This Statement of Work (SOW) is issued by Brookhaven Science Associates, LLC for the U.S. Department of Energy, detailing the fabrication and assembly of the LT-EL-BL-PD-PDU-0101 M-Drive Power System Rev A. The scope requires a contractor to provide all personnel, labor, equipment, and supplies to fabricate, assemble, and test 20 units of the power system. Specific requirements include machining and silk screen printing of surfaces, functional testing, quality verification, and procurement of materials and equipment according to provided specifications. BNL NSLS-II will supply the documentation for assembly, which is included in attached zip files. The project has a single task of assembling and submitting the completed unit assembly, with the document signed by Dyon Buitenkamp from Brookhaven National Laboratory.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date: 12/11/25

Brookhaven Science Associates, LLC Building 741 P.O. Box 5000 Upton, NY 11973-5000 Phone 631.344.5092 Email: dbuitenka@bnl.gov managed by Brookhaven Science Associates for the U.S. Department of Energy

Statement of Work Title: LT-EL-BL-PD-PDU-0101 M-Drive Power System

Overview: Fabrication and Assembly of LT-EL-BL-PD-PDU-0101 M-Drive Power System Rev A

Scope of Work: The Contractor shall provide all personnel, labor, equipment and supplies to fabricate, assemble and test 20pcs LT-EL-BL-PD-PDU-0101 M-Drive Power System Rev A in accordance with the specifications included herein.

• BNL NSLS-II – supplies the documentation for assembly of 20 units (the documentation is in the zip files attached)

• The vendor will provide all personnel, labor, equipment, materials and supplies to fabricate, assemble and test these units. This includes the following:

o Machining and silk screen printing of surfaces as required.

o Functional testing and quality verification.

o Procurement of all required materials and equipment per specifications.

Applicable Documents:

Document Description .zip file LT-EL-BL-PD-PDU-0101 M-Drive Power System Rev A

Project Task(s):

Task No.

Description Due Date

1 Assemble and submit completed unit assembly

Signature: _______Dyon Buitenkamp_______