIT THREE
COPIES WITH CONTRACTOR'S REVIEW STAMP. OWNER'S REPRESENTATIVE (GEI) SHOP DRAWING
REVIEW IS FOR GENERAL CONFORMANCE ONLY OF THE DESIGN CONCEPT AND CONTRACT
DOCUMENTS. OWNER'S REPRESENTATIVE (GEI) COMMENTS SHALL NOT BE CONSTRUED AS
RELIEVING THE CONTRACTOR FROM COMPLIANCE WITH THE PROJECT PLANS AND
SPECIFICATIONS. THE CONTRACTOR REMAINS RESPONSIBLE FOR DETAILS AND ACCURACY, FOR
CONFORMING AND CORRELATING ALL QUANTITIES AND DIMENSIONS AND FOR PERFORMING THE
WORK IN SAFE MANNER.
7. CONTRACTOR IS RESPONSIBLE FOR DEVELOPING AND IMPLEMENTING A SEQUENCE AND
SCHEDULE FOR COMPLETION OF THE WORK IN ACCORDANCE WITH APPLICABLE PROVISIONS OF
THE CONTRACT DOCUMENTS. THE CONTRACTOR SHALL SUBMIT THEIR WORK PLAN WHICH SHALL
INCLUDE THE PROPOSED SEQUENCE OF WORK.
8. ACCOMMODATIONS SHALL BE MADE FOR OWNER AND/OR THE OWNER'S REPRESENTATIVE FOR
INSPECTION, REVIEW, ETC. AT ANY POINT DURING CONSTRUCTION WITHOUT DELAY.
COORDINATION:
1. SCHEDULE, COORDINATE, AND PERFORM THE WORK TO MEET THE OVERALL PROJECT SCHEDULE
CONSTRAINTS.
2. COORDINATE WITH THE OWNER FOR DESIGNATION OF SPECIFIC WORK AREAS FOR RESTRICTED
ACCESS DURING PARTICULAR PERIODS OF THE WORK, AS WELL AS NEED FOR FENCING,
SIGNAGE, AND OTHER MEASURES NECESSARY TO PROTECT THE PUBLIC, COMPLETED WORK,
WORK IN PROGRESS, AND CONTRACTOR'S EQUIPMENT AND PROPERTY ON SITE.
3. MAINTAIN FULL AND COMPLETE ACCESS TO WORK TO OWNER, ENGINEER, AND REGULATORY
PERSONNEL.
PERMITTING AND ENVIRONMENTAL:
COMPLY WITH ALL REQUIREMENTS OF OWNER-OBTAINED PROJECT PERMITS. CONTRACTOR SHALL OBTAIN
ALL OTHER PERMITS NECESSARY FOR CONSTRUCTION OF THE WORK.
STEWARDSHIP / ARTIFACT NOTE:
IF ANY ARTIFACTS ARE DISCOVERED DURING THE CONSTRUCTION PROCESS, ALL WORK IS TO
STOP AND THE OWNER'S REPRESENTATIVE / PROJECT MANAGER SHALL BE NOTIFIED.
ARTIFACTS OR ARCHEOLOGICAL MATERIALS ARE DEFINED AS : ABORIGINAL ANTIQUITIES AND
OTHER RECORDS ON ANTIQUITY, INCLUDING MOUNDS, MINES, EARTHWORKS, VILLAGE SITES,
CAMP SITES, BURIALS, HUMAN OR OTHER BONES, SHELLS, STONE IMPLEMENTS, BONE OR
COPPER IMPLEMENTS, POTTERY OR SHARD OF POTTER, OR OTHER OBJECTS RELATING TO
NATIVE AMERICAN OCCUPATION; AND MODERN ARTIFACTS, SUCH AS FORTS, RELICS, AND
OTHER ARTIFACTS RELATING TO THE HISTORIC, COLONIAL, TERRITORIAL AND EARLY
STATEHOOD PERIODS.
