DRAFT - Specifications RVKQ 24-0003 Replace Building 2503 Roof - NFARS 17DEC24.pdf
PDF 1 MB Posted
- Attached to
- Synopsis - Repair Army Reserve Roof at B2503
- Solicitation number
- RVKQ24-0003
About this file
These are draft specifications for a Design-Build roofing project at Building 2503, an Army Reserve building located at Niagara Falls Air Reserve Station in New York. The project involves completely replacing the existing asphalt shingle roof with a new standing seam metal roofing system, including all associated components such as flashing, parapet wall flashing, venting, ice and water shield, underlayment, gutter/downspout systems, lightning protection, snow rail systems, and fall protection systems. The specifications detail technical requirements for a comprehensive, watertight roofing solution, with specific emphasis on panel profile, material specifications, finish quality, and installation standards. The project is designated with the number RVKQ 24-0003 and is dated 17 December 2024, prepared by the 914 MSG/CEC unit.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| DRAFT - SOW_RVKQ_24-0003_Replace Facility Roof at B2503 10DEC24.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Replace Facility Roof at Building 2503 Army Reserve Building Niagara Falls Air Reserve Station (NFARS) Niagara Falls, NY 14304 Project Number: RVKQ 24-0003
Design-Build Project
Specifications 17 December 2024
Prepared by:
914 MSG/CEC
2405 Franklin Drive Niagara Falls, NY 14304-5063 For a Design-Build Roofing Project
DRAFT
SECTION 01 11 00 Page 1
Niagara Falls Air Reserve Station
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 45 00.00 10 QUALITY CONTROL
01 57 20.00 10 ENVIRONMENTAL MANAGEMENT AND PROTECTION
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
07 41 13 METAL ROOF PANELS
-- End of Project Table of Contents --
SECTION 01 11 00 Page 2
PART 1 GENERAL
1.1 REFERENCES
SECTION 01 11 00
SUMMARY OF WORK
08/11
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E2114 (2008) Standard Terminology for
Sustainability Relative to the Performance of Buildings
GREEN BUILDING INITIATIVE (GBI)
Green Globes (2004) Green Globes(tm) US Green Building
Rating System
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
Energy Star (1992; R 2006) Energy Star Energy Efficiency Labeling System
U.S. GREEN BUILDING COUNCIL (USGBC)
LEED NC (2009) Leadership in Energy and
Environmental Design(tm) New Construction Rating System
1.2 DEFINITIONS
Definitions pertaining to sustainable development are as defined in ASTM E2114 and as specified.
a. "Environmentally preferable products" have a lesser or reduced effect on the environment in comparison to conventional products and services. This comparison may consider raw materials acquisition, production, manufacturing, packaging, distribution, reuse, operation, maintenance, or disposal of the product.
b. "Indoor environmental quality" is the physical characteristics of the building interior that impact occupants, including air quality, illumination, acoustics, occupant control, thermal comfort, daylighting, and views.
c. "Operational performance" is the functional behavior of the building as a whole or of the building components.
d. "Sustainability" is the balance of environmental, economic, and societal considerations.
SECTION 01 11 00 Page 3
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Submit the following items to the Contracting Officer:
Utility Outage Requests Utility Connection Requests Welding Permits
1.4 WORK COVERED BY CONTRACT DOCUMENTS
1.4.1 Project Description
The work includes the replacement of entire roofing systems at Niagara Falls Air Reserve Station, Building 2503, summarized as follows:
Demolish asphalt shingle roof systems, and replace with standing seam metal roofing systems.
Roofing systems for Building 2503 shall include all flashing, parapet wall flashing caps (where applicable), venting, self-adhered ice and water shield/protection, self-adhered underlayment, gutter/downspout systems, lightning protection systems, snow rail systems, fall protection systems, and all necessary appurtenances for a complete and watertight system.
The Design shall specify phases of construction.
The contractor shall comply with Base regulations and requirements.
1.4.2 Location
The work shall be located at the Niagara Falls Air Reserve Station, Building 2503, Niagara Falls, NY 14304.
1.5 WORK RESCHEDULING
Contractor shall allow for a maximum of 15 calendar days where construction activity is prohibitive.
Normal duty hours for work shall be from 7:15 a.m. to 4 p.m., Monday through Friday. Requests for additional work shall require written approval from the Contracting Officer 15 days in advance of the proposed work period.
