Technical Specifications Summary
This file is a technical specifications document issued by the City of Dania Beach Department of Public Works for the NW 1st Street drainage improvements project, scheduled for February 2026. The document provides comprehensive requirements for drainage infrastructure construction along NW 1st Street from Bryan Road to Federal Highway, including detailed specifications for inlets, manholes, junction boxes, pipe culverts, precast concrete drainage products, and related drainage components. The specifications cover construction methods, materials, quality standards, and testing requirements for concrete pipe, corrugated metal pipe, plastic pipe, and precast concrete structures. Key sections address pipe joint standards (water-tight or soil-tight requirements), end treatments, backfilling procedures, pipe inspection protocols utilizing video documentation with laser profiling technology for pipes 48 inches or less in diameter, and reinspection requirements. The document establishes minimum performance standards for storm drains, cross drains, side drains, and gutter drains, with specific tolerances for pipe alignment, deflection limits of 5% for flexible pipe, and dimensional requirements for precast products. Additional specifications cover precast prestressed concrete construction, including quality control programs, material certification, tensioning equipment calibration, form design, and concrete curing requirements for fabricated drainage elements.
The specifications require contractors to obtain materials from Department-approved production facilities with current Quality Control certification, submit notarized certifications, and maintain detailed documentation of material testing, fabrication processes, and installation procedures. Payment is structured by item type—including pipe culvert installations by excavation or jack and bore methods, end treatments, structure adjustments, desilting operations, and filling/plugging of pipes—with measurements based on plan quantities in place and accepted. The document emphasizes strict adherence to material standards for concrete, reinforcement, gaskets, and other components through references to applicable ASTM standards, AASHTO specifications, and supplementary sections covering concrete quality, drainage materials, and specialized products. Contractors must also comply with comprehensive inspection and documentation requirements, including video submission standards, laser profiling calibration criteria, and detailed reporting of pipe condition, joint separations, and any defects prior to final acceptance.
View the file
Other files for this state and local contract opportunity
Show all 50
NW 1ST STREET COMPLETE STREETS IMPROVEMENT LOCAL AGENCY PROGRAM (LAP) PROJECT has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NW 1st Street 000101-1
Procurement and Contracting Documents
CITY OF DANIA BEACH
TECHNICAL SPECIFICATIONS FOR DRAINAGE IMPROVEMENTS
Project Name:
NW 1ST STREET
Project Address:
NW 1ST STREET FROM BRYAN ROAD TO FEDERAL HIGHWAY
Owner:
City of Dania Beach Department of Public Works
1201 Stirling Road Dania Beach, FL 33004
Date:
February 2026
SECTION 425
INLETS, MANHOLES, AND JUNCTION BOXES
425-1 Description.
Construct inlets, manholes, and junction boxes from reinforced concrete as shown in the
Standard Plans and the Plans. Furnish and install the necessary metal frames and gratings.
Construct yard drains from concrete meeting the requirements of Section 347. Adjust structures shown in the Plans to be adjusted or requiring adjustment for the satisfactory completion of the work.
For precast structures, meet the requirements in 449-1.
425-2 Composition and Proportioning.
425-2.1 Concrete: For inlets, manholes, and junction boxes, use Class II or IV concrete, as designated in the Plans and Standard Plans and as specified in Section 346. For concrete aprons and yard drains, use concrete as specified in Section 347.
425-2.2 Mortar: For brick masonry, make the mortar by mixing one-part cement to three parts sand. Miami Oolitic rock screenings may be substituted for the sand, provided the screenings meet the requirements of 902 except for gradation requirements. Use materials passing the No. 8 sieve that are well graded from coarse to fine. Submit documentation, from a
Department approved mine or a Department approved concrete plant, confirming the sand or sand substitute meets the requirements of 902-3.2.
Preblended masonry cement mortar may be used in lieu of the above-specified mortar. Deliver the product in original and unopened packages properly identified by brand name of manufacturer, net weight of package, and type. Store the material in full compliance with the manufacturer’s recommendations. Material must be used within manufacturer’s recommended shelf life.
425-3 Materials.
425-3.1 General: Meet the following requirements:
Sand (for mortar).................................................Section 902
Portland Cement..................................................Section 921
Water ...................................................................Section 923
Reinforcing Steel ................................ Sections 931 and 415
Liner Repair Systems ..........................................Section 948
Brick and Concrete Masonry Units.....................Section 949
Castings for Frames and Gratings .......................Section 962
Masonry Cement, Type M or S........................... ASTM C91
Preblended Dry Masonry Cement Mortar, Type M or S
......................................................................... ASTM C1714
425-3.2 Gratings, Covers, and Frames: Use gratings and frames fabricated from structural steel or cast iron as designated in the appropriate Standard Plans Index. When “Alt. G” grates are specified in the Plans, provide structural steel grates that are galvanized in accordance with the requirements of ASTM A123 and hardware galvanized in accordance with the requirements of ASTM A153.
472 FY 2026-27
Use rigid frames and covers either 24 inches or 36 inches or optional three-piece adjustable frames and covers as indicated in Standard Plans, Index 425-001.
For three-piece adjustable frames, the inner frame may include replaceable resilient seats to support the cover. In addition, the inner frame shall indicate it is adjustable, by clearly having the word “adjustable” imprinted into the exposed portion of the inner frame so
“adjustable” is visible from the roadway after installation.
425-3.3 Skimmer: Include 1.5% by weight of carbon black with plastic skimmers on french drain systems.
425-4 Forms.
Design and construct wood or metal forms so that they may be removed without damaging the concrete. Build forms true to line and grade and brace them in a substantial and unyielding manner. Obtain the Engineer’s approval before filling them with concrete.
425-5 Precast Inlets, Manholes, and Junction Boxes.
