This document is a set of mechanical design and demolition plans for an HVAC replacement project at the U.S. Naval Air Weapons Station in China Lake, California. The project scope involves replacing the existing HVAC unit (evaporative cooling and heating) in Building 20279's elevator mechanical room with a new packaged air-to-air heat pump, meeting UFC 3-490-26 requirements. The drawings include detailed mechanical plans, roof plans, and installation details, specifying galvanized steel double-wall ductwork with fiberglass insulation, a heat pump with 50.74 MBH cooling capacity, and specific installation requirements for duct supports, penetrations, and electrical connections. The project involves removing the existing mechanical system, installing new equipment, and ensuring proper configuration and performance according to military engineering standards.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Q and A 1.pdf | ||
| Solicitation Amendment - N6893626Q50200001.pdf | ||
| Updated SOW.pdf | ||
| Wage Determination.pdf | ||
| N6893626Q5020.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N
W E
S
PROJECT LOCATION
SCALE IN MILES
20100 *
* OLANCHA
TRONA
ISABELLA
TEHACHAPI
MOJAVE
LANCASTER
LOS
ANGELES
SAN
BERNARDINO
BARSTOW
BAKERSFIELD
CHINA LAKE
RIDGECREST
INYOKERN
395 15
U.S. NAVAL
AIR WEAPONS
STATION
U. S. N.
RANDSBURG
WASH
CR CR
IS
S
U E
D F
O R
S
TA
TI
O
N R
E
VI
E W
/1
3/
E
LE
V A
TO
R
M A
C H
IN
E
R M
. A /C
R E
P
LA
C E
M E
N T
N A
V A
L A
IR
W
E A
P O
N S
C E
N
TE
R
W E
A P
O N
S D
IV
IS
IO
N
IS
S
U E
D F
O R
C O
N S
TR
U
C
TI
O N
/2
4/
SIZING CONDENSERS AND CONDENSING UNITS, ADD 5°F TO
THE OUTDOOR DB TEMPERATURE.
SUMMER
106°F DB 66°F WB
WINTER
23°F DB
SUMMER/WINTER
70°F-90°F DB 35%-60% RH
WINTER
68°F DB
OUTSIDE DESIGN CONDITIONS
ELEVATOR MR DESIGN CONDITIONS
APPLICABLE CODES
ALL WORK SHALL BE IN ACCORDANCE WITH THE LATEST REVISION/EDITION OF
THE FOLLOWING REFERENCED CODES AND STANDARDS.
NFPA 70 NATIONAL ELECTRIC CODE
NFPA 90A STANDARD FOR INSTALLATION OF AIR CONDITIONING
AND VENTILATION SYSTEM
NFPA 101 LIFE SAFETY CODE
UFC 3-110-03 ROOFING
UFC 3-301-01 STRUCTURAL ENGINEERING
UFC 3-310-04 SEISMIC DESIGN OF BUILDINGS
UFC 3-450-01 NOISE AND VIBRATION CONTROL
UFC 3-400-02 ENGINEERING WEATHER DATA
UFC 3-401-01 MECHANICAL ENGINEERING
UFC 3-410-01 HEATING, VENTILATION & AIR CONDITIONING SYSTEMS
UFC 3-420-01 PLUMBING SYSTEMS
UFC 3-501-01 ELECTRICAL ENGINEERING
UFC 3-550-01 EXTERIOR ELECTRICAL POWER DISTRIBUTION
UFC 3-560-01 ELECTRICAL SAFETY
UFC 4-010-01 DOD MINIMUM ANTI-TERRORISM STANDARDS FOR
BUILDINGS
DWG
T-1
SHEET TITLE
TITLE SHEET
DRAWING SCHEDULE
M-1 MECHANICAL PLAN
M-2 MECHANICAL DETAILS
SCOPE OF WORK SUMMERY
REPLACE THE EXISTING HVEC UNIT (EVAPORATIVE COOLING AND HYDRONIC
HEATING) WITH A NEW PACKAGED AIR TO AIR HEAT PUMP TO MEET UFC
3-490-26 REQUIREMENTS. TI
TL
E
SH
EE
T
T-1
PROJECT LOCATION
IR #11-6554
GENERAL DEMOLITION NOTES:
1. THIS DRAWING WAS COMPILED USING AVAILABLE RECORD DRAWINGS AND ARE
INTENDED TO INDICATE DEMOLITION SCOPE FOR THE EXISTING HVEC SYSTEM.
THE CONTRACTOR SHALL FIELD VERIFY ALL DUCTWORK, PIPING, EQUIPMENT
LOCATION, DIMENSIONS AND ALL FIELD CONDITIONS.
2. PRIOR TO COMMENCING WORK, THE CONTRACTOR SHALL DISCONNECT
ELECTRICAL POWER TO THE EXISTING EQUIPMENT.
3. AFTER DISCONNECTION WORK HAS BEEN COMPLETED, THE CONTRACTOR SHALL
REMOVE EXISTING MECHANICAL SYSTEM INCLUDING (1) EVAPORATIVE COOLING,
HEATING HOT WATER HEATING UNIT WITH ASSOCIATED DUCTING (INTERIOR AND
EXTERIOR), INSULATIONS, PIPING, AND ACCESSORIES FOR AIR DISTRIBUTION
SYSTEM (SUPPLY WALL REGISTER)
4. REMOVE ALL EXISTING THERMOSTATS/TEMPERATURE SENSORS. DEMOLITION TO
INCLUDE ALL WIRING, CONDUIT.
