DRAWINGS 1.pdf

PDF 13 MB Posted

Attached to
26-022 TAXIWAY BRAVO WEST RELOCATION RICHARD B RUSSELL AIRPORT
Solicitation number
PE-65700-NONST-2026-000000093
Issued by
Fayette County, Georgia

About this file

This is a technical drawings document for Floyd County, Georgia's Taxiway Bravo West Relocation project at Richard B. Russell Regional Airport in Rome, Georgia. The project encompasses comprehensive runway and taxiway reconstruction involving 80 line items across multiple construction phases totaling 240 days. Key bid items include full depth pavement milling (31,000 sq. yards), unclassified excavation (40,700 cu. yards), crushed aggregate base course (8,000 cu. yards), storm drain pipe installation (24-inch RCP, 3,400 linear feet), catch basin construction (18 each), electrical duct bank installation with various PVC configurations (multiple linear feet), taxiway edge lighting (77 stake-mounted and 45 base-mounted L-861T lights), guidance sign relocation and installation (multiple modules), pavement markings in various colors and applications (multiple square footage quantities), and asphaltic concrete placement (2,400 tons of 12.5MM and 3,300 tons of 19MM Superpave). The project includes two additive alternatives with reduced quantities of similar materials. Construction is phased across five phases with specific operational restrictions: Phase 1 (170 days) involves Taxiway Bravo West work with Runway 7-25 closed and Runway 1-19 open; Phase 2 (30 days) addresses Taxiway Alpha and Bravo intersection work with both runways operational; Phase 3 (10 days) covers Taxiway Bravo work within Runway 1-19 RSA with Runway 1-19 closed; Phase 4 (15 days) addresses taxilane connectors with both runways open; and Phase 5 (15 days) includes final pavement marking and erosion control removal with both runways operational.

Contractors must maintain maximum equipment heights of 35 feet above ground level and provide 72-hour advance notice to airport management for NOTAM issuance. The project includes critical utility coordination requirements, with contractors responsible for determining actual locations of all underground utilities and obtaining detailed information from respective utility companies. Emergency procedures require immediate notification to utility companies and the engineer in the event of unexpected utility interference, with restoration costs borne by the contractor at no additional contract expense. Environmental controls include temporary seeding and mulching (32 acres), silt fence installation and maintenance (2,100 linear feet), temporary erosion control matting (20,000 sq. yards), permanent erosion control matting (20,000 sq. yards), temporary sediment pond construction and maintenance, and water quality inspections and monitoring over 7 months. The drawings also detail construction entrance specifications, runway and taxiway closure markers with flashing light capability, and flag line and barricade details. Total project scope spans 81 sheets with comprehensive electrical, drainage, pavement, and lighting components requiring coordination across multiple trades and strict adherence to airport operational requirements.

View the file

Other files

File Type Posted
DRAWINGS 2.pdf PDF
Bid 26_022 Richard B_ Russell Taxiway Bravo W.pdf PDF
DRAWINGS 3.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DROP INLET

43.2"X60"

TOP= 639.77

INV= 636.61

12" RCP12" RCP

DROP INLET

55.2"X60"

TOP= 637.96

INV= 628.8912" RCP

INV= 633.41

12" RCP

INV= 629.32

15" RCP

DROP INLET

26"X33"

TOP= 637.38

INV= 631.4312" RCP

INV= 631.43

12" RCP

INV= 631.49

DROP INLET

26"X33"

TOP= 636.30

INV= 632.59

12" RCP

DROP INLET

26"X33"

TOP= 635.30

INV= 631.49

12" RCP

INV= 632.33

" R

CP

DROP INLET

26"X32"

TOP= 634.59

INV= 629.82

12" RCP

INV= 629.94

" R

CP

DROP INLET

44"X44"

TOP= 632.87

INV= 628.56

18" RCP

DROP INLET

44"X44"