1.6 PROJECT ENVIRONMENTAL GOALS
Contractor shall distribute copies of the Environmental Goals to each subcontractor and the Contracting Officer. The overall goal for design, construction, and operation is to produce a building that meets the functional program needs and incorporates the principles of sustainability. Specifically:
SECTION 01 11 00 Page 4
a. Preserve and restore the site ecosystem and biodiversity; avoid site degradation and erosion. Minimize offsite environmental impact.
b. Use the minimum amount of energy, water, and materials feasible to meet the design intent. Select energy and water efficient equipment and strategies.
c. Use environmentally preferable products and decrease toxicity level of materials used.
d. Use renewable energy and material resources.
e. Optimize operational performance (through commissioning efforts) in order to ensure energy efficient equipment operates as intended.
Consider the durability, maintainability, and flexibility of building systems.
f. Manage construction site and storage of materials to ensure no negative impact on the indoor environmental quality of the building.
g. Reduce construction waste through reuse, recycling, and supplier take-back.
1.7 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area.
Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.8 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.9 ON-SITE PERMITS
1.9.1 Utility Outage Requests and Utility Connection Requests
Notify the Contracting Officer at least 72 hours prior to starting excavation work. Contractor is responsible for marking and verifying all utilities not marked.
The Contractor shall verify the elevations of existing piping and utilities not indicated or specified to be removed, but indicated in locations to be transversed by piping, ducts, and other work to be installed.
SECTION 01 11 00 Page 5
Work shall be scheduled to hold outages to a minimum.
Requests for utility outages and connections shall be made in writing to the Contracting Officer at least 7 calendar days in advance of the time required. Each request shall state the system involved, area involved, approximate duration of outage, and the nature of work involved.
1.9.2 Borrow, Excavation, Welding, and Burning Permits
ACTIVITY SUBMISSION DATE SUBMISSION FORM
Welding Permits 7 calendar days prior to work Letter Format
Permits shall be posted at a conspicuous location in the construction area.
Burning of trash or rubbish is not permitted at Niagara Falls ARS .
1.10 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of any excavation by contacting the Contracting Officer 15 calendar days in advance. Scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed.
1.10.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
-- End of Section – DRAFT
SECTION 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
11/11
1.1 CONTRACTOR ACCESS AND USE OF PREMISES
1.1.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification.
1.1.1.1 Subcontractors and Personnel Contacts
Furnish a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.1.1.2 Identification Badges and Installation Access
The Contractor shall obtain access to the installation for all personnel by submitting to requisite background checks by the Base Security Forces.
Submit all required information on an Entry Access List to the Contracting Officer at least 7 calendar days prior to requiring access. All personnel shall obtain access badges through the Base Visitor Center and present identification, vehicle registration, and proof of vehicle insurance. As of October 1, 2021, all personnel requesting access shall present personal identification meeting federal REAL ID standards.
1.1.1.3 No Smoking Policy
Smoking is prohibited within and outside of all buildings except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.1.2 Working Hours
Regular working hours shall consist of an 7:15 a.m. and 4:00 p.m., Monday through Friday, excluding Government holidays.
1.1.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number, and project title.
SECTION 01 14 00 Page 2
Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer.
1.1.4 Occupied and Existing Buildings
The Contractor shall be working on an existing building which is occupied.
The existing buildings and their contents shall be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
Provide dust covers or protective enclosures to protect existing work that remains and Government material located in the hangar bay during the construction period.
Leave attached equipment in place, and protect it against damage, or temporarily disconnect, relocate, protect, and reinstall it at the completion of the work.
The Government will remove and relocate other Government property in the areas of the building scheduled to receive work.
1.1.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and fire suppression systems shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."
d. Operation of Station Utilities: The Contractor shall not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor shall notify the Contracting Officer giving reasonable advance notice when such operation is required.
Not Used
-- End of Section --
SECTION 01 30 00 Page 1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/11
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
15 CFR 772 Definition of Terms
15 CFR 773 Special Licensing Procedures
1.2 SUBMITTALS
approval. The following shall be submitted in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
View location map; G
Progress and completion pictures; G
1.3 VIEW LOCATION MAP
Submit to the Contracting Officer, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.4 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 16 digital photographs each week throughout the entire project from a minimum of eight views from points located by the Contracting Officer. Submit a view location sketch indicating points of view. Indicate photographs demonstrating environmental procedures. Photographs for each month shall be in a separate monthly directory and each file shall be named to indicate its location on the view location sketch. All file names shall include a date designator. Cross reference submittals in the appropriate daily report. Photographs shall be provided for unrestricted use by the Government. Submit photographs via DoD Safe.
SECTION 01 30 00 Page 2
1.5 SUPERVISION
The Contractor shall have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual shall also have fluent English communication skills.
1.6 PRECONSTRUCTION CONFERENCE
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work shall also attend.
