This notice solicits market research and feedback regarding draft requests for proposal for multiple-award indefinite delivery indefinite quantity contracts to support the installation of electric vehicle supply equipment at federal agency locations. The contracts would include design-build capabilities for general construction services.

The draft requests for proposal include a four-zone small business set-aside for the first phase. Each zone would have approximately six contract awards for a total of around 24 small business indefinite delivery indefinite quantity contracts. The zones cover different regions of the United States. A second nationwide phase is also planned, intended for larger and more complex requirements. Responses to provide feedback on the draft requests for proposal and to indicate interest are requested by January 21, 2022. The General Services Administration aims to award first phase contracts in July 2022. The documents seek information on firms' experience and capabilities to inform scope and set-aside determinations.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DRAFT

PBS Governmentwide Multiple-Award IDIQ Contracts for General Construction with Design-Build Capabilities

To Support the Installation of Electric Vehicle Supply Equipment (EVSE) at Federal Agency Locations Throughout the United States Of America

IDIQ Statement of Work

(1) Background

Executive Order 14008 - Tackling the Climate Crisis at Home and Abroad issued on January 27, 2021, outlines the importance of and places significant emphasis on climate change initiatives being launched across the government. GSA has an important and active role to play in many areas including greening Federal buildings and electrifying the Federal Fleet.

Executive Order 14057 - Catalyzing Clean Energy Industries and Jobs Through Federal Sustainability issued on December 8, 2021, sets goals including 100 percent zero-emission vehicle acquisitions by 2035, which will also entail deploying zero-emission vehicle re-refueling infrastructure for the Federal Fleet.

GSA’s Public Buildings Service (PBS) is issuing this contract to prepare governmentwide real estate to support an influx of zero-emission vehicles to the Federal Fleet and provide a streamlined procurement process for federal agencies to support the installation of Electric Vehicle Supply Equipment (EVSE) at Federal locations throughout the United States of America.

These PBS Governmentwide indefinite delivery, indefinite quantity (IDIQ) contracts are established on a geographic zonal basis and are for use by any Federal Agency in both space under GSA’s jurisdiction, custody, or control or non-GSA controlled space.

(2) Contract Services

These construction and design-build IDIQ contracts include architectural, engineering, construction, and other related services necessary to design and to construct EVSE infrastructure improvements and installation, compliant with applicable codes.

Related services include, but are not limited to, feasibility studies, site assessments, site planning, utility coordination, relocation & connections, permitting, testing and inspection during construction, commissioning, and supporting the transition from construction to operations.

Construction and design-build services consist of interior and exterior building construction, and repair and alterations, including but not limited to: electrical, plumbing, mechanical, architectural, landscaping, exterior renovations, demolition services, abatement services (e.g., asbestos, lead, mold, and polychlorinated biphenyls (PCB)), earthwork, pavement repair, and other miscellaneous work.

The work to be performed under the terms of these IDIQ contracts includes, but is not limited to:

installation or modification of electrical service feeds, switchgear, switchboards, panelboards, transformers, conduit, cabling; trenching, coring, road surfaces such as asphalt, concrete and other types of pavement; renovations, site work, signage, new construction, wall partition construction; HVAC ductwork modification and install; lighting installation and modification;

modification of existing building fire sprinkler and fire alarm systems; and other such related work which would be outlined in Task Order and job drawings.

(3) Geographic Zones

The PBS Governmentwide IDIQ contracts include four (4) multiple-award Geographic Zones set-aside for small businesses. The Geographic Zones are as follows:

(4) Contract Type

These are firm-fixed price IDIQ contracts . All construction services to be acquired under the IDIQ contracts will be accomplished by the issuance of individual firm-fixed price Task Orders.

However, as indicated in Statement of Work Section (8), the Task Order Contracting Officer may specify if EVSE and Ancillary Services are to be included within the IDIQ Task Order on a firm-fixed price, labor hour or time-and-material basis. The individual Task Orders to be placed under the IDIQ contracts are generally anticipated to range in dollar value from approximately $50,000 up to $4,000,000. However, Task Orders may be outside of this range. The aggregate maximum order limitation (MOL) is $500 million for the entire duration of all contracts awarded in each of the Geographic Zones. In other words, there is no single MOL per contractor or individual Task Order nor a single MOL per year, other than the MOL of the entire Geographic Zone.