TOP= 632.29

INV= 627.82

18" RCP

INV= 627.91

THE LOCATION, SIZE AND TYPE OF MATERIAL OF EXISTING UNDERGROUND

UTILITIES INDICATED ON THE PLANS IS NOT REPRESENTED AS BEING

ACCURATE, SUFFICIENT OR COMPLETE. IT SHALL BE THE CONTRACTOR'S

RESPONSIBILITY TO DETERMINE THE ACTUAL LOCATION OF ALL SUCH

FACILITIES, INCLUDING SERVICE CONNECTIONS TO UNDERGROUND

UTILITIES. PRIOR TO CONSTRUCTION, THE CONTRACTOR SHALL NOTIFY

THE UTILITY COMPANIES OF HIS OPERATIONAL PLANS AND SHALL OBTAIN

FROM THE RESPECTIVE UTILITY COMPANIES DETAILED INFORMATION AND

ASSISTANCE RELATIVE TO THE LOCATION OF THEIR FACILITIES AND THE

WORKING SCHEDULE OF THE COMPANIES FOR REMOVAL OR ADJUSTMENT

WHERE REQUIRED. IN THE EVENT AN UNEXPECTED UTILITY INTERFERENCE

IS ENCOUNTERED DURING CONSTRUCTION, THE CONTRACTOR SHALL

IMMEDIATELY NOTIFY THE UTILITY COMPANY OF JURISDICTION. THE

ENGINEER SHALL ALSO BE IMMEDIATELY NOTIFIED. ANY SUCH MAINS AND

SERVICES SHALL BE RESTORED TO SERVICE AT ONCE AND PAID FOR BY

THE CONTRACTOR AT NO ADDITIONAL COST TO THE CONTRACT.

COMMON GROUND ALLIANCE

www.call811.com or Phone: 811

CALL 911 IN THE EVENT IN WHICH DAMAGE

RESULTS IN THE RELEASE OF NATURAL GAS.

TOTAL SHEETS: 81

DROP INLET

43.2"X60"

TOP= 639.77.77

INV= 636V= 636.61

12" RCP

12" R

12" RCP

12" RCP

DROP INLET

55.2"X60"

TOP= 637.96

INV= 628.898912" RCP

12" RCP

15" RCP

DROP INLET

26"X33"

TOP= 637.38

INV= 631.4312" RCP

12" RCP

INV= 631.49

DROP INLET

26"X33"

TOP= 636.30

INV= 632.59INV

12" RCP

12" RCP

DROP INLET

26"X33"

TOP= 635.30

INV= 631.49

12" RCP

INV= 632.33

" R

CP

" R

CP

DROP INLETD

26"X32"

TOP= 634.59

INV= 629.82

12" RCP

INV= 629.94

" R

CP

" R

CP

DROP INLETLET

44"X444"X44"

= 632.8TOP= 632

INV= 628.56INV

RRR

DROP INLET

44"X44"