OHL
X
U/E
LINETYPE LEGEND
TOPOGRAPHIC CONTOURS - MAJOR
TOPOGRAPHIC CONTOURS - MINOR
WATER SURFACE
PROPERTY BOUNDARY
EXISTING OVERHEAD LINES
CHAIN LINK FENCE
UNDERGROUND LINE
USACE NAVIGABLE CHANNEL
ACCESS ROUTE
LIMITS OF CONSTRUCTION
SILT FENCE
LOC
G-02
SF
© 2021 Microsoft Corporation © 2021 Maxar ©CNES (2021) Distribution Airbus DS
LOC
LO
C
LOC
LOC
LO
C
LOC
LOC
\\geiconsulta B:\Working\DTMB\1904013 Cheboygan Lock Facility - Repair and Reno\CAD\Design\Working\Dam Drawings\SITE ACCESS.dwg - 7/31/2023
MICHIGAN DEPARTMENT OF
TECHNOLOGY, MANAGEMENT AND
BUDGET
GEI Project 1904013
If this scale bar does not measure 1" then drawing is not original scale.
Attention: CHEBOYGAN DAM IMPROVEMENTS PROJECT
CHEBOYGAN, MI
GEI CONSULTANTS OF MICHIGAN, P.C.
109 W. BARAGA AVENUE
MARQUETTE, MI 49855
(906)451-4021
Consultants
0 1"
NO. DATE ISSUE/REVISION APP
A 8/24/2023 ISSUE FOR BID SAE
Designed:
Checked:
Drawn:
JEP
KAR
JEP
Approved By: SAE
SHEET NO.
DWG. NO.
OF 7
ISSUE FOR BID
SITE ACCESS PLAN
G-03
- SITE ACCESS
PLAN
UPSTREAM
ACCESS TO DAM
OVERPASS
CEC SUBSTATION
GREAT LAKES TISSUE (GLT) PROPERTY LINE
CEC PROPERTY LINE
SCALE, FEET
120 240
MICHIGAN STATE
WATERWAYS
PROPERTY LINE
CONSUMERS ENERGY (CEC) SUBSTATION
PROPERTY CONTACT: RON BOURGEOIS AT
517-740-8936
M-27
E.
L
IN
C
O
LN
A
VE
SOUTH ST.
CHEBOYGAN DAM
MAIN SPILLWAY
CONTRACTOR STAGING
AREA (CLOSED TO
PUBLIC) SEE NOTE 1
REMOVABLE SKID
DOCK (SEE NOTE 3)
OHLOHLOHL
GREAT LAKES TISSUE
POWER PLANT
PROJECT LOCATION:
PART OF THE W 1/2 OF THE SE 1/4 OF SECTION 31 IN T38N, R01W
CITY OF CHEBOYGAN
GENERAL NOTES:
1. UPSTREAM ACCESS CAN BE ACHIEVED THROUGH THE CHEBOYGAN LOCK DNR BOATING ACCESS SITE.
2. PROPERTY LINE INFORMATION GATHERED FROM CHEBOYGAN COUNTY ONLINE MAPPING SYSTEM
ACCESSED ON 11/9/2021.
3. THE MDNR WILL REMOVE THE SKID DOCK AT THE REQUEST OF THE CONTRACTOR AS NEEDED TO PROVIDE
ADDITIONAL SPACE FOR LAUNCHING BARGES AND EQUIPMENT.
4. IF ACCESSING FROM THE EAST THROUGH GLT PROPERTY, THERE EXISTS A HOPPER THAT LIMITS
OVERHEAD CLEARANCE TO 9' 6". THIS LIMITATION SHOULD BE CONSIDERED DURING ACCESS PLANNING.
5. VISUAL INSPECTION OF THE ACCESS BRIDGE IMMEDIATELY UPSTREAM OF THE GLT POWERHOUSE HAS
DETERMINED A MAXIMUM LOAD RATING FOR THE BRIDGE OF LIGHT DUTY CLASS 2A TRUCKS WITH A
MAXIMUM AXLE WEIGHT OF 4,000 LBS.
EXTENTS OF USACE
NAVIGABLE CHANNEL
EXTENTS OF USACE
NAVIGABLE CHANNEL
UPSTREAM ACCESS TO LOCK
VIA MDNR EASEMENT THROUGH
GREAT LAKES TISSUE
HOPPER
(SEE NOTE 4)
POWERHOUSE
ACCESS
BRIDGE (SEE
NOTE 5)
X
X
X
X
E E
LOC
LOC
LOC
LOC
LOC
LOC
LOC
LOC
LOC
LOC LOC
LOC
LOC
LO
C
LO
C
LO
C
LO
C
LO
C
LO
C
LO
C
LOC
LOC
LOC
LOC
LOC
LOC
LOC
LOC
LOC
LOC
SF
SF
SF
SF
CHEBOYGAN DAM
PLAN
SCALE, FEET
20100
SOIL EROSION AND SEDIMENT CONTROL PLAN
G-04
\\geiconsulta B:\Working\DTMB\1904013 Cheboygan Lock Facility - Repair and Reno\CAD\Design\Working\Dam Drawings\SOIL EROSION AND SEDIMENT CONTROL PLAN.dwg - 8/11/2023
MICHIGAN DEPARTMENT OF
TECHNOLOGY, MANAGEMENT AND
BUDGET
GEI Project 1904013
If this scale bar does not measure 1" then drawing is not original scale.