Precast inlets, manholes, and junction boxes, designed and fabricated in accordance with the Plans, the Standard Plans and Section 449 may be substituted for cast-in-place units.
425-6 Skimmers.
Furnish and install skimmers in accordance with the Plans and Standard Plans.
425-7 Construction Methods.
425-7.1 Excavation: Excavate as specified in Section 125.
Where unsuitable material for foundations is encountered, excavate the unsuitable material and backfill with suitable material prior to constructing or setting inlets, manholes and junction boxes.
As an option to the above and with the Engineer’s approval, the Contractor may carry the walls down to a depth required for a satisfactory foundation, backfill to 8 inches below the flowline with clean sand and cast a non-reinforced 8 inch floor.
425-7.2 Placing and Curing Concrete: Place the concrete in the forms, to the depth shown in the Plans, and thoroughly vibrate it. After the concrete has hardened sufficiently, cover it with suitable material and keep it moist for a period of three days. Finish the traffic surface in accordance with 522-7.2, or with a simulated broom finish approved by the Engineer.
425-7.3 Setting Manhole Castings: After curing the concrete as specified above, set the frame of the casting in a full mortar bed composed of one-part portland cement to two parts of fine aggregate.
425-7.3.1 Standard Castings: Set manhole frames in a mortar bed and adjust to grade using brick or concrete grade rings, with a maximum 12 inch adjustment.
425-7.3.2 Optional Adjustable Castings: When using a three-piece adjustable frame and cover, install the frame and cover with brick or concrete grade rings to the base course height. Make adjustments using the inner frame in accordance with the manufacturer’s installation recommendations so the inner frame and cover meet the grade and slope of the pavement surface opened to traffic.
425-7.4 Reinforcing Steel: Follow the construction methods for the steel reinforcement as specified in Section 415.
425-7.5 Laying Brick: Brick masonry may be used if the structure is circular and constructed in place, or for adjustments of rectangular risers up to a maximum 12 inches in
473 FY 2026-27
height. Saturate all brick with water before laying. Bond the brick thoroughly into the mortar using the shove-joint method to lay the brick. Arrange headers and stretchers so as to bond the mass thoroughly. Finish the joints properly as the work progresses and ensure that they are not less than 1/4 inch or more than 3/4 inch in thickness. Do not use spalls or bats except for shaping around irregular openings or when unavoidable at corners.
425-7.6 Backfilling: Backfill as specified in Section 125, meeting the specific requirements for backfilling and compaction around inlets, manholes, and junction boxes detailed in 125-8.1 and 125-8.2. However; for outfall lines beyond the sidewalk or future sidewalk area, where no vehicular traffic will pass over the pipe, inlets, manholes, and junction boxes, compact backfill as required in 125-9.2.2.
425-7.7 Adjusting Structures: Adjust existing manholes, catch basins, inlets, valve boxes, etc., within the limits of the proposed work, to meet the finished grade of the proposed pavement, or if outside of the proposed pavement area, to the finished grade designated in the
Plans for such structures. Adjust structures prior to placement of final asphalt pavement surface layer. Adjust structures to match final pavement surface cross-slope. Use materials and construction methods which meet the requirements specified above to adjust the existing structures.
The Contractor may extend manholes needing to be raised using adjustable extension rings of the type which do not require the removal of the existing manhole frame. Use an extension device that provides positive locking action and permits adjustment in height as well as diameter and meets the approval of the Engineer. When adjusting structures in flexible pavement, restore final road surface in accordance with Standard Plans, Index 125-001.
425-8 Method of Measurement.
The quantities to be paid for will be the number of inlets, manholes, junction boxes, and yard drains, completed and accepted; and the number of structures of these types (including also valve boxes) satisfactorily adjusted. Performance Turf will be paid in accordance with
Section 570.
425-9 Basis of Payment.
425-9.1 New Structures: Price and payment will be full compensation for furnishing all materials and completing all work described herein or shown in the Plans, including all clearing and grubbing outside the limits of clearing and grubbing as shown in the Plans, all excavation except the volume included in the measurement designated to be paid for under the items for the grading work on the project, all backfilling around the structures, the disposal of surplus material, and the furnishing and placing of all aprons, gratings, frames, covers, and any other necessary fittings.
425-9.2 Adjusted Structures: When an item of payment for adjusting manholes, valve boxes, or inlets is provided in the proposal, price and payment will be full compensation for the number of such structures designated to be paid for under such separate items, and which are satisfactorily adjusted, at the Contract unit prices each for adjusting inlets, adjusting manholes, and adjusting valve boxes.
For any of such types of these structures required to be adjusted but for which no separate item of payment is shown in the proposal for the specific type, payment will be made under the item of adjusting miscellaneous structures.
474 FY 2026-27
425-9.3 Payment Items: Payment will be made under:
Item No.425- 1- Inlets - each.
Item No.425- 2- Manholes - each.
Item No.425- 3- Junction Boxes - each.
Item No.425- 4- Adjusting Inlets - each.
Item No.425- 5- Adjusting Manholes - each.
Item No.425- 6- Adjusting Valve Boxes - each.
Item No.425- 8- Adjusting Miscellaneous Structures - each.
Item No.425- 10- Yard Drains - each.
Item No. 425- 17- Back of Sidewalk Endwall - each.
475 FY 2026-27
SECTION 430
PIPE CULVERTS
430-1 Description.
Furnish and install drainage pipe and end sections at the locations called for in the Plans.
Furnish and construct joints and connections to existing pipes, catch basins, inlets, manholes, walls, etc., as may be required to complete the work.
Obtain pipe culverts and drainage products from a plant that is currently on the
Department’s Production Facility Listing. Producers seeking inclusion on the list shall meet the requirements of Section 105.