1.7 PARTNERING
To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the Supported Command, the End User (who will occupy the facility), the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays on schedule.
The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.
1.7.1 Informal Partnering
The Contracting Officer will organize the Partnering Sessions with key personnel of the project team, including Contractor personnel and Government personnel.
The Initial Partnering session should be a part of the Pre-Construction Meeting. Partnering sessions will be held at a location agreed to by the Contracting Officer and the Contractor (typically a conference room provided by the PWD FEAD/ROICC office or the Contractor).
The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the Contracting Officer.
The Partners will determine the frequency of the follow-on sessions.
1.8 AVAILABILITY OF CADD DRAWING FILES
Because of building ages and other factors, there is limited availability of CADD drawing files for buildings referenced in this project. Therefore, the Government will not be able to provide CADD drawing files for all buildings. Scanned copies of hand-drawn plans in PDF format area available for most buildings without CADD files, although detail and clarity may be limited. Hardcopy plans and drawings, which are available, may be viewed in BCE Office. Plans provided may be outdated, obsolete, or in error.
SECTION 01 30 00 Page 3
The Contractor is responsible for verifying all dimensions, drawings, configurations, and any other information provided in drawings (CADD, PDF, or hardcopy). In the event that any electronic data files, CADD files, or drawings are made available by the Government to the Contractor, they may only be used in preparation of construction data related to the referenced contract subject to the following terms and conditions.
Drawings or data contained in electronic files shall not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these drawings, electronic data files, or CADD files. The Contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These drawings, electronic data or CADD files provided by the Government to the Contractor are not construction documents. Differences may exist between the drawings, electronic data files and CADD files, and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the drawings, electronic data files, or CADD files, nor does it make representation to the compatibility of these files with the Contractors hardware or software. The Contractor is responsible for determining the accuracy of any drawings, electronic data files, or CADD files supplied by the Government. Use of these files or drawings does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.
If the Contractor uses, duplicates and/or modifies these drawings, electronic data files, or CADD files provided by the Government, for use in producing construction data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.
1.9 ELECTRONIC MAIL (E-MAIL) ADDRESS
The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats.
Within 10 days after contract award, the Contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes, terrorist threats, etc.
Multiple email address will not allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to this email address.
SECTION 01 35 26 Page 1
SECTION 01 35 26
GOVERNMENTAL SAFETY REQUIREMENTS
02/12
AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)
ASSE/SAFE A10.32 (2004) Fall Protection
ASSE/SAFE A10.34 (2001; R 2005) Protection of the Public on or Adjacent to Construction Sites
ASSE/SAFE Z359.1 (2007) Safety Requirements for Personal Fall Arrest Systems, Subsystems and Components
ASME INTERNATIONAL (ASME)
ASME B30.22 (2010) Articulating Boom Cranes
ASME B30.3 (2009) Tower Cranes
ASME B30.5 (2011) Mobile and Locomotive Cranes
ASME B30.8 (2010) Floating Cranes and Floating Derricks
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION (NASA)
NASA NPG 8621.1 (2004a) NASA Mishap Reporting, Investigating and Record Keeping Policy
NASA NPG 8715.3 (2004) NASA Safety Manual
NASA-STD 8719.12 (2010) Safety Standard for Explosives, Propellants, and Pyrotechnics
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 10 (2010; Errata 2012) Standard for Portable
Fire Extinguishers
NFPA 241 (2009) Standard for Safeguarding Construction, Alteration, and Demolition Operations
NFPA 306 (2009) Standard for Control of Gas Hazards on Vessels
NFPA 51B (2009; TIA 09-1) Standard for Fire
SECTION 01 35 26 Page 2
Prevention During Welding, Cutting, and Other Hot Work
NFPA 70 (2011; Errata 2 2012) National Electrical
Code
NFPA 70E (2012) Standard for Electrical Safety in the Workplace
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements
Manual
10 CFR 20 Standards for Protection Against Radiation
29 CFR 1910 Occupational Safety and Health Standards
29 CFR 1910.146 Permit-required Confined Spaces
29 CFR 1910.147 Control of Hazardous Energy (Lock Out/Tag Out)
29 CFR 1915 Confined and Enclosed Spaces and Other Dangerous Atmospheres in Shipyard Employment
29 CFR 1919 Gear Certification
29 CFR 1926 Safety and Health Regulations for Construction
29 CFR 1926.1400 Cranes & Derricks in Construction
29 CFR 1926.16 Rules of Construction
29 CFR 1926.450 Scaffolds
29 CFR 1926.500 Fall Protection
CPL 2.100 (1995) Application of the Permit-Required Confined Spaces (PRCS) Standards, 29 CFR 1910.146
U.S. NAVAL FACILITIES ENGINEERING COMMAND (NAVFAC)
NAVFAC P-307 (2009; Change 1 Mar 2011; Change 2 Aug
2011)Management of Weight Handling Equipment
a. High Visibility Accident. Any mishap which may generate publicity or high visibility.