Attention: CHEBOYGAN DAM IMPROVEMENTS PROJECT
CHEBOYGAN, MI
GEI CONSULTANTS OF MICHIGAN, P.C.
109 W. BARAGA AVENUE
MARQUETTE, MI 49855
(906)451-4021
Consultants
0 1"
NO. DATE ISSUE/REVISION APP
A 08/XX/2023 ISSUE FOR BID SAE
Designed:
Checked:
Drawn:
JEP
KAR
JEP
Approved By: SAE
SHEET NO.
DWG. NO.
OF 7
ISSUE FOR BID
SILT FENCE (TYP)
INSTALLATION WITH TRENCHING
NOTES:
1. SILT FENCE SHALL BE PLACED ON SLOPE CONTOURS TO MAXIMIZE PONDING EFFICIENCY.
2. INSPECT AND REPAIR FENCE AFTER EACH STORM EVENT AND REMOVE SEDIMENT WHEN
NECESSARY. 9" (225mm) MAXIMUM RECOMMENDED STORAGE HEIGHT.
3. REMOVED SEDIMENT SHALL BE DEPOSITED TO AN AREA THAT WILL NOT CONTRIBUTE
SEDIMENT OFF-SITE AND CAN BE PERMANENTLY STABILIZED.
EXTRA STRENGTH FILTER
FABRIC NEEDED WITHOUT
WIRE MESH SUPPORT
STEEL OR WOOD POST
ATTACH FILTER FABRIC
SECURELY TO UPSTREAM
SIDE OF POST
10' (3m) MAXIMUM SPACING WITH WIRE SUPPORT FENCE 6' (1.8m)
MAXIMUM SPACING WITHOUT
WIRE SUPPORT FENCE
FLOW
PONDING HEIGHT
8" (200 mm)
3/4" (20mm) MIN
DRAIN ROCK
FLOW
12" MIN
(300 MM)
9" MAX
(225 mm)
STORAGE HT
PONDING HEIGHT
FLOW
INSTALLATION WITHOUT TRENCHING
STEEL OR WOOD
POST
36" (1M) HIGH MAX
12" MIN
(300 mm)
4"x6" (100x150mm)
TRENCH WITH
COMPACTED BACKFILL
SILT FENCE 2
SCALE: NTS
X
X X
E
F
E
580580
LOC
LOC LOC
LOC
LO
C
LOC
LOC
EXISTING SITE PLAN
20 40
SCALE:
1" = 20'
- OVERALL SITE
PLAN
NOTES:
1. EXISTING BASEMAP COMPILED FROM AERIAL IMAGERY OBTAINED FROM
GOOGLE EARTH (2008) OVERLAYED BY THE RESULTS OF A SITE SURVEY
CONDUCTED SEPTEMBER 23, 2019 BY GEI CONSULTANTS.
2. A TRIMBLE R6 GNSS SYSTEM GPS WAS USED FOR THE DATA COLLECTION
AND WAS SUPPLEMENTED WITH A SEAFLOOR HYDROLITE SINGLE BEAM ECHO
SOUNDER FOR THE BATHYMETRY MEASUREMENTS.
CHEBOYGAN RIVER
(EL. VARIES, 594.2' TO 590.2')
C-02
CHEBOYGAN DAM
GLT PROPERTY LINE
100 AMP ELECTRIC SERVICE
APPROXIMATE U/G
ELECTRICAL SERVICE
TO DAM GATES
(ACTUAL LOCATION
TO BE CONFIRMED
BY CONTRACTOR)
\\geiconsulta B:\Working\DTMB\1904013 Cheboygan Lock Facility - Repair and Reno\CAD\Design\Working\Dam Drawings\EXISTING SITE PLAN.dwg - 7/31/2023
MICHIGAN DEPARTMENT OF
TECHNOLOGY, MANAGEMENT AND
BUDGET
GEI Project 1904013
If this scale bar does not measure 1" then drawing is not original scale.