5. CONTRACTOR IS RESPONSIBLE FOR PATCHING ALL PENETRATIONS CREATED BY
REMOVAL OF EQUIPMENT, DUCTWORK, PIPING, ETC. TO MATCH EXISTING. REPAIR
ADJACENT CONSTRUCTION AND FINISHES DAMAGED DURING DEMOLITION AND
EXTENSION WORK. PATCH TO MATCH ORIGINAL CONSTRUCTION.
6. COORDINATE DEMOLITION WORK WITH OTHER TRADES.
GENERAL NOTES:
1. PROVIDE DRY BULB ECONOMIZER WITH POWER EXHAUST AND FACTORY INSTALLED
AND WIRED, FULLY MODULATING ACTUATORS WITH LOW LEAKAGE DAMPERS.
2. EFFICIENCY RATING REQUIREMENTS SHALL MEET ASHRAE 90.1.
3. PROVIDE DOUBLE WALL DUCT WITH 3" INSULATION. SIZE SHOWN IS INSIDE CLEAR
DIMENSION. TYPICAL FOR ALL EXPOSED DUCTWORK ON ROOF.
4. PROVIDE REPLACEMENT THE (E) EC-9 WITH A (N) HEAT PUMP.
5. PROVIDE FACTORY MOUNTED 120V POWERED GFCI CONVENIENCE OUTLET.
6. THE CONTRACTOR SHALL MODIFY THE (E) EC-9 UNIT MOUNTING SYSTEM TO RESIST
UPLIFT AND SLIDING FORCES FROM WIND AND OTHER LOADS, ENSURING IT MEETS THE
MANUFACTURER'S SPECIFIED LOAD CAPACITY AND PROVIDES CORROSION
PROTECTION AS OUTLINED IN THE RELEVANT UFC.
KEY NOTES:
REUSE EXISTING WALL PENETRATION.
PROVIDE MAN BAR PER DETAIL 6/M-2.
PROVIDE 7 DAYS PROGRAMMABLE THERMOSTAT WITH LOCKING COVER.
PROVIDE A 600V, 30A, 3-PHASE, HEAVY DUTY, NEMA 3, NON-FUSED, ELECTRICAL DISCONNECT.
EXTEND EXISTING CIRCUIT TO NEW DISCONNECT AND MAKE FINAL TERMINATIONS TO THE NEW
MECHANICAL EQUIPMENT.
REPLACE (E) OVERCURRENT PROTECTIVE DEVICE WITH A 15A, 3-POLE MOLDED CASE BREAKER.
COORDINATE BREAKER MAXIMUM OVERCURRENT PROTECTION (MOCP) RATING WITH THE
PROCURED EQUIPMENT MANUFACTURER. BREAKER IS LOCATED IN DISTRIBUTION EQUIPMENT
'MCC-2'.
CR CR
IS
S
U E
D F
O R
S
TA
TI
O
N R
E
VI
E W
/1
3/
E
LE
V A
TO
R
M A
C H
IN
E
R M
. A /C
R E
P
LA
C E
M E
N T
N A
V A
L A
IR
W
E A
P O
N S
C E
N
TE
R
W E
A P
O N
S D
IV
IS
IO
N
IS
S
U E
D F
O R
C O
N S
TR
U
C
TI
O N
/2
4/
MECHANICAL DEMO PLAN
SCALE: 316 " = 1'
N
M
EC
H
AN
IC
AL
P
LA
N
MECHANICAL ROOF PLAN
SCALE: 316 " = 1'
N
M-1
KEY NOTES:
DISCONNECT AND REMOVE (E) ELECTRICAL DISCONNECT. PULL BACK (E) FEEDER AND
SAFE-OFF FOR RE-USE.
IR #11-6555
CR CR
IS
S
U E
D F
O R
S
TA
TI
O
N R
E
VI
E W
/1
3/
E
LE
V A
TO
R
M A
C H
IN
E
R M
. A /C
R E
P
LA
C E
M E
N T
N A
V A
L A
IR
W
E A
P O
N S
C E
N
TE
R
W E
A P
O N
S D
IV
IS
IO
N
IS
S
U E
D F
O R
C O
N S
TR
U
C
TI
O N
/2
4/
M
EC
H
AN
IC
AL
D
ET
AI
LS
M-2
GRILLES AND REGISTERS SCHEDULE
DOUBLE DEFLECTION
SIDEWALL SUPPLY REGISTER
SYMBOL DESCRIPTION MAX
CFM
TP
(in.wg)
FACE
SIZE NC
FIXED ANGLE SIDEWALL RETURN GRILLE
STEEL CONSTRUCTION, 45° FIXED BLADE 35
1670 0.168 24"x18"
1668 -
DUCT SYSTEM
DESCRIPTION MATERIAL INSULATION
SUPPLY AIR DUCT (OUTDOOR) A 1
RETURN AIR DUCT (OUTDOOR) A 1
GALVANIZED STEEL DOUBLE WALLA
FIBERGLASS INSULATION (R-8) BETWEEN INNER AND
OUTER DUCT WALLS.1
24"x18"
IR #11-6556
| T-1 |
| M-1 |
| M-2 |