(5) Contracting Authority

These IDIQ contracts will be available for use at Federal locations throughout the United States of America, as indicated above in Section 3, Geographic Zones.

Task Orders may be issued by any warranted PBS Contracting Officer or any other warranted Federal Agency Contracting Officer with authority delegated by the Contracting Officer of the

IDIQ.

(6) Task Order Requirements

Services will be required under these contracts on an as-needed basis. Task Orders will be prepared based on defined statements of work for specific projects and issued as fixed-price Task Orders awarded to the contractor who provides the best value to the Government. The technical specifications, statements of work, drawings and/or other technical documents associated with each Task Order will be issued with the Request for Proposals (RFP).

Each Task Order under this contract will be different and therefore specifications and requirements will be unique to each Task Order. See Attachment (A) for additional information on individual requirements which may be included in a Task Order.

(7) Task Order RFPs

GSA or another Federal Agency Contracting Officer with authority delegated by the Contracting Officer of the IDIQ will issue a Task Order RFP for projects in accordance with FAR 16.505. Task Order RFPs will identify the project delivery method to be used for each project. Typically each Task Order RFP will include a single project; however the Government reserves the right to combine projects into one Task Order RFP dependent upon site location and mission support requirements. Task Order RFPs will specify the evaluation method and basis of award for each Task Order. Each Task Order RFP may require a technical and price proposal or other submittals.

Unless the Task Order Contracting Officer specifies another format, Task Order price proposals shall utilize the line items established in the IDIQ contract and not exceed the line item prices established in the IDIQ contract. For any work that is not covered by line items established in the IDIQ contract, the Task Order Contracting Officer will specify the format of price proposal.

For each Task Order, the designated Contracting Officer will determine the applicable Geographic Zone (Zones A through D).

Competition of Task Order RFPs will be exclusive to the IDIQ contracts awarded within each Geographic Zone.

If applicable, the Task Order RFP will notify all contractors of the estimated magnitude of the project, using the ranges found in FAR 36.204.

Ordering activities will require prospective contractors to identify potential conflicts of interest and address/resolve any concerns prior to any Task Order awards.

Contractors are not obligated to propose on all Task Orders; however, they are required to notify the Task Order Contracting Officer within seven (7) calendar days, unless another timeframe is specified by the Task Order Contracting Officer, if they cannot submit an offer in response to an RFP. Failure to provide this notification may impact future consideration of the contractor for Task Orders and the exercise of any option.

Some Task Orders may include requirements for feasibility studies/site assessments only.

Contractors are advised that, in this event, the completed feasibility studies/site assessments may be included with separate Task Order RFPs under this IDIQ for design-build construction services.

(8) Inclusion of EVSE and Ancillary Services Within Task Order Requirements

A Class Deviation to FAR 51.1 is anticipated that will authorize Contracting Officers to permit contractors to use the Federal Supply Schedule (FSS) “Electric Vehicle Supply Equipment (EVSE) and Ancillary Services” Blanket Purchase Agreements (BPAs) for EVSE products and related services in performing Task Orders under these IDIQ contracts.

IDIQ contractors must utilize the FSS EVSE and Ancillary Services BPAs for any EVSE and Ancillary Services specified in the Task Order requirements following the process described in this Section.

The Task Order Contracting Officer may specify if EVSE and Ancillary Services are to be included within the IDIQ Task Order on a firm-fixed price, labor hour or time-and-material basis.

This includes, but is not limited to all types of electric vehicle charging hardware for governmentwide use including existing and emerging technologies; non-ownership charging options such as Charging as a Service; and ancillary services to include but not be limited to EVSE site assessments, consulting services, planning and make-ready services, network data plans, data network services, smart metering, power management and distributed energy software, extended warranty, operation and maintenance plans, and integrated energy/battery storage solutions. Network plan and data package services should be provided using available vendor agnostic protocols such as Open Charge Point Protocol ( OCPP) and Open Charge Point

Interface ( OCPI).