Attention: CHEBOYGAN DAM IMPROVEMENTS PROJECT
CHEBOYGAN, MI
GEI CONSULTANTS OF MICHIGAN, P.C.
109 W. BARAGA AVENUE
MARQUETTE, MI 49855
(906)451-4021
Consultants
0 1"
NO. DATE ISSUE/REVISION APP
A 8/24/2023 ISSUE FOR BID SAE
Designed:
Checked:
Drawn:
JEP
KAR
JEP
Approved By: SAE
SHEET NO.
DWG. NO.
OF 7
ISSUE FOR BID
EXTENTS OF USACE
NAVIGABLE CHANNEL
EXTENTS OF USACE
NAVIGABLE CHANNEL
C-01
CHEBOYGAN LOCK
POWERHOUSE
ACCESS BRIDGE
(SEE G-03 FOR
LIMITATIONS)
HOPPER (SEE G-03 FOR LIMITATIONS)
GREAT LAKES
TISSUE COMPANY
PLANT
DRAWBRIDGE
U/E U/E
EXISTING DAM GATE CONTROLS
SCALE: N.T.S.
- ORIGINAL GATE CONSTRUCTION SECTION AND ELEVATION
DETAIL 20 40
SCALE:
1" = 20'
C-01 CHEBOYGAN DAM
PLAN
GATE #6
GATE #5 GATE #4 GATE #3
GATE #2 GATE #1
FLOW
CHEBOYGAN DAM GATE
SCHEDULE
GATE NO. LENGTH HEIGHT
ESTIMATED
DEAD
WEIGHT
1 13' - 11 14" 6' - 0" 2600 LBS
2 13' - 11 14" 6' - 0" 2600 LBS
3 13' - 11 14" 6' - 0" 2600 LBS
4 15' - 4 34" 6' - 0" 3000 LBS
5 16' - 9 34" 6' - 0" 3200 LBS
6 12' - 4 14" 6' - 0" 2400 LBS
- DAM GATE HOIST OPERATION
EXISTING CONDITION PHOTOS
CHEBOYGAN RIVER
REMOVE GATE ACTUATOR (TYP)
REMOVE ACME SCREW (TYP)
REMOVE SHAFT AND COUPLER (TYP) REMOVE GATE ACTUATOR (TYP)
REMOVE ACME SCREW (TYP)
SCALE: N.T.S.
C-02 TYPICAL DAM GATE TO HOIST SCREW
CONNECTION
DETAIL
L 7"X4"X3/8"
L 7"X4"X3/8"
2" DIA. ACME SCREW
COLLAR5"X3/8" STIFFENER PL
SET SCREW
4"
SCALE: N.T.S.
C-02 TYPICAL DAM GATE TO HOIST SCREW
CONNECTION
DETAIL
LOCATION OF CONNECTION
APPROXIMATELY 7" BELOW TOP CHANNEL
L 7"X4"X3/8" LLH
L 7"X4"X3/8" LLH
5"X3/8" STIFFENER PL
SET SCREW
COLLAR
2" DIA. ACME SCREW
LOCATION OF CONNECTION
APPROXIMATELY 7" BELOW
TOP CHANNEL
C-02 3
C-02
C-02
E
E
E
EE
E
100 AMP ELECTRICAL SERVICE
(LOCATION APPROXIMATE)
ELECTRICAL OUTLETS (TYP)
NOTES:
1. NO STOPLOGS EXIST FOR DEWATERING DAM GATES.
2. CONTRACTOR SHALL SUFFICIENTLY BRACE GATE IN THE
CLOSED POSITION DURING REPLACEMENT OF GATE
ACTUATORS.
3. ONLY TWO (2) GATES MAY BE WORKED ON CONCURRENTLY.
THE ACTUATOR REPLACEMENTS SHALL BEGIN WITH GATES 1
AND 2. ONCE GATES 1 AND 2 PASS OPERATIONAL TESTING,
THE DEMO WORK ON GATES 3 AND 4 MAY BEGIN.