TOP= 632.29

INV= 627.82

18" RCP

INV= 627.91

BASE BID

ITEM SPEC ITEM

NO NO. DESCRIPTION UNIT PLAN FINAL

1 C-100-14.01 CONTRACTOR QUALITY CONTROL PROGRAM (CQCP) L. SUM 1

2 C-102-5.01 TEMPORARY SEEDING AND MULCHING ACRE 32

3 C-102-5.02 INSTALLATION AND REMOVAL OF SILT FENCE LIN. FT. 2,100

4 C-102-5.03 MAINTENANCE OF SILT FENCE LIN. FT. 2,100

5 C-105-6.01 MOBILIZATION L. SUM 1

6 P-101-5.01 FULL DEPTH PAVEMENT MILLING SQ. YD. 31,000

7 P-101-5.02 DRAINAGE STRUCTURE REMOVAL EACH 11

8 P-101-5.03 PIPE REMOVAL LIN. FT. 1,700

9 P-152-4.01 UNCLASSIFIED EXCAVATION CU. YD. 40,700

10 P-152-4.02 ROCK EXCAVATION CU. YD. 2,000

11 P-152-4.03 UNSUITABLE EXCAVATION CU. YD. 3,000

12 P-155-8.01 LIME-TREATED SUBGRADE SQ. YD. 5,000

13 P-155-8.02 LIME TON 80

14 P-209-5.01 CRUSHED AGGREGATE BASE COURSE CU. YD. 8,000

15 P-209-5.02 SEPARATION GEOTEXTILE SQ. YD. 2,000

16 P-602-5.01 EMULSIFIED ASPHALT PRIME COAT GAL 6,200

17 P-603-5.01 EMULSIFIED ASPHALT TACK COAT GAL 1,600

18 P-605-5.01 SAWCUT AND SEAL PAVEMENT JOINT LIN. FT. 900

19 P-620-5.01 PAVEMENT MARKING, WHITE, REFLECTIVE, FULL RATE APPLICATION,

WITH MICROBICIDE SQ. FT. 300

20 P-620-5.02 PAVEMENT MARKING, YELLOW, NON-REFLECTIVE, HALF RATE

APPLICATION SQ. FT. 4,500

21 P-620-5.03 PAVEMENT MARKING, YELLOW, REFLECTIVE, FULL RATE

APPLICATION, WITH MICROBICIDE SQ. FT. 4,500

22 P-620-5.04 PAVEMENT MARKING, BLACK, NON-REFLECTIVE, FULL RATE

APPLICATION SQ. FT. 7,600

23 P-620-5.05 PAVEMENT MARKING REMOVAL SQ. FT. 1,300

24 D-699-5.01 CONSTRUCTION OF TEMPORARY SEDIMENT POND EACH 1

25 D-699-5.02 MAINTENANCE OF TEMPORARY SEDIMENT POND EACH 1

26 D-699-5.03 CLEANUP & FINAL STABILIZATION OF POND EACH 1

27 D-700-4.01 STONE RETROFITTING EACH 1

28 D-701-5.01 24" RCP STORM DRAIN PIPE, CLASS III LIN. FT. 3,400

29 D-701-5.02 TRENCHING FOR STORM DRAIN PIPE AND BACKFILL IN SOIL LIN. FT. 2,300

30 D-701-5.03 TRENCHING FOR STORM DRAIN PIPE AND BACKFILL IN ROCK LIN. FT. 1,100

31 D-751-5.01 CATCH BASINS EACH 18

32 D-751-5.02 CONSTRUCTION OF POND OUTLET STRUCTURE/PIPING EACH 1

33 D-753-5.01 RIP RAP TON 50

34 D-753-5.02 ROCK FILTER DAM EACH 1

35 D-753-5.03 CHECK DAM EACH 20

36 E-891-5.01 INLET PROTECTION EACH 20

37 E-895-5.01 TEMPORARY EROSION CONTROL MATTING SQ. YD. 20,000

38 E-895-5.02 PERMANENT EROSION CONTROL MATTING SQ. YD. 20,000

39 T-901-5.01 SEEDING ACRE 32

40 T-905-5.01 TOPSOIL (OBTAINED ON SITE OR REMOVED FROM STOCKPILE) CU. YD. 14,900

41 T-908-5.01 MULCHING ACRE 32

42 L-108-5.01 REMOVE EXISTING CABLE IN UNIT DUCT, CONDUIT, OR TRENCH LIN. FT. 3,800 43 L-108-5.02 TRENCHING FOR DIRECT BURIED CABLE AND BACKFILL IN SOIL LIN. FT. 7,900 44 L-108-5.03 TRENCHING FOR DIRECT BURIED CABLE AND BACKFILL IN ROCK LIN. FT. 2,400