SECTION 01 35 26 Page 3
b. Medical Treatment. Treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even through provided by a physician or registered personnel.
c. Recordable Injuries or Illnesses. Any work-related injury or illness that results in:
(1) Death, regardless of the time between the injury and death, or the length of the illness;
(2) Days away from work (any time lost after day of injury/illness onset);
(3) Restricted work;
(4) Transfer to another job;
(5) Medical treatment beyond first aid;
(6) Loss of consciousness; or
(7) A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in
(1) through (6) above.
d. "USACE" property and equipment specified in USACE EM 385-1-1 should be interpreted as Government property and equipment.
e. Weight Handling Equipment (WHE) Accident. A WHE accident occurs when any one or more of the eight elements in the operating envelope fails to perform correctly during operation, including operation during maintenance or testing resulting in personnel injury or death;
material or equipment damage; dropped load; derailment; two-blocking;
overload; or collision, including unplanned contact between the load, crane, or other objects. A dropped load, derailment, two-blocking, overload and collision are considered accidents even though no material damage or injury occurs. A component failure (e.g., motor burnout, gear tooth failure, bearing failure) is not considered an accident solely due to material or equipment damage unless the component failure results in damage to other components (e.g., dropped boom, dropped load, roll over, etc.) Any mishap meeting the criteria described above shall be documented in both the Contractor Significant Incident Report (CSIR) and using the NAVFAC prescribed Navy Crane Center (NCC) form submitted within five days both as provided by the approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
Government acceptance, as defined in EM 385-1-1, is required for submittals with a "G, A" designation.
SECTION 01 35 26 Page 4
Accident Prevention Plan (APP); G
Activity Hazard Analysis (AHA); G
Crane Critical Lift Plan; G
Proof of qualification for Crane Operators; G
SD-06 Test Reports
Notifications and Reports; G
Submit reports as their incidence occurs, in accordance with the requirements of the paragraph, "Notifications and Reports."
Accident Reports; G
Crane Reports; G
SD-07 Certificates
Confined Space Entry Permit; G
Hot work permit; G
License Certificates; G
Contractor Safety Self-Evaluation Checklist; G
Certificate of Compliance (Crane); G
Submit one copy of each permit/certificate attached to each Daily Quality Control Report.
1.4 REGULATORY REQUIREMENTS
In addition to the detailed requirements included in the provisions of this contract, comply with the most recent addition of USACE EM 385-1-1, and the following federal, state, and local laws, ordinances, criteria, rules and regulations. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work. Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern.
1.5 SITE QUALIFICATIONS, DUTIES AND MEETINGS
1.5.1 Personnel Qualifications
1.5.1.1 Site Safety and Health Officer (SSHO)
The SSHO must meet the requirements of EM 385-1-1 section 1 and ensure that the requirements of 29 CFR 1926.16 are met for the project. Provide a Safety oversight team that includes a minimum of one (1) person at each project site to function as the Site Safety and Health Officer (SSHO).
SECTION 01 35 26 Page 5
The SSHO or an equally-qualified Designated Representative/alternate shall be at the work site at all times to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan. The SSHO's training, experience, and qualifications shall be as required by EM 385-1-1 paragraph 01.A.17, entitled SITE SAFETY AND HEALTH OFFICER (SSHO), and all associated sub-paragraphs.
A Competent Person shall be provided for all of the hazards identified in the Contractor's Safety and Health Program in accordance with the accepted Accident Prevention Plan, and shall be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. Provide the credentials of the Competent Persons(s) to the the Contracting Officer for acceptance in consultation with the Safety Office.
1.5.1.1.1 Contractor Quality Control (QC) Person:
The Contractor Quality Control Person can be the SSHO on this project.
1.5.1.2 Crane Operators
Meet the crane operators requirements in USACE EM 385-1-1, Section 16 and Appendix I. In addition, for mobile cranes with Original Equipment Manufacturer (OEM) rated capacitates of 50,000 pounds or greater, designate crane operators as qualified by a source that qualifies crane operators (i.e., union, a government agency, or an organization that tests and qualifies crane operators). Provide proof of current qualification.