AC
M
E
SC
R
EW
~7 6"
(V
IF
, T
YP
A
LL
G
AT
ES
EXISTING OUTLET
SEE DETAIL 3 ON NEXT SHEET
EXISTING CONDUIT
SEE DETAIL 3 ON NEXT SHEET
EXISTING OUTLET
EXISTING CONDUIT
\\geiconsulta B:\Working\DTMB\1904013 Cheboygan Lock Facility - Repair and Reno\CAD\Design\Working\Dam Drawings\EXISTING DAM GATE CONTROLS.dwg - 10/25/2022
MICHIGAN DEPARTMENT OF
TECHNOLOGY, MANAGEMENT AND
BUDGET
GEI Project 1904013
If this scale bar does not measure 1" then drawing is not original scale.
Attention: CHEBOYGAN DAM IMPROVEMENTS PROJECT
CHEBOYGAN, MI
GEI CONSULTANTS OF MICHIGAN, P.C.
109 W. BARAGA AVENUE
MARQUETTE, MI 49855
(906)451-4021
Consultants
0 1"
NO. DATE ISSUE/REVISION APP
A 8/24/2023 ISSUE FOR BID SAE
Designed:
Checked:
Drawn:
JEP
KAR
JEP
Approved By: SAE
SHEET NO.
DWG. NO.
OF 7
ISSUE FOR BID
TYPICAL GATE SYSTEM LOOKING DOWSTREAM EXISTING HOIST SCREW CONNECTION
INCLUDING DEMOLITION NOTES
C-02
E E
E
E
E
E
\\geiconsulta B:\Working\DTMB\1904013 Cheboygan Lock Facility - Repair and Reno\CAD\Design\Working\Dam Drawings\PROPOSED DAM GATE CONTROLS.dwg - 7/31/2023
MICHIGAN DEPARTMENT OF
TECHNOLOGY, MANAGEMENT AND
BUDGET
GEI Project 1904013
If this scale bar does not measure 1" then drawing is not original scale.
Attention: CHEBOYGAN DAM IMPROVEMENTS PROJECT
CHEBOYGAN, MI
GEI CONSULTANTS OF MICHIGAN, P.C.
109 W. BARAGA AVENUE
MARQUETTE, MI 49855
(906)451-4021
Consultants
0 1"
NO. DATE ISSUE/REVISION APP
A 8/24/2023 ISSUE FOR BID SAE
Designed:
Checked:
Drawn:
JEP
KAR
JEP
Approved By: SAE
SHEET NO.
DWG. NO.
OF 7
ISSUE FOR BID
PROPOSED DAM GATE CONTROLS
20 40
SCALE:
1" = 20'
- TYPICAL DAM GATE
ELEVATION
REPLACE ACME SCREW (TYP)
REPLACE BEVEL GEAR
REPLACE DRIVE SHAFT AND COUPLER
REPLACE DRIVE BEVEL GEAR
NEW ELECTRICAL ACTUATOR
SHEET NOTES
1. PROPOSED GATE OPERATING SYSTEM SHALL BE MOUNTED TO EXISTING DOUBLE CHANNEL
SUPPORTS.
2. BEVEL GEARS, ACTUATORS, CONDUIT, SUPPORT FRAMING, ETC. SHALL NOT IMPEDE PUBLIC
ACCESS WALKWAY.
3. PROPOSED OPERATING SYSTEM SHALL ALLOW THE OWNER TO OPERATE EACH OF THE SIX
GATES WITH PUSH BUTTON CONTROLS LOCATED WITHIN A LOCKABLE BOX AT EACH ACTUATOR.
GATES ARE ANTICIPATED TO BE OPERATED ONE AT A TIME UNDER THE DIRECT OBSERVATION
OF THE OPERATOR.
4. ACTUATORS SHALL INCLUDE LOCKABLE MANUAL OVERRIDE HANDWHEEL/CRANK AT EACH GATE.
5. SYSTEM SHALL BE SUFFICIENT TO HOIST GATE UNDER FULL HYDROSTATIC PRESSURE. 10 KIP
SERVICE LOAD IS ASSUMED FOR EACH GATE PER PROJECT SPECIFICATIONS.
6. THE SYSTEM SHALL INCLUDE A POSITION LIMIT SWITCH TO REDUCE THE POTENTIAL OF
UNNECESSARY LOADS IMPOSED ON THE GATE DUE TO 'OVER-OPENING' OR 'OVER-CLOSING' OF
THE GATE.