IDIQ contractors placing orders under the FSS EVSE and Ancillary Services BPAs must:

● Identify and separate those ancillary supplies/services that are proposed to be purchased under the FSS EVSE and Ancillary Services BPAs on the quote submitted to the Government and on the subsequent invoice

● Purchase supplies and/or services at the FSS contract price (or lower)

● If supplies and/or services are provided by the FSS EVSE and Ancillary Services BPA contractor at lower than the contract price, the IDIQ contractor must pass on the savings by invoicing the Government accordingly

● Provide a copy of the written authorization from the Government with each applicable order to the FSS EVSE and Ancillary Services BPA contractor

● Ensure that the IDIQ contractor’s IDIQ contract number is on each order issued to the FSS EVSE and Ancillary Services BPA contractor

● Remit full payment to the FSS EVSE and Ancillary Services BPA contractor

● Submit documentation of the transmittal of full payment to the FSS EVSE and Ancillary

Services BPA contractor when invoicing the Government

● Follow any applicable FSS ordering procedures in addition to procedures outlined in

FAR 8.405-3(c)(2), Ordering from BPAs, Multiple-award BPAs, and FAR Part 51.

(9) Bid Guarantees

When applicable (see FAR 28.101-1), Bid Guarantees are required to be submitted with Task Order offers in accordance with FAR 52.228-1, Bid Guarantee.

(10) Task Order Award and Performance and Payment Bonds for Task Orders

A Notice to Proceed (NTP) for Task Orders under $35,000 may be issued upon award of the Task Order. For Task Orders valued at $35,000 through $150,000, a form of payment protection must be provided and accepted by the Government (payment bond or irrevocable letter of credit) before an NTP can be issued. For Task Orders over $150,000, both performance and payment bonds must be received and accepted by the Government prior to issuance of the NTP. These dollar values are stated in FAR 28.102-1 and FAR 28.102-2, but may change over the life of the contract.

FAR 52.228-13 applies to orders which exceed $35,000, but do not exceed $150,000.00. FAR 52.228-15 shall apply to all orders expected to exceed $150,000.00. Payment and/or performance bonds shall be submitted no later than ten (10) calendar days after Task Order award, unless another timeframe is specified by the Task Order Contracting Officer. The contractor will be required to submit proof of payment for the bonds for individual Task Orders.

The requirements for Performance and Payment Bonds for Task Order amounts may change over the life of the Contract.

(11) Post Task Order Award Coordination

A coordination meeting will be scheduled by the Government to begin immediately following the Task Order award. Pre-construction conferences for each Task Order may be scheduled by the Government project team. Attendance, in person, by the contractor is expected unless otherwise noted in the Task Order requirements. Key subcontractors are encouraged to attend.

(12) Construction Wage Rate Requirements

The contractor will be required to pay their employees based on the Construction Wage Rate Requirements statute (formerly known as the Davis Bacon Act) for projects which fall under that statute. The applicable wage determination will be incorporated into each Task Order.

(13) Labor and Payroll Records

The contractor is responsible for timely, complete and correct submission of required certified labor and payroll records for each Task Order. The contractor is responsible for screening all subcontractor-furnished certified labor and payroll records prior to submitting to the Task Order Contracting Officer. The contractor should furnish a log of corresponding subcontract payrolls, in addition to its own, for each project. For subcontracted design and/or engineering efforts, an invoice of the labor categories used and hours billed may be required as supporting documentation.

(14) Contract Manager

The primary Contract Manager shall be designated as the central point of contact, tasked with serving as an overall manager of ongoing projects responsible to the Government for scheduling/coordinating all project and contract deliverables and activities. The primary Contract Manager should be an individual with administrative oversight responsibilities.

The primary Contract Manager shall ensure that a written quarterly report is provided to the IDIQ Contracting Officer beginning 3 months after contract award. The quarterly report shall summarize the contract status identifying both pending and issued Task Orders. The report shall also provide a summary indicating the value of the pending and issued Task Orders and identify the contracting activity that has issued the pending and issued Task Orders.