At the beginning of each project, submit a notarized certification statement to the
Engineer in accordance with Section 6. The Production Facility Quality Control Stamp or label on each product indicates certification that the product was fabricated in conformance with the
Producer QC Plan, the Contract, and this Section. Ensure that each shipment of drainage products to the project site is accompanied with a QC signed or stamped delivery ticket providing the description and the list of the products.
When the Producer Quality Control Program is suspended by the Department, accept responsibility of either obtaining products from a plant with an approved Quality Control
Program, or await re-approval of the plant. The Engineer will not allow changes in Contract
Time or completion dates as a result of the plant’s loss of qualification. Accept responsibility for all delay costs or other costs associated with the loss of the plant’s qualification.
Construct structural plate pipe culverts or underdrains in accordance with Sections 435 and 440.
For pipe culverts installed by jack and bore, install in accordance with Section 556.
430-2 Materials.
430-2.1 Pipe: Meet the following requirements:
Flowable Fill ..........................................................................Section 121
Portland Cement Concrete .....................................................Sections 346 and 347
End Treatments ......................................................................Sections 425 and 449
Joint Materials ........................................................................430-7 through 430-9
Concrete Pipe .........................................................................Section 449
Steel Pipe ...............................................................................556-2.1
Round Rubber Gaskets, Preformed Plastic Gaskets ..............Section 942
Resilient Connectors* ............................................................Section 942
Corrugated Steel Pipe and Pipe Arch.....................................Section 943
Corrugated Aluminum Pipe and Pipe Arch ...........................Section 945
Corrugated Polyethylene Pipe................................................Section 948
Steel Reinforced Polyethylene Ribbed Pipe ..........................Section 948
Steel Reinforced Polyethylene Corrugated Pipe ....................Section 948
Corrugated Polypropylene Pipe .............................................Section 948
Corrugated Polyvinyl Chloride (PVC) Pipe ..........................Section 948
Fiberglass Reinforced Polymer Pipe ......................................Section 948
Metal Grates ...........................................................................Section 962
Pipe Sleeve Adapters .............................................................Section 948
Geosynthetic Materials, D-3 Geotextile * .............................Section 985
476 FY 2026-27
*Use products on the Department’s Approved Product List (APL).
430-2.2 Mortar: Use mortar composed of one part Portland cement and two parts of clean, sharp sand, to which mixture the Contractor may add hydrated lime in an amount not to exceed 15% of the cement content. Use mortar within 30 minutes after its preparation.
430-2.3 End Treatments: Meet the requirements of Section 425-3.1. For precast end treatments, meet the requirements in 449-1. Use the concrete Class designated in the Plans and
Standard Plans, and as specified in Section 346 and 347.
430-3 Type of Pipe to be Used.
430-3.1 General: Prior to the preconstruction conference, submit to the Engineer which optional pipe material from the optional materials tabulation sheet will be used. Once a pipe material is selected, do not change pipe materials without approval of the Engineer.
When the Plans designate a type (or types) of pipe, use only the type (or choose from the types) designated. As an exception, when the Plans designate reinforced concrete pipe as Class S, Class I, Class II, Class III and Class IV, the Contractor may use non-reinforced concrete pipe up to and including 36 inch in diameter.
430-3.2 Side Drain: If the Plans do not designate a type (or types) of pipe, the Contractor may use either a minimum Class I concrete pipe, corrugated steel pipe, corrugated aluminum pipe, corrugated high-density polyethylene pipe, steel reinforced polyethylene ribbed pipe, polypropylene pipe, or PVC pipe. If one of the metal types is chosen, use the minimum gage specified in Section 943 for steel pipe or Section 945 for aluminum pipe. Alternatively, when metal pipe is allowed and no future maintenance concerns exist, the Contractor may propose the pipe gage based on the Department’s Drainage Manual and Culvert Service Life Estimator for approval by the Engineer. When extending existing pipes, construct the pipe extensions of the same size and kind as the existing pipe. Extensions of existing pipes, whose materials are no longer produced, shall be extended with the most similar pipe material available.
Non-reinforced concrete pipe may also be substituted for concrete pipe in side drains, subject to the provisions of 430-3.1.
430-4 Laying Pipe.
430-4.1 General: Lay all pipe, true to the lines and grades given, with bells upgrade and spigot end fully entered into the bell. When pipe with quadrant reinforcement or circular pipe with elliptical reinforcement is used, install the pipe in a position such that the manufacturer’s marks designating “top” and “bottom” of the pipe are not more than five degrees from the vertical plane through the longitudinal axis of the pipe. Do not allow departure from and return to plan alignment and grade to exceed 1/16 inch per foot of nominal pipe length, with a total of not more than 1 inch departure from theoretical line and grade. Take up and relay any pipe that is not in true alignment or which shows any settlement after laying at no additional expense to the
Department.
Do not use concrete pipe with lift holes except round pipe which has an inside diameter in excess of 54 inches or any elliptical pipe.
Repair lift holes, if present, with hand-placed, stiff, non-shrink, 1-to-1 mortar of cement and fine sand, after first washing out the hole with water. Completely fill the void created by the lift hole with mortar. Cover the repaired area with a 24 inch by 24 inch piece of geotextile secured to the pipe.
Follow the manufacturer’s instructions, to secure the geotextile to the pipe, until the backfill is placed and compacted.
477 FY 2026-27
Do not cut or drill into or through the corrugations or ribs of plastic pipe except when necessary to meet the dimensional requirements shown in the Plans.