45 L-108-5.04 NO. 8 AWD 5 KV, L-824, TYPE C CABLE, INSTALLED IN TRENCH, DUCT

BANK OR CONDUIT LIN. FT. 13,700

46 L-108-5.05

NO. 6 AWG, SOLID, BARE COPPER COUNTERPOISE WIRE, INSTALLED

IN TRENCH, INCLUDING GROUND RODS,

CONNECTIONS/TERMINATIONS

LIN. FT. 7,900

47 L-108-5.06 2#6 XLP-USE, 1#8 GND INSTALLED IN TRENCH LIN. FT. 300

48 L-108-5.07 NO. 8 AWG, 600V, TYPE THWN CABLE INSTALLED IN TRENCH, DUCT

BANK, OR CONDUIT LIN. FT. 500

49 L-109-7.01 AIRFIELD VAULT MODIFICATIONS L. SUM 1

50 L-109-7.02 NEW 7.5KW REGULATOR, INSTALLED, COMPLETE (TAXIWAY B) EACH 1

51 L-110-5.01 CONCRETE ENCASED ELECTRICAL DUCT BANK 1-2" SCHEDULE 40

PVC LIN. FT. 500

52 L-110-5.02 CONCRETE ENCASED ELECTRICAL DUCT BANK 2-2" SCHEDULE 40

PVC LIN. FT. 400

53 L-110-5.03 CONCRETE ENCASED ELECTRICAL DUCT BANK 3-2" SCHEDULE 40

PVC LIN. FT. 300

54 L-110-5.04 CONCRETE ENCASED ELECTRICAL DUCT BANK 4-2" SCHEDULE 40

PVC LIN. FT. 200

55 L-110-5.05 NON-ENCASED ELECTRICAL CONDUIT 1-2" SCHEDULE 40 PVC LIN. FT. 8,000

56 L-110-5.06 REMOVE CONDUIT LIN. FT. 3,800

57 L-110-5.07 CLEAR EXISTING CONDUIT LIN. FT. 400

58 L-110-5.08 EXTEND CONCRETE ENCASED ELECTRICAL DUCT BANK 2-2"

SCHEDULE 40 PVC LIN. FT. 40

59 L-115-5.01 2-CAN JUNCTION CAN PLAZA, INSTALLED, COMPLETE EACH 2

60 L-115-5.02 SPLICE CAN, INSTALLED, COMPLETE EACH 5

61 L-115-5.03 REMOVE OR RELOCATE EXISTING ELECTRICAL HANDHOLES,

INSTALLED, COMPLETE EACH 2

62 L-115-5.04 REMOVE OR RELOCATE EXISTING ELECTRICAL SPLICE CAN,

INSTALLED, COMPLETE EACH 2

63 L-115-5.05 EXISTING ELECTRICAL JUNCTION STRUCTURE ELEVATION

ADJUSTMENT EACH 4

64 L-115-5.06 3-CAN JUNCTION CAN PLAZA, INSTALLED, COMPLETE EACH 2

65 L-125-5.01 L-861T(L) TAXIWAY STAKE MOUNTED EDGE LIGHT, INSTALLED,

COMPLETE EACH 77

66 L-125-5.02 L-861T(L) TAXIWAY BASE MOUNTED EDGE LIGHT, INSTALLED,

COMPLETE EACH 45

67 L-125-5.03 RELOCATE GUIDANCE SIGN, 1 MODULE ON NEW FOUNDATION,

INSTALLED, COMPLETE EACH 1

68 L-125-5.04 RELOCATE GUIDANCE SIGN, 2 MODULE ON NEW FOUNDATION,

INSTALLED, COMPLETE EACH 1

69 L-125-5.05 RELOCATE GUIDANCE SIGN, 3 MODULE ON NEW FOUNDATION,

INSTALLED, COMPLETE EACH 4

70 L-125-5.06 NEW GUIDANCE SIGN, 3 MODULE ON NEW FOUNDATION, INSTALLED,

COMPLETE EACH 2

71 L-125-5.07 L-853 TYPE II RETROREFLECTIVE MARKERS, INSTALLED, COMPLETE EACH 18

72 L-125-5.08 REMOVE AND REINSTALL L-850C, HIGH INTENSITY RUNWAY EDGE

LIGHT, IN-PAVEMENT, INSTALLED, COMPLETE EACH 1

73 L-125-5.09 REMOVE ELEVATED LIGHT EACH 46