1.5.2 Personnel Duties
1.5.2.1 Site Safety and Health Officer (SSHO)
The SSHO shall:
a. Conduct daily safety and health inspections and maintain a written log which includes area/operation inspected, date of inspection, identified hazards, recommended corrective actions, estimated and actual dates of corrections. Attach safety inspection logs to the Contractors' daily production report.
b. Conduct mishap investigations and complete required reports. Maintain the OSHA Form 300 and Daily Production reports for prime and sub-contractors.
c. Maintain applicable safety reference material on the job site.
d. Attend the pre-construction conference, pre-work meetings including preparatory inspection meeting, and periodic in-progress meetings.
e. Implement and enforce accepted APPS and AHAs.
f. Maintain a safety and health deficiency tracking system that monitors outstanding deficiencies until resolution. Post a list of unresolved safety and health deficiencies on the safety bulletin board.
g. Ensure sub-contractor compliance with safety and health requirements
SECTION 01 35 26 Page 6
h. Maintain a list of hazardous chemicals on site and their material safety data sheets.
Failure to perform the above duties will result in dismissal of the superintendent, QC Manager, and/or SSHO, and a project work stoppage.
The project work stoppage will remain in effect pending approval of a suitable replacement.
1.5.3 Meetings
1.5.3.1 Preconstruction Conference
a. Contractor representatives who have a responsibility or significant role in accident prevention on the project shall attend the preconstruction conference. This includes the project superintendent, site safety and health officer, quality control supervisor, or any other assigned safety and health professionals who participated in the development of the APP (including the Activity Hazard Analyses (AHAs) and special plans, program and procedures associated with it).
b. Discuss the details of the submitted APP to include incorporated plans, programs, procedures and a listing of anticipated AHAs that will be developed and implemented during the performance of the contract. This list of proposed AHAs will be reviewed at the conference and an agreement will be reached between the Contractor and the Contracting Officer's representative as to which phases will require an analysis. In addition, establish a schedule for the preparation, submittal, review, and acceptance of AHAs to preclude project delays.
c. Deficiencies in the submitted APP will be brought to the attention of the Contractor at the preconstruction conference, and the Contractor shall revise the plan to correct deficiencies and re-submit it for acceptance. Do not begin work until there is an accepted APP.
1.6 ACCIDENT PREVENTION PLAN (APP)
Use a qualified person to prepare the written site-specific APP. Prepare the APP in accordance with the format and requirements of USACE EM 385-1-1 and as supplemented herein. Cover all paragraph and subparagraph elements in USACE EM 385-1-1, Appendix A, "Minimum Basic Outline for Accident Prevention Plan". Specific requirements for some of the APP elements are described below. The APP shall be job-specific and address any unusual or unique aspects of the project or activity for which it is written. The APP shall interface with the Contractor's overall safety and health program. Include any portions of the Contractor's overall safety and health program referenced in the APP in the applicable APP element and made site-specific. The Government considers the Prime Contractor to be the "controlling authority" for all work site safety and health of the subcontractors. Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out. The APP shall be signed by the person and firm (senior person) preparing the APP, the Contractor, the on-site superintendent, the designated site safety and health officer, the Contractor Quality control Manager, and any designated CSP or CIH.
SECTION 01 35 26 Page 7
Submit the APP to the Contracting Officer 15 calendar days prior to the date of the preconstruction conference for acceptance. Work cannot proceed without an accepted APP.
Once accepted by the Contracting Officer, the APP and attachments will be enforced as part of the contract. Disregarding the provisions of this contract or the accepted APP will be cause for stopping of work, at the discretion of the Contracting Officer, until the matter has been rectified.
Once work begins, changes to the accepted APP shall be made with the knowledge and concurrence of the Contracting Officer, project superintendent, SSHO and quality control manager. Should any severe hazard exposure, i.e. imminent danger, become evident, stop work in the area, secure the area, and develop a plan to remove the exposure and control the hazard. Notify the Contracting Officer within 24 hours of discovery. Eliminate/remove the hazard. In the interim, take all necessary action to restore and maintain safe working conditions in order to safeguard onsite personnel, visitors, the public (as defined by ASSE/SAFE A10.34,) and the environment.
Copies of the accepted plan will be maintained at the Contracting Officer's office and at the job site.
Continuously review and ammend the APP, as necessary, throughout the life of the contract. Incorporate unusual or high-hazard activities not identified in the original APP as they are discovered.