When installing pipes in structures, construct inlet and outlet pipes of the same size and kind as the connecting pipe shown in the Plans. Use the same pipe material within each continuous run of pipe. Extend the pipes through the walls for a distance beyond the outside surface sufficient for the intended connections, and construct the concrete around them neatly to prevent leakage along their outer surface as shown on Standard Plans, Index 425-001. Keep the inlet and outlet pipes flush with the inside of the wall. Resilient connectors as specified in 942-3 may be used in lieu of a masonry seal.
Furnish and install a geotextile jacket around all pipe joints and the joint between the pipe and the structure in accordance with Standard Plans, Indexes 425-001 and 430-001. Use geotextile meeting the physical requirements of Type D-3 specified in Section 514. Extend the geotextile a minimum of 12 inches beyond each side of the joint or both edges of the coupling band, if a coupling band is used. The geotextile must have a minimum width of 24 inches, and a length sufficient to provide a minimum overlap of 24 inches. Secure the geotextile jacket against the outside of the pipe by metal or plastic strapping or by other methods approved by the
Engineer.
Meet the following minimum joint standards:
Table 430-1
Pipe Application Minimum Standard
Storm and Cross Drains Water-tight
Gutter Drain Water-tight
Side Drains Soil-tight
When rubber gaskets are to be installed in the pipe joint, the gasket must be the sole element relied on to maintain a tight joint. Soil tight joints must be watertight to 2 psi.
Water-tight joints must be water-tight to 5 psi unless a higher pressure rating is required in the
Plans.
When laying pipes that pass through mechanically stabilized earth (MSE) reinforced fill, connect the portion of the pipe within the wall to the external portion of the pipe run only after the full height of the wall supported embankment is in place.
When Wall Zone Pipes are shown in the Plans, meet the following requirements:
1. Use resilient connectors on pipes entering and leaving drainage structures.
2. Provide a 2 to 4 inch pipe overhang beyond the drainage structure internal walls.
3. For pipes without welded joints, meet the following additional requirements:
a. Pipe joints must be watertight to 10.8 psi when pulled out
2 inches from the fully homed position in both straight alignment and 5% deflection.
b. Do not allow the gap between sections of pipe to exceed
5/8 inch for all pipe diameters.
430-4.2 Trench Excavation: Excavate the trench for storm and cross drains, and side drains as specified in Section 125.
478 FY 2026-27
430-4.3 Foundation: Provide a suitable foundation, where the foundation material is of inadequate supporting value, as determined by the Engineer. Remove the unsuitable material and replace it with suitable material, as specified in 125-8. Where in the Engineer’s opinion, the removal and replacement of unsuitable material is not practicable, they may direct alternates in the design of the pipeline, as required to provide adequate support. Minor changes in the grade or alignment will not be considered as an adequate basis for extra compensation.
Do not lay pipe on blocks or timbers, or on other unyielding material, except where the use of such devices is called for in the Plans.
430-4.4 Backfilling: Backfill around the pipe as specified in 125-8 unless specific backfilling procedures are described in the Contract Documents.
430-4.5 Plugging Pipe: When existing pipe culverts are to be permanently placed out of service, fill them with flowable fill that is non-excavatable, contains a minimum 350 pounds per cubic yard of cementitious material and meets the requirements of Section 121 and/or plug them with masonry plugs as shown in the Plans. Install masonry plugs that are a minimum of 8 inches in thickness, in accordance with Standard Plans, Index 430-001.
When proposed or existing pipe culverts are to be temporarily placed out of service, plug them with prefabricated plugs as shown in the Plans. Install prefabricated plugs in accordance with the manufacturer’s recommendations. Do not fill or construct masonry plugs in any pipe culvert intended for current or future service.
430-4.6 End Treatment: Place an end treatment at each storm and cross drain, and side drain as shown in the Plans. Sod around end treatments in accordance with Standard Plans, Index
570-001.
430-4.6.1 U-Type Concrete Endwalls: Construct in accordance with the Plans and Standards Plans, Indexes 430-010 through 430-012 and Index 430-090.
430-4.6.2 Flared End Sections: Construct in accordance with the Plans and
Standard Plans, Index 430-020. Use precast flared end sections only.
430-4.6.3 Mitered End Sections: Construct in accordance with the Plans and
Standard Plans, Indexes 430-021 and 430-022. Construct mitered end sections for corrugated high-density polyethylene (HDPE) pipe, polypropylene (PP) pipe, steel reinforced polyethylene ribbed (SRPE) pipe and polyvinyl-chloride (PVC) pipe as specified in Section 948 and as detailed in the Standard Plans.
430-4.6.4 Straight and Winged Concrete Endwalls: Construct in accordance with the Plans and Standard Plans, Indexes 430-030 through 430-040.
Provide end treatments for corrugated polyethylene pipe, polypropylene pipe, and
PVC pipe as specified in Section 948, or as detailed in the Plans.
430-4.7 Metal Pipe Protection: Apply a bituminous coating to the surface area of the pipe within and 12 inches beyond the concrete or mortar seal prior to sealing, to protect corrugated steel or aluminum pipe embedded in a concrete structure, such as an inlet, manhole, junction box, endwall, or concrete jacket.
Ensure that the surface preparation, application methods (dry film thickness and conditions during application), and equipment used are in accordance with the coating manufacturers’ published specifications.
Obtain the Engineer’s approval of the coating products used.
430-4.8 Pipe Inspection: For pipes installed under the roadway, inspection is to be conducted when backfill reaches 3 feet above the pipe crown or upon completion of the stabilized subgrade. For pipe installed within fills, including embankments confined by walls, 479 FY 2026-27 inspection is to be conducted when compacted embankment reaches 3 feet above the pipe crown or the finished earthwork grade as specified in the Plans. Prior to conducting the inspection, submit to the Engineer an inspection schedule for dewatering the installed pipe, and the removal of all silt, debris, and obstructions. Submit pipe inspection videos and reports to the Department for review prior to the continuation of paving.