74 L-125-5.10 REMOVE GUIDANCE SIGN FOUNDATION EACH 7

75 L-125-5.11 REMOVE AND REPLACE GUIDANCE SIGN ISOLATION TRANSFORMER EACH 7

76 L-125-5.12 UPGRADE STAKE MOUNTED L-861T(L) EDGE LIGHTS TO BASE

MOUNTED EACH 77

77 GDOT 167-5.01 WATER QUALITY INSPECTIONS MONTH 7

78 GDOT 167-5.02 WATER QUALITY MONITORING AND SAMPLING EACH 7

79 GDOT-402-5.01

RECYLCLED ASPHALTIC CONCRETE 12.5MM SUPERPAVE,

GROUP-BLEND, INCLUDING POLYMER-MODIFIED BITUMINOUS

MATERIALS AND HYDRATED LIME

TON 2,400

80 GDOT-402-5.02

RECYLCLED ASPHALTIC CONCRETE 19MM SUPERPAVE,

GROUP-BLEND, INCLUDING POLYMER-MODIFIED BITUMINOUS

MATERIALS AND HYDRATED LIME

TON 3,300

ADDITIVE ALTERNATIVE 1

ITEM SPEC ITEM

NO NO. DESCRIPTION UNIT PLAN FINAL

1 P-209-5.01 CRUSHED AGGREGATE BASE COURSE CU. YD. 500

2 P-602-5.01 EMULSIFIED ASPHALT PRIME COAT GAL 800

3 P-603-5.01 EMULSIFIED ASPHALT TACK COAT GAL 200

4 P-620-5.02 PAVEMENT MARKING, YELLOW, NON-REFLECTIVE, HALF RATE

APPLICATION SQ. FT. 500

5 P-620-5.03 PAVEMENT MARKING, YELLOW, REFLECTIVE, FULL RATE

APPLICATION, WITH MICROBICIDE SQ. FT. 500

6 P-620-5.04 PAVEMENT MARKING, BLACK, NON-REFLECTIVE, FULL RATE

APPLICATION SQ. FT. 1,000

7 L-125-5.07 L-853 TYPE II RETROREFLECTIVE MARKERS, INSTALLED,

COMPLETE EACH 18

8 GDOT-402-5.01

RECYLCLED ASPHALTIC CONCRETE 12.5MM SUPERPAVE,

GROUP-BLEND, INCLUDING POLYMER-MODIFIED BITUMINOUS

MATERIALS AND HYDRATED LIME

TON 300

9 GDOT-402-5.02

RECYLCLED ASPHALTIC CONCRETE 19MM SUPERPAVE,

GROUP-BLEND, INCLUDING POLYMER-MODIFIED BITUMINOUS

MATERIALS AND HYDRATED LIME

TON 300

ADDITIVE ALTERNATIVE 2

ITEM SPEC ITEM

NO NO. DESCRIPTION UNIT PLAN FINAL

1 P-209-5.01 CRUSHED AGGREGATE BASE COURSE CU. YD. 400

2 P-602-5.01 EMULSIFIED ASPHALT PRIME COAT GAL 400

3 P-603-5.01 EMULSIFIED ASPHALT TACK COAT GAL 100

4 P-620-5.02 PAVEMENT MARKING, YELLOW, NON-REFLECTIVE, HALF RATE

APPLICATION SQ. FT. 200

5 P-620-5.03 PAVEMENT MARKING, YELLOW, REFLECTIVE, FULL RATE

APPLICATION, WITH MICROBICIDE SQ. FT. 200

6 P-620-5.04 PAVEMENT MARKING, BLACK, NON-REFLECTIVE, FULL RATE

APPLICATION SQ. FT. 300

7 L-125-5.07 L-853 TYPE II RETROREFLECTIVE MARKERS, INSTALLED, COMPLETE EACH 6

8 GDOT-402-5.01

RECYLCLED ASPHALTIC CONCRETE 12.5MM SUPERPAVE,

GROUP-BLEND, INCLUDING POLYMER-MODIFIED BITUMINOUS

MATERIALS AND HYDRATED LIME

TON 200

9 GDOT-402-5.02

RECYLCLED ASPHALTIC CONCRETE 19MM SUPERPAVE,

GROUP-BLEND, INCLUDING POLYMER-MODIFIED BITUMINOUS

MATERIALS AND HYDRATED LIME