1.6.1 EM 385-1-1 Contents
In addition to the requirements outlined in Appendix A of USACE EM 385-1-1, the following is required:
a. Names and qualifications (resumes including education, training, experience and certifications) of all site safety and health personnel designated to perform work on this project to include the designated site safety and health officer and other competent and qualified personnel to be used such as CSPs, CIHs, STSs, CHSTs. Specify the duties of each position.
b. Qualifications of competent and of qualified persons. As a minimum, designate and submit qualifications of competent persons for each of the following major areas: excavation; scaffolding; fall protection;
hazardous energy; confined space; health hazard recognition, evaluation and control of chemical, physical and biological agents;
personal protective equipment and clothing to include selection, use and maintenance.
c. Confined Space Entry Plan. Develop a confined and/or enclosed space entry plan in accordance with USACE EM 385-1-1, applicable OSHA standards 29 CFR 1910, 29 CFR 1915, and 29 CFR 1926, OSHA Directive CPL 2.100, and any other federal, state and local regulatory requirements identified in this contract. Identify the qualified person's name and qualifications, training, and experience. Delineate the qualified person's authority to direct work stoppage in the event of hazardous conditions. Include procedure for rescue by contractor personnel and the coordination with emergency responders. (If there is no confined space work, include a statement that no confined space work exists and none will be created.)
SECTION 01 35 26 Page 8
d. Crane Critical Lift Plan.
Prepare and sign weight handling critical lift plans for lifts over 75 percent of the capacity of the crane or hoist (or lifts over 50 percent of the capacity of a barge mounted mobile crane's hoists) at any radius of lift; lifts involving more than one crane or hoist; lifts of personnel;
and lifts involving non-routine rigging or operation, sensitive equipment, or unusual safety risks. Submit 15 calendar days prior to on-site work and include the requirements of USACE EM 385-1-1, paragraph 16.H. and the following:
(1) For lifts of personnel, demonstrate compliance with the requirements of 29 CFR 1926.1400.
e. Fall Protection and Prevention (FP&P) Program Documentation. The program documentation shall be site specific and address all fall hazards in the work place and during different phases of construction. Address how to protect and prevent workers from falling to lower levels when they are exposed to fall hazards above 6 feet. A qualified person for fall protection shall prepare and sign the program documentation. Include fall protection and prevention systems, equipment and methods employed for every phase of work, responsibilities, assisted rescue, self-rescue and evacuation procedures, training requirements, and monitoring methods. Revise the Fall Protection and Prevention Program documentation or lengthy projects, reflecting any changes during the course of construction due to changes in personnel, equipment, systems or work habits. Keep and maintain the accepted Fall Protection and Prevention Program documentation at the job site for the duration of the project.
Include the Fall Protection and Prevention Program documentation in the Accident Prevention Plan (APP).
The FP&P Plan shall include a Rescue and Evacuation Plan in accordance with USACE EM 385-1-1, Section 21.M. The plan shall include a detailed discussion of the following: methods of rescue; methods of self-rescue; equipment used; training requirement; specialized training for the rescuers; procedures for requesting rescue and medical assistance; and transportation routes to a medical facility.
Include the Rescue and Evacuation Plan in the Fall Protection and Prevention (FP&P) Plan, and as part of the Accident Prevention Plan
(APP).
f. Site Demolition Plan. The safety and health aspects prepared in accordance with Section 02 41 00 DECONSTRUCTION and referenced sources.
1.7 ACTIVITY HAZARD ANALYSIS (AHA)
The Activity Hazard Analysis (AHA) format shall be in accordance with USACE EM 385-1-1, Section 1. Submit the AHA for review at least 15 calendar days prior to the start of each phase. Format subsequent AHAs as amendments to the APP. The analysis should be used during daily inspections to ensure the implementation and effectiveness of the activity's safety and health controls.
The AHA list will be reviewed periodically (at least monthly) at the Contractor supervisory safety meeting and updated as necessary when procedures, scheduling, or hazards change.
SECTION 01 35 26 Page 9
Develop the activity hazard analyses using the project schedule as the basis for the activities performed. Any activities listed on the project schedule will require an AHA. The AHAs will be developed by the contractor, supplier or subcontractor and provided to the prime contractor for submittal to the Contracting Officer.
1.8 DISPLAY OF SAFETY INFORMATION
Within one calendar day(s) after commencement of work, erect a safety bulletin board at the job site. Where size, duration, or logistics of project do not facilitate a bulletin board, an alternative method, acceptable to the Contracting Officer, that is accessible and includes all mandatory information for employee and visitor review, shall be deemed as meeting the requirement for a bulletin board. Include and maintain information on safety bulletin board as required by EM 385-1-1, section 01.A.06. Additional items required to be posted include:
a. Confined space entry permit.
b. Hot work permit.