7. CONTRACTOR SHALL MATE NEW ACME SCREW WITH EXISTING GATES AS SHOWN IN DETAIL 2
BELOW.
8. CONTRACTOR TO ADD 60A 240V FEEDER CIRCUIT FROM THE EXISTING SERVICE TO SUPPLY THE
ACTUATORS. SEE PANEL SCHEDULE AND NOTES BELOW.
A C-03
A C-03
20 40
SCALE:
1" = 20'
A
C-03 TYPICAL DAM GATE SCHEMATIC
SECTION
NEW ELECTRICAL ACTUATOR
REPLACE ACME SCREW (TYP)
REPLACE BEVEL GEAR
SCALE: N.T.S.
C-03 TYPICAL DAM GATE TO HOIST
SCREW CONNECTION
DETAIL
NEW ACME SCREW
REPLACE IN KIND
THREADED
COLLAR
SET BOLT
BOLT MOUNTING PLATE TO
EXISTING FRAME TO
ACCOMODATE NEW BEVEL
GEAR AND ACTUATOR
4"
8"
SCALE: N.T.S.
C-03 TYPICAL DAM GATE TO HOIST SCREW
CONNECTION
DETAIL
C-03
C-03
EXISTING BEAM IN
BACKGROUND
EXISTING
WALKWAY
EXISTING HANDRAIL
6"
BOLT SPACING
6" X 10 1/2"
HOIST SCREW SPACING
GATE NO. SCREW SPACING (VIF)
1 9'-7 1/2" 2 9'-11 1/2" 3 9'-11 1/2" 4 11'-4 3/4" 5 12'-9 3/4" 6 8'-4 1/2"
VARIES SEE TABLE
EXISTING
C12X20.7
3 1/2"
EXISTING
ELECTRICAL
OUTLET
EXISTING
CONDUIT
EXISTING OUTLET
EXISTING CONDUIT
DETAIL 3 BELOW
PROPOSED SERVICE
CONDUIT
EXISTING OUTLET
PROPOSED SERVICE
CONDUIT
20 40
SCALE:
1" = 20'
- CHEBOYGAN DAM
PLAN
GATE #6 GATE #5 GATE #4 GATE #3
GATE #2 GATE #1
FLOW
CHEBOYGAN RIVER
SEE NOTE 8
EXISTING ELECTRICAL OUTLETS
NEW CONDUIT FOR
GATE ACTUATORS
Dam 240/120 Panel Modifications
Rev Remarks Load
(VA)
Conductor Size
Type
Trip
CK
T # A B
CK
T
Type
Trip Conductor
Size Load (VA) Remarks Rev
0 SPILLWAY 2880
2 #10, #10
GND, 30A
1 A 2
20A 2 #12, #12
GND, 600 LIGHT 0
OUTLETS 3/4" C 1P 1P 3/4" C POLES
0 SIGN 600
2 #12, #12
GND, 20A
3 B 4
20A 2 #12, #12
GND, 600 TIME 0
LIGHTS 3/4" C 1P 1P 3/4" C CLOCK
0 US FISH 600
2 #12, #12
GND, 20A
5 A 6 60A 3 #6, #8 GND TBD DAM GATE
1& WILDLIFE 3/4" C 1P
7 B 8 2P 1" C TBD ACTUATORS
NOTES:
1. GATE ACTUATOR CIRCUIT TO INCLUDE 30A NEMA 4X STAINLESS STEEL FUSED DISCONNECT SWITCH (15A FUSES) FOR EACH ACTUATOR.
2. USE NEMA 4X STAINLESS STEEL J-BOXES IN FEEDER RUN TO ALLOW #12 AWG TAPS TO EACH DISCONNECT SWITCH (TAP RULES APPLY).
PROPOSED
CONDUIT SERVICE
C-03 file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt file:///G:/Blocks/GEI%20General/D_GEI-Section-Mark-FULL_Help.txt
| Sheets and Views |
| G-01 COVER SHEET |
| G-02 GENERAL NOTES AND LEGEND |
| G-03 SITE ACCESS PLAN |
| G-04 SOIL EROSION AND SEDIMENT CONTROL PLAN |
| C-01 EXISTING SITE PLAN |
| C-02 EXISTING DAM GATE CONTROLS |
| C-03 PROPOSED DAM GATE CONTROLS |