TON 200

L3

TAXIWAY B NEW

L4

TAXIWAY B NEW

L5

TAXIWAY B NEW

L6

TAXIWAY B NEW

L7

L1

RUNWAY 7-25

L2

RUNWAY 1-19

L4

TAXIWAY B NEW

L5

TAXIWAY B NEW

L6

TAXIWAY B NEW

L4

TAXIWAY B NEW

L5

TAXIWAY B NEW

L6

TAXIWAY B NEW

PHASE CONSTRUCTION AFFECTED OPERATIONS

AREAS WORK HOURS SAFETY AND SECURITY

CONSTRUCTION

TIME (DAYS)

MOBILIZATION, EROSION CONTROL

SETUP, TAXIWAY BRAVO WEST

PAVEMENT REMOVAL, GRADING,

PAVEMENT CONSTRUCTION, LIGHTING

INSTALLATION.

RUNWAY 7-25 CLOSED

RUNWAY 1-19 OPEN

NORMAL /

UNRESTRICTED

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

TAXIWAY ALPHA AND BRAVO

INTERSECTION PAVEMENT REMOVAL,

GRADING, LIGHTING INSTALLATION &

REMOVAL, AND TEMPORARY MARKING.

RUNWAY 7-25 OPEN

RUNWAY 1-19 OPEN

NORMAL /

UNRESTRICTED

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

TAXIWAY BRAVO PAVEMENT REMOVAL,

GRADING, PAVEMENT CONSTRUCTION,

LIGHTING INSTALLATION & REMOVAL,

AND TEMPORARY MARKING WITHIN

RUNWAY 1-19 RSA.

RUNWAY 7-25 OPEN

RUNWAY 1-19 CLOSED

NORMAL /

UNRESTRICTED

INCLUDING THE

WEEKEND

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

TAXILANE CONNECTORS TO BRAVO

WEST PAVEMENT REMOVAL,

GRADING, PAVEMENT

CONSTRUCTION, AND TEMPORARY

MARKING.

RUNWAY 7-25 OPEN

RUNWAY 1-19 OPEN

NORMAL /

UNRESTRICTED

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

FULL RATE PAVEMENT MARKING

(30 DAYS AFTER ASPHALT PAVING),

FINAL GRASSING, REMOVE

TEMPORARY EROSION CONTROL

DEMOBILIZATION.

RUNWAY 7-25 OPEN

RUNWAY 1-19 OPEN

NORMAL /

UNRESTRICTED

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

TOTAL CONSTRUCTION TIME: 240

L4

TAXIWAY B NEW

L5

TAXIWAY B NEW

L6

TAXIWAY B NEW

TAXIWAY A

TAXIWAY B

TAXILANE

PHASE CONSTRUCTION AFFECTED OPERATIONS

AREAS WORK HOURS SAFETY AND SECURITY

CONSTRUCTION

TIME (DAYS)

MOBILIZATION, EROSION CONTROL

SETUP, TAXIWAY BRAVO WEST

PAVEMENT REMOVAL, GRADING,

PAVEMENT CONSTRUCTION, LIGHTING

INSTALLATION.

RUNWAY 7-25 CLOSED

RUNWAY 1-19 OPEN

NORMAL /

UNRESTRICTED

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

TAXIWAY ALPHA AND BRAVO

INTERSECTION PAVEMENT REMOVAL,

GRADING, LIGHTING INSTALLATION &

REMOVAL, AND TEMPORARY MARKING.

RUNWAY 7-25 OPEN

RUNWAY 1-19 OPEN

NORMAL /

UNRESTRICTED

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

TAXIWAY BRAVO PAVEMENT REMOVAL,

GRADING, PAVEMENT CONSTRUCTION,

LIGHTING INSTALLATION & REMOVAL,

AND TEMPORARY MARKING WITHIN

RUNWAY 1-19 RSA.

