This document is a Draft Statement of Work (SOW) for a parking lot maintenance project at the Colville Service Unit in Omak, Washington. The scope of work includes sealing cracks and joints in the asphalt surface, applying a commercial-grade weather-resistant seal coat, re-striping the parking area with high-visibility traffic-grade paint, and adding ADA-compliant markings. The project requires compliance with various codes and standards, including ABA accessibility standards, ASTM specifications, International Building Code, OSHA, and Washington State Building Code.
The contractor must provide pre-construction submittals, including a project schedule, safety plan, and quality control plan, and use specific materials such as asphalt emulsion-based seal coat, hot rubberized asphalt crack sealer, and thermoplastic markings. Quality assurance requirements include holding a valid Washington state contractor's license, OSHA construction safety certification, and providing a 1-year warranty. The work must be performed when environmental conditions are favorable, with paint application only allowed in dry weather above 45°F, and will involve detailed crack sealing, surface preparation, and precise parking lot striping procedures.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| DRAFT SOW - Fort Hall ID.zip | ZIP file | |
| DRAFT SOW - Annex and White Swan WA.docx | DOCX document | |
| DRAFT SOW - Nespelem WA.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C
DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
1. OVERVIEW
A. SITE LOCATIONS
Colville Service Unit Omak Building 2A: 916 Koala Dr, Omak WA A sitemap is included as Attachment A.
B. PROBLEM STATEMENTS
The parking lot surface of the Colville service unit in Omak, WA, has numerous cracks due to weather and wear, and the ADA markings are not visible.
C. OBJECTIVE
This project will provide necessary maintenance of the parking lot surfaces by applying a fresh top coat to help extend the useful life of the asphalt, as well as filling and repairing the cracks. Additionally, the project will re-stripe the parking area and add ADA markings.
D. WORK SUMMARY
1. Seal all cracks and joints in the asphalt surface
1. Apply a commercial-grade weather-resistant seal coat
1. Stripe with high-visibility, traffic-grade acrylic or latex paint. Add ADA-compliant markings
1. Provide submittal documenting the final inspection report, including before and after photographs.
1. Dispose of all refuse and debris at a legally established landfill.
1. Follow accepted standards for safe practice.
1. Perform inspections and tests to ensure quality and safety standards
II. TECHNICAL REQUIREMENTS
A. CODES, REFERENCES, AND STANDARDS
Work under this contract shall be performed in compliance with the codes, references, and standards listed below. The current version of all codes and standards shall be used.
1. ABA standards for accessible design
2. ASTM D3320 standard specification for Emulsified Asphalt
3. International Building Code (IBC)
4. OSHA/ TOSHA
5. Washington State Building Code (WSBC)
6. Washington State Department of Transportation “Standard Specifications for Road, Bridge, and Municipal Construction” Designation M 41-10, 2024 (WSDOT)
7. NFPA 101
8. NFPA 70
B. SUBMITTALS
The Contractor shall provide submittals on the items listed below. COR approval is required before proceeding with the portion of the work to which the submittal applies. Submittals shall be reviewed and approved within fourteen (14) working days of receipt.
1. Pre-Construction
a. Project Schedule
b. Safety and Accident Prevention Plan / Hazardous Waste Management and Disposal
c. Shop drawings
d. Control traffic plan and Contractor quality control plan
2. Materials
a. Asphalt emulsion-based seal coat
b. Asphalt crack sealer
c. Thermoplastic markings
d. Anti-stripping additive
3. Post Construction
a. Operation & Maintenance Information
b. Warranty
c. Completion report
d. Red-lined drawings
C. MATERIAL & EQUIPMENT SPECIFICATIONS
1. Seal coat
a. Commercial grade asphalt emulsion-based seal coat
b. ASTM D3320 Standard specification for emulsified asphalt
2. Crack sealing compound
a. Prepackaged, Hot rubberized asphalt crack sealer
b. ASTM D6690 Standard specification for Joint and Crack sealant
c. Application at least 40 degrees Fahrenheit
3. Stripping paint
a. High visibility traffic grade acrylic or latex paint
b. Waterborne acrylic alkyd traffic marking paint in colors indicated in the Washington State Department of Transportation “Standard Specifications for Road, Bridge, and Municipal Construction” Designation M 41-10, 2024 (WSDOT)
c. Paint to match the existing layout, including handicapped
1. ADA Marking
a. Thermoplastic markings for ADA symbols
b. ADA standards for accessible design, dimensions, and color contrast
B. QUALITY ASSURANCE
As written, the Contractor must only abide by this rule for the parking lot and nowhere else. The Contractor shall perform all work in a manner that meets all accepted standards for safe practices during operations and maintains safe conditions of the premises at all times, including the safe storage of equipment, machines, and materials. This includes compliance with Tribal and Federal laws, as well as OSHA and/or TOSHA regulations, at all times to protect all persons, including the Contractor’s employees and the Owner, against injury or damage to property.