For pipe 48 inches or less in diameter, submit to the Engineer the video files and reports using low barrel distortion video equipment with laser profile technology, non-contact video micrometer and associated software. For all pipe types, provide a Pipe Observation
Summary Report for each pipe run that shall include:
1. Actual recorded length and width measurements of all cracks within the pipe.
2. Actual recorded separation measurement of all rigid pipe joints.
3. Detailed written observations of leaks, debris, or other damage or defects.
For flexible pipe types, submit a Pipe Ovality Report for each pipe run that includes:
1. Representative diameter of the pipe.
2. Pipe deformation/deflections measurements with the 5% deflection limit clearly delineated.
Laser profiling and measurement technology must be certified by the company performing the work to be in compliance with the calibration criteria posted at:
https://fdotwww.blob.core.windows.net/sitefinity/docs/default-source/construction/engineers/environmental/laser-profiling-calibration-criteria.pdf. Reports submitted in electronic media are preferred.
For pipe larger than 48 inches, submit to the Engineer a detailed visual inspection summary report for each pipe run, including photos, locations and details of deficient cracks, joint separations, infiltration, and damage.
The Engineer may waive this requirement for side drains and cross drains which are short enough to inspect from each end of the pipe.
430-4.8.1 Video Report: Provide video files via digital media (DVD, flash drive, or other) or by online digital distribution with a minimum standard resolution of 720 x 480. Use a camera with lighting suitable to allow a clear picture of the entire periphery of the pipe. Center the camera in the pipe both vertically and horizontally and be able to pan and tilt to a 90-degree angle with the axis of the pipe and rotating 360 degrees. Use equipment to move the camera through the pipe that will not obstruct the camera’s view or interfere with proper documentation of the pipe’s condition.
The video image shall be clear, focused, and relatively free from roll, static, or other image distortion qualities that would prevent the reviewer from evaluating the condition of the pipe. The video will include identification before each section of pipe filmed.
The identification will include the project number, the structure number corresponding to the structure number in the Plans for the project, size of pipe, the date and time, and indicate which pipe is being filmed if multiple pipes are connected to the structure. Notes should be taken during the video recording process. Submit these notes along with the video.
Move the camera through the pipe at a speed not greater than 30 feet per minute. Mark the video with the distance down the pipe. The distance shall have an accuracy of one foot per 100 feet. Film the entire circumference at each joint. Stop the camera and pan when
480 FY 2026-27
https://fdotwww.blob.core.windows.net/sitefinity/docs/default-source/construction/engineers/environmental/laser-profiling-calibration-criteria.pdf https://fdotwww.blob.core.windows.net/sitefinity/docs/default-source/construction/engineers/environmental/laser-profiling-calibration-criteria.pdf necessary to document and measure defects. Position the camera head perpendicular to all defects requiring measurement by the video micrometer.
430-4.8.2 Reinspection: At any time after reviewing the submitted pipe inspection reports, the Engineer may direct additional inspections. If no defects are observed during the reinspection, the Department will pay for the cost of the reinspections in accordance with 4-3. If defects are observed, the reinspection and all work performed to correct the defects will be done at no cost to the Department. Acceptance of all replacements or repairs will be based on video documentation of the completed work prior to Final Acceptance.
430-5 Removing Existing Pipe.
If the Plans indicate that existing pipe is to remain the property of the Department, collect and stack along the right-of-way all existing pipe or pipe arch so indicated in the Plans to be removed, or that does not conform to the lines and grades of the proposed work and that is not to be re-laid, as directed by the Engineer. Take care to prevent damage to salvageable pipe during removal and stacking operations.
430-6 Placing Pipe Under Railroad.
430-6.1 General: Construct pipe culverts under railroad tracks in accordance with the requirements of the railroad company.
Perform all the shoring under the tracks, and sheeting and bracing of the trench, required by the railroad company or deemed necessary by the Engineer in order to ensure safe and uninterrupted movement of the railroad equipment, at no expense to the Department.
430-6.2 Requirements of the Railroad Company: Install pipe using methods required by the railroad company and shown in the Contract Documents.
When the general method of installation required by the railroad company is indicated in the Plans, do not alter such method, or any other specific details of the installation which might be indicated in the Plans, without receiving approval or direction from the railroad, followed by written approval from the Engineer.
430-6.3 Notification to Railroad Company: Notify the railroad company and the
Engineer at least ten days prior to the date on which pipe is to be placed under the railroad tracks.
430-6.4 Placing Pipe by Jacking: Obtain the Engineer’s and the railroad company’s approval of the details of the jacking method to be used, when placing pipe through the railroad embankment, before the work is started.
430-6.5 Use of Tunnel Liner: When the railroad company requires that a tunnel liner be used for placing the pipe in lieu of the jacking method, the Department will pay for the tunnel liner material separately in cases where the Contract Documents do not require the use of a tunnel liner. For these cases the Department will reimburse the Contractor for the actual cost of the liner, delivered at the site. The Department will base such cost on a liner having the minimum gage acceptable to the railroad.
430-7 Specific Requirements for Concrete Pipe.
430-7.1 Sealing Joints: Seal the pipe joints with round rubber or profile gaskets meeting the requirements of Section 449. Ensure that the gasket and the surface of the pipe joint, including the gasket recess, are clean and free from grit, dirt, and other foreign matter, at the time the joints are made. In order to facilitate closure of the joint, application of a vegetable soap lubricant immediately before closing of the joint will be permitted. Prelubricated gaskets may be
481 FY 2026-27
used in lieu of a vegetable soap lubricant when the lubricating material is certified to be inert with respect to the rubber material.