RUNWAY 7-25 OPEN

RUNWAY 1-19 CLOSED

NORMAL /

UNRESTRICTED

INCLUDING THE

WEEKEND

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

TAXILANE CONNECTORS TO BRAVO

WEST PAVEMENT REMOVAL,

GRADING, PAVEMENT

CONSTRUCTION, AND TEMPORARY

MARKING.

RUNWAY 7-25 OPEN

RUNWAY 1-19 OPEN

NORMAL /

UNRESTRICTED

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

FULL RATE PAVEMENT MARKING

(30 DAYS AFTER ASPHALT PAVING),

FINAL GRASSING, REMOVE

TEMPORARY EROSION CONTROL

DEMOBILIZATION.

RUNWAY 7-25 OPEN

RUNWAY 1-19 OPEN

NORMAL /

UNRESTRICTED

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

L4

TAXIWAY B NEW

L5

TAXIWAY B NEW

L6

TAXIWAY B NEW

TAXIWAY A

TAXIWAY B

TAXILANE

CONSTRUCTION

TIME (DAYS)

MOBILIZATION, EROSION CONTROL

SETUP, TAXIWAY BRAVO WEST

PAVEMENT REMOVAL, GRADING,

PAVEMENT CONSTRUCTION, LIGHTING

INSTALLATION.

RUNWAY 7-25 CLOSED

RUNWAY 1-19 OPEN

NORMAL /

UNRESTRICTED

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

TAXIWAY ALPHA AND BRAVO

INTERSECTION PAVEMENT REMOVAL,

GRADING, LIGHTING INSTALLATION &

REMOVAL, AND TEMPORARY MARKING.

RUNWAY 7-25 OPEN

RUNWAY 1-19 OPEN

NORMAL /

UNRESTRICTED

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

TAXIWAY BRAVO PAVEMENT REMOVAL,

GRADING, PAVEMENT CONSTRUCTION,

LIGHTING INSTALLATION & REMOVAL,

AND TEMPORARY MARKING WITHIN

RUNWAY 1-19 RSA.

RUNWAY 7-25 OPEN

RUNWAY 1-19 CLOSED

NORMAL /

UNRESTRICTED

INCLUDING THE

WEEKEND

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

TAXILANE CONNECTORS TO BRAVO

WEST PAVEMENT REMOVAL,

GRADING, PAVEMENT

CONSTRUCTION, AND TEMPORARY

MARKING.

RUNWAY 7-25 OPEN

RUNWAY 1-19 OPEN

NORMAL /

UNRESTRICTED

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

FULL RATE PAVEMENT MARKING

(30 DAYS AFTER ASPHALT PAVING),

FINAL GRASSING, REMOVE

TEMPORARY EROSION CONTROL

DEMOBILIZATION.

RUNWAY 7-25 OPEN

RUNWAY 1-19 OPEN

NORMAL /

UNRESTRICTED

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

L4

TAXIWAY B NEW

L5

TAXIWAY B NEW

L6

TAXIWAY B NEW

TAXIWAY A

CONSTRUCTION

TIME (DAYS)

MOBILIZATION, EROSION CONTROL

SETUP, TAXIWAY BRAVO WEST

PAVEMENT REMOVAL, GRADING,

PAVEMENT CONSTRUCTION, LIGHTING

INSTALLATION.

RUNWAY 7-25 CLOSED

RUNWAY 1-19 OPEN

NORMAL /

UNRESTRICTED

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

TAXIWAY ALPHA AND BRAVO

INTERSECTION PAVEMENT REMOVAL,

GRADING, LIGHTING INSTALLATION &

REMOVAL, AND TEMPORARY MARKING.

RUNWAY 7-25 OPEN

RUNWAY 1-19 OPEN

NORMAL /

UNRESTRICTED

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

TAXIWAY BRAVO PAVEMENT REMOVAL,

GRADING, PAVEMENT CONSTRUCTION,

LIGHTING INSTALLATION & REMOVAL,

AND TEMPORARY MARKING WITHIN

RUNWAY 1-19 RSA.