1. All work must be performed by a valid general contractor’s license in the state of Washington
2. OSHA construction safety certification for the site supervisor
3. Offer a 1-year warranty period for the construction
4. Have an interim life safety measures plan assessment.
5. Verify that all walkways meet design specifications and quality standards.
6. Contractor must hold all relevant state and local licenses for performing asphalt maintenance and striping work, i.e., National Pavement Contractors Association (NPCA), National Asphalt Pavement Association (NAPA).
C. WORK EXECUTION REQUIREMENTS
Parking lot
· Clean and seal all cracks and joints greater than or equal to 1/8 inch in the asphalt surfaces by applying hot mix asphalt to provide a waterproof bond, in accordance with the crack sealant manufacturer’s recommendations and the Washington State Department of Transportation's “Standard Specifications for Road, Bridge, and Municipal Construction,” Section 5-03.
· The crack should be slightly overfilled and leveled with a 3-inch sealing disk or a V-shaped squeegee.
· Crack sealing should only occur when environmental conditions are favorable and in accordance with the manufacturer’s recommendations for the crack sealant. Final crack cleaning will occur on the same day as the sealing operation.
· The existing asphalt surface shall be cleaned in accordance with the Washington State Department of Transportation “Standard Specifications for Road, Bridge, and Municipal Construction” Chapter 5-03.3(1), and all debris resulting from the cleaning must be removed from the site by the Contractor. The contractor will furnish all necessary equipment, supervision, labor, materials, tools, traffic control, and incidentals for the job.
Strip Painting/ADA marking
· The parking lot and curbs shall be painted according to the manufacturer’s recommendations. The Contractor shall verify measurements and evaluate actual site conditions.
· Parking stalls shall be painted white.
· All paint shall have a minimum film thickness of 15 mils, and lines shall be 4 inches wide.
· The international symbol of accessibility shall comply with the ABA Standards for Accessible Design.
· The pavement markings shall include the delineation of parking stalls, crosswalks, access routes, no parking zones, and handicapped parking designations.
· Paint shall be applied in dry weather and only when the pavement and atmospheric temperatures are above 45°F and are anticipated to remain above 45°F for eight hours after completion.
· Application will not be permitted when precipitation is anticipated or when temperature and humidity conditions are such that the paint cannot dry thoroughly.
· The paint will be applied with mechanical equipment to produce uniform, straight edges.
Crack Sealant (Fog seal)
· Follow the manufacturer’s recommendations for crack cleaning.
· Use prepackaged, hot-pour rubberized asphalt crack sealer specifically formulated for slow-moving vehicle traffic and foot traffic, such as parking lots.
· Should be compatible with the climatic temperature, falling within the manufacturer’s minimum application temperature and maximum heating temperature.
· The Contractor is required to follow the Recommended Performance Guideline for Fog seals checklist developed by the Federal Highway Administration
Testing
Before testing, samples of each aggregate source must be taken, including a representative sample and a random sample, as recommended by the WBDG (Inspector’s Manual for Hot-Mixed Asphalt and Portland Cement Concrete Pavement Construction), Chapter 3-2.2. Ensure that the samples do not cool down before compaction of the mix is conducted. If this occurs, do not reheat the samples. The acceptable tests will be performed by the contractor/ manufacturer.
· Asphalt content to determine the amount of asphalt; ASTM D6307 tested by ignition or ASTM D2172 tested by solvent extraction. WBDG (Inspector’s Manual for Hot-Mixed Asphalt and Portland Cement Concrete Pavement Construction) chapter 3-8.5
· Air voids to ensure good mixture performance; ASTM D3203. WBDG (Inspector’s Manual for Hot-Mixed Asphalt and Portland Cement Concrete Pavement Construction) chapter 3-8.6
· Stability and flow on the compacted asphalt mixtures; ASTM D6927. WBDG (Inspector’s Manual for Hot-Mixed Asphalt and Portland Cement Concrete Pavement Construction) chapter 3-8.8
1. Kickoff Meeting:
a. A kickoff meeting with the COR is required to evaluate and understand the building layout and project needs.
2. Closeout Procedures:
a. Provide Operation and Maintenance (O&M) Manual
b. Submit copies of Operation and Maintenance Manuals three days in advance of applicable demonstrations and trainings.
c. Provide warranty information for all materials within the O&M documentation. If the manufacturer requires registration for warranty tracking or offers upgrades as a result of registration, include all registration information and instructions on how to submit it.
d. Submit complete project package
3. Closeout Meeting
a. The Contractor shall coordinate a closeout meeting with the Contracting Officer Representative (COR) and the Facility Manager.
b. Contractor shall record and provide meeting minutes.
I. ATTACHMENTS
A. Site Map II. Attachment A – Colville Service Unit Omak image1.png