1.9 SITE SAFETY REFERENCE MATERIALS
Maintain safety-related references applicable to the project, including those listed in the article "References." Maintain applicable equipment manufacturer's manuals.
1.10 EMERGENCY MEDICAL TREATMENT
Contractors will arrange for their own emergency medical treatment.
Government has no responsibility to provide emergency medical treatment.
1.11 NOTIFICATIONS and REPORTS1.11.1 Crane Reports
Submit crane inspection reports required in accordance with USACE EM 385-1-1, Appendix I and as specified herein with Daily Reports of Inspections.
1.11.2 Certificate of Compliance
Provide a Certificate of Compliance for each crane entering an activity under this contract (see Contracting Officer for a blank certificate).
State within the certificate that the crane and rigging gear meet applicable OSHA regulations (with the Contractor citing which OSHA regulations are applicable, e.g., cranes used in construction, demolition, or maintenance comply with 29 CFR 1926 and USACE EM 385-1-1 Section 16 and Appendix I. Certify on the Certificate of Compliance that the crane operator(s) is qualified and trained in the operation of the crane to be used. For cranes at DOD activities in foreign countries, certify that the crane and rigging gear conform to the appropriate host country safety standards. Also certify that all of its crane operators working on the DOD activity have been trained in the proper use of all safety devices (e.g., anti-two block devices). Post certifications on the crane. DRAFT
SECTION 01 35 26 Page 10
1.12 HOT WORK
Submit and obtain a written permit prior to performing "Hot Work" (welding, cutting, etc.) or operating other flame-producing/spark producing devices, from the Base Fire Chief. A permit is required from the Explosives Safety Office for work in and around where explosives are processed, stored, or handled. CONTRACTORS ARE REQUIRED TO MEET ALL CRITERIA BEFORE A PERMIT IS ISSUED. Provide at least two (2) twenty (20) pound 4A:20 BC rated extinguishers for normal "Hot Work". All extinguishers shall be current inspection tagged, approved safety pin and tamper resistant seal. It is also mandatory to have a designated FIRE WATCH for any "Hot Work" done at this activity. The Fire Watch shall be trained in accordance with NFPA 51B and remain on-site for a minimum of 30 minutes after completion of the task or as specified on the hot work permit.
When starting work in the facility, require personnel to familiarize themselves with the location of the nearest fire alarm boxes and place in memory the emergency Base Fire Chief phone number. ANY FIRE, NO MATTER
HOW SMALL, SHALL BE REPORTED TO THE BASE FIRE CHIEF IMMEDIATELY.
1.13 RADIATION SAFETY REQUIREMENTS
License Certificates for radiation materials and equipment shall be submitted to the Contracting Officer and Radiation Safety Office (RSO)for all specialized and licensed material and equipment that could cause fatal harm to construction personnel or to the construction project.
Workers shall be protected from radiation exposure in accordance with 10 CFR 20. Standards for Protection Against Radiation
Loss of radioactive material shall be reported immediately to the
Actual exposure of the radiographic film or unshielding the source shall not be initiated until after 5 p.m. on weekdays.
In instances where radiography is scheduled near or adjacent to buildings or areas having limited access or one-way doors, no assumptions shall be made as to building occupancy. Where necessary, the Contracting Officer will direct the Contractor to conduct an actual building entry, search, and alert. Where removal of personnel from such a building cannot be accomplished and it is otherwise safe to proceed with the radiography, a fully instructed employee shall be positioned inside such building or area to prevent exiting while external radiographic operations are in process.
Transportation of Regulated Amounts of Radioactive Material will comply with 49 CFR, Subchapter C, Hazardous Material Regulations. Local Fire authorities and the site Radiation Safety officer (RSO) shall be notified of any Radioactive Material use.
Transmitter Requirements: The base policy concerning the use of transmitters such as radios, cell phones, etc., must be adhered to by all contractor personnel. They must also obey Emissions control (EMCON) restrictions.
1.14 FACILITY OCCUPANCY CLOSURE
Streets, walks, and other facilities occupied and used by the Government shall not be closed or obstructed without written permission from the
SECTION 01 35 26 Page 11
1.15 SEVERE STORM PLAN
In the event of a severe storm warning, the Contractor must:
a. Secure outside equipment and materials and place materials that could be damaged in protected areas.
b. Check surrounding area, including roof, for loose material, equipment, debris, and other objects that could be blown away or against existing facilities.
c. Ensure that temporary erosion controls are adequate.
1.16 CONFINED SPACE ENTRY REQUIREMENTS.
Contractors entering and working in confined spaces while performing general industry work are required to follow the requirements of OSHA 29 CFR 1926 and comply with the requirements in Section 34 of EM 385-1-1, OSHA 29 CFR 1910, and OSHA 29 CFR 1910.146.