(15) Changes to the Key Personnel

There shall be no changes to this IDIQ contract’s Key Personnel during the entire term of this contract, but for circumstances beyond the contractor’s control such as death, disability, termination, resignation, or illness. Based on the above, should it become necessary to substitute such Key Personnel, the contractor shall submit to the Contracting Officer, in writing, the detailed experience and qualifications of the proposed Key Personnel (and firm, as appropriate) for the Contracting Officer’s approval. All such proposed substitutions shall possess, at a minimum, qualifications and experience equal to or greater than the Key Personnel proposed to be replaced.

(16) Occupying Agency Security Requirements

The contractor will be required to comply with the security requirements imposed by occupying agencies including obtaining the necessary security clearances for personnel assigned to work in the space.

(17) Travel

The contractor is responsible for all costs necessary to support the requirements of each Task Order. If there are circumstances which require one or more contractor or subcontractor staff to travel for work, then the need shall be described in the narrative that is submitted with the Task Order proposal pricing.

(18) As-Built Drawings

The contractor is required to provide as-built drawings in the format specified in each Task Order.

(19) Adherence to Established Standards

Adherence to general requirements associated with the base IDIQ contract is required. GSA design specification PBS-P100 (Facilities Standards for the Public Buildings Service) has basic design requirements for facilities under the jurisdiction, custody and control of GSA and can be found at https://www.gsa.gov/real-estate/design-construction/engineering-and-architecture/facilities-stand ards-p100-overview . Unless notified otherwise by the Task Oder Contracting Officer, the contract must comply with the latest version in effect as of the effective date of each Task Order.

Additionally, ordering agency design requirements will be provided with each Task Order RFP, as applicable.

(20) Contractor Response for Warranty Calls

The contractor is expected to respond to the designated government representative within 48 hours to any issued warranty call for work completed under the contract. Warranty calls for installed work or materials may be made by the original Project Manager, Contracting Officer, or the Property Manager of the facility. Warranty call site visits will be made at no additional expense to the government.

https://www.gsa.gov/real-estate/design-construction/engineering-and-architecture/facilities-standards-p100-overview https://www.gsa.gov/real-estate/design-construction/engineering-and-architecture/facilities-standards-p100-overview

(21) Sustainable Construction

GSA has adopted a robust approach to sustainable construction efforts. Sustainable Construction includes the identification of designated products as “Key Sustainable Products” (KSP), waste stream management, high levels of recycled content, low use of virgin material, energy efficient water and electrical components, and low or no volatile organic emissions.

Requirements for the use and/or exemption of KSP designated materials will be identified in each Task Order Statement of Work.

(22) Historic Preservation Considerations

Historic Preservation : The National Historic Preservation Act of 1966 mandates that federal agencies use historic properties to the greatest extent possible and strive to rehabilitate them in a manner that preserves their architectural character. Task Orders under this IDIQ contract may affect historic resources and, therefore, require consideration of historic preservation measures.

When applicable, the contractor shall work with Federal and State Historic Preservation Officers and other consulting parties to ensure that projects are designed and constructed in accordance with the Secretary of the Interior’s Standards for Rehabilitation and Guidelines for Rehabilitating Historic Buildings. The contractor shall prepare the Section 106 Report and supporting documents to submit to the consulting parties for review and comment.

Work in Legacy (Non-Historic) Buildings : Buildings that are deemed by the Government to be “exceptional” and/or determined to be eligible for listing the historic register require innovative solutions that can preserve the character of the buildings while resolving issues of functionality, cost, safety, and quality of space and public experience.

(23) Supply Chain Risk Management (SCRM)

U.S. adversaries have, and will continue to attack our nation's supply chains and compromise Government systems, capitalizing on security weaknesses in U.S. companies and third party affiliates. It is incumbent on GSA's industrial base to implement vigilant SCRM procedures. This IDIQ requires awardees to complete a Cyber Supply Chain Risk Management (C-SCRM) plan in the format provided.

IDIQ contractors will be required to update their C-SCRM Plan annually and to submit these updates to the COR no later than 30 days after the end of each contract year, over the life of the IDIQ contract. The C-SCRM Plan must be completed using the attachment “PBS EV - Vendor SCRM Plan Template”. Specific instructions are noted within the template.