430-7.2 Laying Requirements for Concrete Pipe with Rubber Gasket Joints: Do not allow the gap between sections of pipe to exceed 5/8 inch for pipe diameters of 12 inches through 18 inches, 7/8 inch for pipe diameters of 24 through 66 inches, and 1 inch for pipe diameters 72 inches and larger. Where minor imperfections in the manufacture of the pipe create an apparent gap in excess of the tabulated gap, the Engineer will accept the joint provided that the imperfection does not exceed 1/3 the circumference of the pipe, and the rubber gasket is
1/4 inch or more past the pipe joint entrance taper. Where concrete pipes are outside of these tolerances, replace them at no expense to the Department. Do not apply mortar, joint compound, or other filler to the gap which would restrict the flexibility of the joint.
430-7.3 Field Joints for Elliptical Concrete Pipe: Use either a preformed plastic gasket material or an approved rubber gasket to make a field joint.
430-7.3.1 Plastic Gasket: Meet the following requirements when field joints are made from preformed plastic gasket material:
430-7.3.1.1 General: Install field joints in accordance with the manufacturer’s instructions and the following:
430-7.3.1.2 Material: Meet the requirements of 942-2.
430-7.3.1.3 Joint Design: Ensure that the pipe manufacturer submits details to the Engineer regarding configuration of the joint and the amount of gasket material required to affect a satisfactory seal. Do not brush or wipe joint surfaces which are to be in contact with the gasket material with a cement slurry. Fill minor voids with cement slurry.
430-7.3.1.4 Primer: Apply a primer of the type recommended by the manufacturer of the gasket material to all joint surfaces which are to be in contact with the gasket material, prior to application of the gasket material. Thoroughly clean and dry the surface to be primed.
430-7.3.1.5 Application of Gasket: Apply gasket material to form a continuous gasket around the entire circumference of the leading edge of the tongue and the groove joint, in accordance with the detail shown on Standard Plans, Index 430-001. Do not remove the paper wrapper on the exterior surface of the gasket material until immediately prior to joining of sections. Apply plastic gasket material only to surfaces which are dry. When the atmospheric temperature is below 60ºF, either store plastic joint seal gaskets in an area above
70ºF, or artificially warm the gaskets to 70ºF in a manner satisfactory to the Engineer.
430-7.3.1.6 Installation of Pipe: Remove and reposition or replace any displaced or contaminated gasket as directed by the Engineer. Install the pipe in a dry trench.
Carefully shape the bottom of the trench to minimize the need for realignment of sections of pipe after they are placed in the trench. Hold to a minimum any realignment of a joint after the gaskets come into contact. Prior to joining the pipes, fill the entire joint with gasket material and ensure that when the pipes are joined there is evidence of squeeze-out of gasket material for the entire internal and external circumference of the joint. Trim excess material on the interior of the pipe to provide a smooth interior surface. If a joint is defective, remove the leading section of pipe and reseal the joint.
430-7.3.2 Rubber Gasket: Meet the following requirements when field joints are made with profile rubber gaskets:
430-7.3.2.1 General: Install field joints in accordance with the manufacturer’s instructions and the following:
482 FY 2026-27
430-7.3.2.2 Material: Meet the requirements of 942-4.
430-7.3.2.3 Joint Design: Ensure that the pipe manufacturer submits details to the Engineer regarding configuration of the joint and gasket required to effect a satisfactory seal. Do not apply mortar, joint compound, or other filler which would restrict the flexibility of the gasket joint.
430-7.4 Requirements for Concrete Radius Pipe:
430-7.4.1 Design: Construct concrete radius pipe in segments not longer than
4 feet (along the pipe centerline), except where another length is called for in the Contract
Documents. Join each segment using round rubber gaskets. Ensure that the pipe manufacturer submits details of the proposed joint, segment length and shape for approval by the Engineer, prior to manufacture.
430-7.4.2 Pre-Assembly: Ensure that the manufacturer pre-assembles the entire radius section in their yard, in the presence of the Engineer, to ensure a proper fit for all parts. At the option of the manufacturer, the Contractor may assemble the pipe without gaskets.
Consecutively number the joints on both the interior and exterior surfaces of each joint, and make match marks showing proper position of joints. Install the pipe at the project site in the same order as pre-assembly.
430-8 Specific Requirements for Corrugated Metal Pipe.
430-8.1 Field Joints:
430-8.1.1 General: Make a field joint with locking bands, as specified in
Article 9 of AASHTO M36 and AASHTO M196M for aluminum pipe. For aluminum pipe, fabricate bands from the same alloy as the culvert sheeting.
When existing pipe to be extended is helically fabricated, make a field joint between the existing pipe and the new pipe using one of the following methods:
1. Cut the new pipe to remove one of the re-rolled annular end sections required in Sections 943 or 945, or fabricate the pipe so that the re-rolled annular section is fabricated only on one end. Use either a spiral (helical) band with a gasket or a flat band with gaskets as required by 430-8.1.2 (2) to join the pipe sections.
2. The Contractor may construct a concrete jacket as shown on
Standard Plans, Index 430-001.
430-8.1.2 Side Drain, Storm and Cross Drain, and Gutter Drains: Where corrugated metal pipe is used as side drain, storm and cross drain, or gutter drain, use a rubber or neoprene gasket of a design shown to provide a joint as specified in 430-4.
Use a gasket of one of the following dimensions:
1. For annular joints with 1/2 inch depth corrugation: either a single gasket a minimum of 7 inches by 3/8 inch or two gaskets a minimum of 3-1/2 inches by
3/8 inch; and for annular joints with 1 inch depth corrugations: either a single gasket a minimum of 7 inches by 7/8 inch or two gaskets a minimum of 3-1/2 inches by 7/8 inch.