RUNWAY 7-25 OPEN

RUNWAY 1-19 CLOSED

NORMAL /

UNRESTRICTED

INCLUDING THE

WEEKEND

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

TAXILANE CONNECTORS TO BRAVO

WEST PAVEMENT REMOVAL,

GRADING, PAVEMENT

CONSTRUCTION, AND TEMPORARY

MARKING.

RUNWAY 7-25 OPEN

RUNWAY 1-19 OPEN

NORMAL /

UNRESTRICTED

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

FULL RATE PAVEMENT MARKING

(30 DAYS AFTER ASPHALT PAVING),

FINAL GRASSING, REMOVE

TEMPORARY EROSION CONTROL

DEMOBILIZATION.

RUNWAY 7-25 OPEN

RUNWAY 1-19 OPEN

NORMAL /

UNRESTRICTED

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

L4

TAXIWAY B NEW

L5

TAXIWAY B NEW

L6

TAXIWAY B NEW

TAXIWAY A

CONSTRUCTION

TIME (DAYS)

MOBILIZATION, EROSION CONTROL

SETUP, TAXIWAY BRAVO WEST

PAVEMENT REMOVAL, GRADING,

PAVEMENT CONSTRUCTION, LIGHTING

INSTALLATION.

RUNWAY 7-25 CLOSED

RUNWAY 1-19 OPEN

NORMAL /

UNRESTRICTED

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

TAXIWAY ALPHA AND BRAVO

INTERSECTION PAVEMENT REMOVAL,

GRADING, LIGHTING INSTALLATION &

REMOVAL, AND TEMPORARY MARKING.

RUNWAY 7-25 OPEN

RUNWAY 1-19 OPEN

NORMAL /

UNRESTRICTED

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

TAXIWAY BRAVO PAVEMENT REMOVAL,

GRADING, PAVEMENT CONSTRUCTION,

LIGHTING INSTALLATION & REMOVAL,

AND TEMPORARY MARKING WITHIN

RUNWAY 1-19 RSA.

RUNWAY 7-25 OPEN

RUNWAY 1-19 CLOSED

NORMAL /

UNRESTRICTED

INCLUDING THE

WEEKEND

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

TAXILANE CONNECTORS TO BRAVO

WEST PAVEMENT REMOVAL,

GRADING, PAVEMENT

CONSTRUCTION, AND TEMPORARY

MARKING.

RUNWAY 7-25 OPEN

RUNWAY 1-19 OPEN

NORMAL /

UNRESTRICTED

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

FULL RATE PAVEMENT MARKING

(30 DAYS AFTER ASPHALT PAVING),

FINAL GRASSING, REMOVE

TEMPORARY EROSION CONTROL

DEMOBILIZATION.

RUNWAY 7-25 OPEN

RUNWAY 1-19 OPEN

NORMAL /

UNRESTRICTED

PLACE BARRICADES AND CLOSURE MARKERS AS

SHOWN. THE CONTRACTOR SHALL NOTIFY THE

AIRPORT AT LEAST 72 HOURS IN ADVANCE OF WORK

SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A

NOTAM OF CONSTRUCTION. THE MAXIMUM EQUIPMENT

HEIGHT IS 35' AGL.

FLASHING LIGHT (ALL LIGHTS

SHALL HAVE THE ABILITY TO BE

STEADY BURNING AND FLASHING)

TRAILER MOUNTED

CLOSURE CROSS

AVIATION YELLOW

POWER SUPPLY

EXIT DIAGRAM

ENTRANCE ELEVATION

TAXIWAY CLOSURE MARKER3 NOT TO SCALE

LIGHTED RUNWAY CLOSURE MARKER2 NOT TO SCALE

CONSTRUCTION ENTRANCE DETAIL6 NOT TO SCALE

LOW-LEVEL LIGHTED BARRICADE DETAIL1 NOT TO SCALE

FLAG LINE DETAIL5 NOT TO SCALE

EQUIPMENT & VEHICLE SIGNAL FLAG4 NOT TO SCALE

File details come from the government source that posted it. Updated .