As part of GSA’s C-SCRM Program, third-party vendor risk illumination tools may be utilized.

Please note, ordering agencies may have additional SCRM requirements at the Task Order level and will specify any additional requirements in the Task Order request.

Attachment (A)

Typical Requirements for a Task Order

Feasibility Study/Site Assessment , may include but is not limited to :

● Meeting with Government to review expectations and scope of work

○ Meeting with Facilities Management team to gain building and systems information

● Conducting an investigation, including an on-site survey to examine existing conditions

● Performing a pre-alteration (hazardous materials) assessment

● Identifying current electric utility service capability

● Performing building load calculations to determine electrical capacity

● Identifying existing code violations related to project work

● Identifying available incentives and rebate programs

● Developing conceptual alternatives, considering

○ Required charging levels (e.g., Level 1, Level 2, Direct Current Fast Charging)

○ Mounting systems

○ Location and number of charging stations (power, accessibility, and placement)

○ Metering

○ Communication and network protocols

○ Visibility, signage and safety

○ Clearances and equipment protection (e.g., wheel stops, bollards)

○ Stormwater management

○ Parking space design and pedestrian flow

○ Scope and scale of required infrastructure upgrades

● Developing construction cost estimates and schedules

● Performing financial and feasibility analyses

● Identifying and justifying a preferred alternative (final recommendation)

● Providing reports and presentations

Design Services , may include but is not limited to :

● Completing and obtaining necessary permits

● Establishing project duration/schedule

● Coordinating with the local utility for proposed EVSE infrastructure

● Coordinating available incentives and rebates

● Developing load control strategies

● Preparing conceptual, design development and construction document submissions, which may include:

○ Site plans showing property extent (property lines, parking areas, structures)

○ Electrical plans showing all electrical system elements (single line drawings, EVSE locations, overcurrent protection devices, sub panels, disconnects, conduit sizes and types, conductor sizes and types, site lighting)

○ Trenching details

○ Structural plans (installation mounting methods, trenching, bollards)

○ Architectural and Civil plans (site slopes, surface conditions, access paths, signage, parking, paving, EVSE protection)

○ Phasing plans

○ Specifications

○ Calculations as required

● Addressing General Requirements thoroughly

● Performing code reviews, quality control reviews, constructability reviews, and design reviews

● Planning construction work sequencing

● Developing submittal schedule

Construction , may include but is not limited to :

● Completing the subcontractor buyout phase

● Leading and documenting scope discussions with subcontractors and the Government

● Submitting contractual/Agency RFI’s

● Reviewing and approving submittals (and coordinating with the Government)

● Executing the Quality Control Plan

● Coordinating with the utility company for connections and utility markings

● Coordinating incentive and rebate programs

● Coordinating with building managers and tenants for scheduling work

● Securing the construction area appropriately (e.g., temporary fencing, barriers, signage)

● Coordinating equipment deliveries and on-site storage of materials

● Coordinating shutdowns/power outages

● Managing self-performed and all trades to execute the work in accordance with the construction documents

● Installing EVSE per manufacturer installation requirements

● Coordinating Agency IT, communication, and networking requirements

● Performing finish work to repair existing surfaces, infrastructure, landscaping, and parking lot striping

● Scheduling final inspections with AHJ and participating in punch list activities

● Programming and activating EVSE

Testing / Commissioning , may include but is not limited to :

● Executing testing and commissioning requirements per Quality Assurance and Commissioning Plans and manufacturer recommendations

● Ensuring work is compliant with all applicable governing documents/codes (e.g., PBS-P100, IBC, NEC, NECA, NETA, NFPA, Agency requirements).

Training, Operation and Maintenance (O&M) , may include but is not limited to :

● Providing comprehensive O&M manuals and warranty documents during close out process

● Ensuring any warranty documents provided have clear timelines associated with them and contact information is understood

● Coordinating with local O&M contractor to ensure inclusion of any EVSE into the O&M contracts and systems (e.g., National Computerized Maintenance Management System (NCMMS) and the NCMMS Asset Uploader template)

● Provide onsite training to a variety of users including building and maintenance staff, customers and end users