2. For helical joints with 1/2 inch depth corrugation: either a single gasket a minimum of 5 inches by 1 inch or two gaskets a minimum of 3-1/2 inches by 1 inch;
and for helical joints with 1 inch depth corrugations: either a single gasket a minimum of
5 inches by 1-1/2 inches or two gaskets a minimum of 3-1/2 inches by 1-1/2 inches.
3. Such other gasket designs as may be approved by the Engineer.
If, in lieu of a single gasket spanning the joint, two gaskets are used, place these individual gaskets approximately 2 inches from each pipe end at the joint. When two gaskets are used, seal the overlapping area on the coupling band between the gaskets consistent
483 FY 2026-27
with the joint performance specified. The Contractor may tuck a strip of preformed gasket material over the bottom lip of the band for this purpose. Use coupling bands that provide a minimum circumferential overlap of 3 inches. As the end connections on the coupling band are tightened, ensure that there is no local bending of the band or the connection. Use precurved coupling bands on pipe diameters of 24 inches or less.
Use flat gaskets meeting the requirements of ASTM D1056, designation
2C2 or 2B3. In placing flat gaskets on pipe prior to placing the coupling band, do not stretch the gasket more than 15% of its original circumference. Use circular gaskets meeting the requirements of ASTM C361. Do not stretch the circular gasket more than 20% of its original circumference in placing the gasket on pipe. Use preformed plastic gasket material meeting the composition requirements of 942-2.2.
Apply an approved vegetable soap lubricant, as specified for concrete pipe in 430-7.1.1.
430-8.1.3 Alternate Joint: In lieu of the above-specified combination of locking bands and flat gaskets, the Contractor may make field joints for these pipe installations by the following combinations:
1. Use the metal bands as specified in Article 9 of AASHTO M36M that are at least 10-1/2 inches wide and consist of a flat central section with a corrugated section near each end, designed to match the annular corrugation in the pipe with which they are to be used.
Connect the bands in a manner approved by the Engineer, with a suitable fastening device such as the use of two galvanized 1/2 inch diameter bolts through a galvanized bar and galvanized strap, suitably welded to the band. Use a strap that is the same gage as the band.
Where helically corrugated pipe is to be jointed by this alternate combination, ensure that at least the last two corrugations of each pipe section are annular, and designed such that the band will engage each pipe end with the next-to-outside annular corrugation.
2. For these bands, use a rubber gasket with a circular cross-section of the
“O-ring” type conforming to ASTM C361. Use gaskets having the following cross-sectional diameter for the given size of pipe:
Table 430-2
Non-SI Units
Pipe Size Gasket Diameter
12 inches through 36 inches (with 1/2 inch depth corrugations) 13/16 inch
42 inches through 96 inches (with 1/2 inch depth corrugations) 7/8 inch
36 inches through 120 inches (with 1 inch depth corrugations) 1-3/8 inches
Use preformed gasket material to seal the overlapping area on the coupling band between gaskets.
3. Use channel band couplers in helical pipe with ends which have been reformed and flanged specifically to receive these bands. Use channel band couplers that are of a two piece design, are fabricated from galvanized steel stock conforming to AASHTO M36, have
2 inch by 2 inch by 3/16 inch angles fastened to the band ends to allow for proper tightening, and meet the following:
484 FY 2026-27
Table 430-3
Non SI Units
Band Thickness Pipe Wall Thickness
0.079 inch 0.109 inch or lighter
0.109 inch 0.138 inch or heavier
3/4 inch wide 0.109 inch or lighter
1 inch wide 0.138 inch or heavier
Furnish two 1/2 inch diameter connection bolts with each band, that conform to ASTM A307, Grade A and are electroplated in accordance with ASTM B633.
Use a gasket with the joint that is a hydrocarbon blend of butyl rubber meeting the chemical composition and physical properties of 942-2.2. Use a 3/8 by 3/4 inch gasket for pipe fabricated from 0.109 inch or lighter material and a 3/8 by 1 inch gasket for pipe fabricated from 0.138 inch and heavier material.
The Contractor may use a flange band coupler without the gasket for all applications other than side drain, storm and cross drain, and gutter drain.
Do not use the flange band coupler to join dissimilar types of pipe.
The Contractor may join reformed flanged helical pipe to existing annular or reformed pipe having annular ends. On non-gasketed installations, use either an annular band or an alternate joint described in 430-8.1.3. On gasketed installations, use an annular band, minimum of five corrugations in width, in conjunction with two O-ring gaskets as specified in
430-8.1.3. Use mastic material to seal the area of band overlap.
The minimum joint performance standards specified in 430-4.1 apply.
430-8.2 Laying and Shape Requirements for Corrugated Metal Pipe: Install pipe using either a trench or open ditch procedure.
Check pipe shape regularly during backfilling to verify acceptability of the construction method used. Pipe deflected 5% or more of the certified actual mean diameter of the pipe at final inspection shall be replaced at no cost to the Department. Deflection measurements are taken at the point of smallest diameter on the corrugations.
430-9 Specific Requirements for Steel Reinforced Polyethylene Ribbed Pipe, Corrugated
High-Density Polyethylene Pipe, Polypropylene Pipe, and Polyvinyl Chloride (PVC) Pipe.
430-9.1 Sampling Requirements: Submit a sample of each pipe material and diameter used on each project to the Engineer a minimum of two weeks prior to the installation, provided that the pipe meets all of the following:
1. Pipe material is PVC, HDPE, steel reinforced polyethylene
2. Pipe is corrugated or ribbed
3. Pipe diameter is 12” or larger
4. Project quantity for a pipe diameter is more than 100 linear feet, unless intended for use as cross drain
5. Pipe is not perforated, unless the material is PVC
6. Pipe is intended for applications requiring 100 year design service life as defined in the Florida Department of Transportation Drainage Manual.