3.1 CONSTRUCTION AND OTHER WORK3.1.1 Hazardous Material Exclusions
Notwithstanding any other hazardous material used in this contract, radioactive materials or instruments capable of producing ionizing/non-ionizing radiation (with the exception of radioactive material and devices used in accordance with USACE EM 385-1-1 such as nuclear density meters for compaction testing and laboratory equipment with radioactive sources) as well as materials which contain asbestos, mercury or polychlorinated biphenyls, di-isocynates, lead-based paint are prohibited. The Contracting Officer, upon written request by the Contractor, may consider exceptions to the use of any of the above excluded materials. Low mercury lamps used within fluorescent lighting fixtures are allowed as an exception without further Contracting Officer approval. Notify the Radiation Safety Officer (RSO) prior to excepted items of radioactive material and devices being brought on base.
3.1.2 Unforeseen Hazardous Material
The design should have identified materials such as PCB, lead paint, and friable and non-friable asbestos and other OSHA regulated chemicals (i.e.
29 CFR Part 1910.1000). If material, not indicated, that may be hazardous to human health upon disturbance during construction operations is encountered, stop that portion of work and notify the Contracting Officer immediately. Within 14 calendar days the Government will determine if the material is hazardous. If material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If material is hazardous and handling of the material is necessary to accomplish the work, the Government will issue a modification pursuant to "FAR 52.243-4, Changes" and "FAR 52.236-2, Differing Site Conditions."
SECTION 01 35 26 Page 12
3.2 PRE-OUTAGE COORDINATION MEETING
Apply for utility outages at least five (5) days in advance. As a minimum, the request should include the location of the outage, utilities being affected, duration of outage and any necessary sketches. Special requirements for electrical outage requests are contained elsewhere in this specification section. Once approved, and prior to beginning work on the utility system requiring shut down, attend a pre-outage coordination meeting with the Contracting Officer to review the scope of work and the lock-out/tag-out procedures for worker protection. No work will be performed on energized electrical circuits unless proof is provided that no other means exist.
3.3 CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT)
Ensure that each employee is familiar with and complies with these procedures and USACE EM 385-1-1, Section 12, Control of Hazardous Energy.
3.4 FALL HAZARD PROTECTION AND PREVENTION PROGRAM
Establish a fall protection and prevention program, for the protection of all employees exposed to fall hazards. Within the program include company policy, identify responsibilities, education and training requirements, fall hazard identification, prevention and control measures, inspection, storage, care and maintenance of fall protection equipment and rescue and evacuation procedures.
3.4.1 Training
Institute a fall protection training program. As part of the Fall Hazard Protection and Prevention Program, provide training for each employee who might be exposed to fall hazards. Provide training by a competent person for fall protection in accordance with USACE EM 385-1-1, Section 21.B.
3.4.2 Fall Protection Equipment and Systems
Enforce use of the fall protection equipment and systems designated for each specific work activity in the Fall Protection and Prevention Plan and/or AHA at all times when an employee is exposed to a fall hazard.
Protect employees from fall hazards as specified in EM 385-1-1, Section
21. In addition to the required fall protection systems, safety skiff, personal floatation devices, life rings etc., are required when working above or next to water in accordance with USACE EM 385-1-1, Paragraphs 21.N through 21.N.04. Personal fall arrest systems are required when working from an articulating or extendible boom, swing stages, or suspended platform. In addition, personal fall arrest systems are required when operating other equipment such as scissor lifts if the work platform is capable of being positioned outside the wheelbase. The need for tying-off in such equipment is to prevent ejection of the employee from the equipment during raising, lowering, or travel. Fall protection must comply with 29 CFR 1926.500, Subpart M, USACE EM 385-1-1 and
ASSE/SAFE A10.32.
3.4.2.1 Personal Fall Arrest Equipment
Personal fall arrest equipment, systems, subsystems, and components shall meet ASSE/SAFE Z359.1. Only a full-body harness with a shock-absorbing lanyard or self-retracting lanyard is an acceptable personal fall arrest body support device.
SECTION 01 35 26 Page 13
Body belts may only be used as a positioning device system (for uses such as steel reinforcing assembly and in addition to an approved fall arrest system). Harnesses shall have a fall arrest attachment affixed to the body support (usually a Dorsal D-ring) and specifically designated for attachment to the rest of the system. Only locking snap hooks and carabiners shall be used. Webbing, straps, and ropes shall be made of synthetic fiber. The maximum free fall distance when using fall arrest equipment shall not exceed 6 feet.