The length of each sample pipe section must comprise at least seven regular corrugations (not including the first three corrugations of the pipe on the bell or spigot ends).
485 FY 2026-27
430-9.2 Field Joints: Use gasketed joints to seal side drain, and storm and cross drain.
Use gaskets meeting the requirements of Section 449. Ensure that the pipe manufacturer provides a joint design approved by the Engineer before use.
430-9.2.1 Requirements For Use In Structures With Resilient Connectors:
Use pipe sleeve adapters in accordance with Section 948-2 and 948-7.
430-9.3 Installation Requirements Including Trenching, Foundation and Backfilling
Operations: Check structure shape regularly during backfilling to verify acceptability of the construction method used.
Replace pipe deflected 5% or more of the certified actual mean diameter of the pipe at final inspection at no cost to the Department.
430-10 Desilting Pipe or Concrete Box Culvert.
Desilt pipe culvert and concrete box culvert as designated in the Plans.
430-11 Method of Measurement.
430-11.1 New Pipe Installed by Excavation or Trenching: The quantity of storm and cross drain pipe, storm drain trench, side drain and gutter drain pipe, installed by pipe culvert optional material - excavation or trenching, to be paid for will be plan quantity, in place and accepted. The plan quantity will be determined from the inside wall of the structure and from station/offset location for end treatments as shown in the Plans, along the centerline of the pipe.
Adjustment to bid quantities, prices and payment will not be allowed for increases, decreases, or changes in material or installation requirements due to the use of any optional pipe materials.
If adjustments are required due to Plan errors or omissions or authorized field changes, the plotted material and not the material elected would be used to establish new pay quantities.
Pipe sizes other than round (elliptical/arch) are summarized and paid for using equivalent round pipe diameter.
430-11.2 New Pipe Installed by Jack and Bore: The quantity of storm and cross drain pipe, storm drain trench, side drain and gutter drain pipe, installed by pipe culvert optional material - jack and bore, to be paid for will be the plan quantity, in place and accepted. The measurement and payment will be the plan quantity length of the casing or carrier pipe installed by jack and bore.
Carrier pipe installed through/inside the casing is paid for as pipe culvert optional material – excavation or trenching.
430-11.3 End Treatment: The quantity of all end treatments to be paid for will be the number completed and accepted. For mitered end sections, the measurement will be per each end of pipe. Sod will be paid for in accordance with Section 570.
430-12 Basis of Payment.
430-12.1 General: Prices and payments will be full compensation for all work specified in this Section, including all excavation except the volume included in the items for the grading work on the project, and except for other items specified for separate payment in Section 125; all backfilling material and compaction; disposal of surplus material; and all clearing and grubbing outside of the required limits of clearing and grubbing as shown in the Plans.
No separate payment will be made for bituminous coating, concrete collars, or concrete jackets.
486 FY 2026-27
No payment will be made for failed bore paths, injection of excavatable flowable fill, products taken out of service, or incomplete installations. Payment will include all work and materials necessary for jack and bore, including boring, backfilling, flowable fill, and restoration materials necessary for a complete and accepted installation.
No payment will be made for jack and bore until a Bore Path Report has been submitted to the Engineer.
430-12.2 Removing Existing Pipe: When existing pipe is removed and replaced with new pipe approximately at the same location, the cost of excavating and removing the old pipe and of its disposal will be included in the Contract unit price for clearing and grubbing.
430-12.3 Site Restoration: The cost of restoring the site, as specified in 125-10, that is disturbed, solely for the purpose of constructing pipe culvert, will be included in the Contract unit price for the pipe culvert, unless designated specifically to be paid for under other items.
430-12.4 Plugging Pipes: The cost of temporarily plugging a pipe culvert, either proposed or existing, will be incidental to the contract unit price for new pipe culvert.
The cost of filling and/or plugging an existing pipe culvert that is to be permanently placed out of service will be paid for at the contract unit price for filling and plugging pipe, per cubic yard. Price and payment will be full compensation for flowable fill, masonry, concrete, mortar, and all labor and materials necessary to complete the work.
When the project includes no quantities for new pipe culverts, and temporary plugs are required for existing pipe culverts, the cost will be considered as extra work, in accordance with 4-3.5.
430-12.5 Desilting Pipe: Desilting pipe will be paid for at the contract unit price per foot for each pipe desilted. Price and payment will be full compensation for furnishing all equipment, tools and labor, disposal of silt and debris, and all incidentals necessary for satisfactorily performing the work.
430-12.6 Desilting Concrete Box Culverts: Price and payment will be full compensation for all work required.
430-12.7 Flared End Sections: Price and payment will be full compensation for all concrete, reinforcement, toe walls, and all work and materials required.
430-12.8 Mitered End Sections: Price and payment will be full compensation for all materials, pipe, grates when required, fasteners, reinforcing, connectors, anchors, concrete, sealants, jackets and coupling bands, and all work required.
430-12.9 U-Type Endwalls: Price and payment will be full compensation for all materials concrete, reinforcement, grate, baffles, accessories, and all work required. Fencing, when called for in the Plans, will be paid for under Fencing, Type B, per foot. Rip rap will be paid for in accordance with Section 530.
430-12.10 Straight and Winged Endwalls: Price and payment will be full compensation for all concrete, reinforcement, grate, accessories, and all work and materials required.
430-12.11 Railroad Requirements: Where pipe culvert is constructed under railroad tracks, the Contract unit price for the pipe culvert will include the costs of any jacking operations and the operation of placing the pipe by use of a tunnel liner, (except as specified for unanticipated tunnel liner, in 430-6.5, where reimbursement is to be made for such unanticipated liner), and all other work necessary to meet the requirements of the railroad…