- Replacement of Computer Room Air Conditioners
- Solicitation number
- 140G0125R0007
About this file
This is a Statement of Work (SOW) for a design-build project to replace and install Computer Room Air Conditioning (CRAC) units at the USGS/Earth Resources Observation and Science (EROS) Center in Sioux Falls, South Dakota. The project requires installing seven dual-cool CRAC units (22-ton and 30-ton units) with chilled water as the primary cooling source and backup compressors across three computer rooms. The scope includes removing five existing units and adding two new units.
The contractor must provide all design, installation, and startup services within 360 days of Notice to Proceed. Key requirements include: designing/installing chilled water piping compatible with existing Honeywell building automation systems, analyzing and installing new electrical distribution components, providing dust control measures, and maintaining continuous operation of computer rooms during installation. The contractor must provide warranties of 1 year for parts and 2-5 years for compressors. Deliverables include construction documents within 60 days of NTP, construction schedule, submittal log, and as-built drawings. The contractor must coordinate with the COR for utility shutdowns with 48-hour advance notice and conduct at least two mandatory site visits during construction.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment_1_-_Industry_Questions_1_-_140G0125R0007_2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EROS Science Center Design / Build
Dual Cool CRACs Units
STATEMENT OF WORK
Introduction
The Department of Interior, USGS/Earth Resources Observation and Science (EROS) Center, Sioux Falls, South Dakota is seeking firms to Design/Build new Computer Room Air Conditioning (CRAC) units at the Mundt Federal Building, located at the EROS Science Center, 47914 252nd Street, Sioux Falls SD 57198.
EROS data center has computer room air conditioner (CRAC) units and these units need to be replaced due to age. Some units are chilled water only and some are dual-cool units with compressors. EROS data center will be installing dual-cooled type CRAC units with chilled water as primary source of cooling with backup compressors to eliminate the need for a computer room outage during rare service times. The installation and startup of the CRAC units will be completed by the contractor furnishing the CRAC units.
Scope Contractor shall perform all work in accordance with the specifications, drawings, and all applicable Federal, State, and local regulations. Drawings will be given to parties after attending the site-visit and filing paperwork with the Contracting Officer for release of documents.
This SOW includes:
Section 1 – General Requirements Attachment A – Project Drawings Attachment B – Basis of Design.
Section 1 – General Requirements
II. STATEMENT OF WORK
A. Project Scope/Objectives:
Remove designated CRAC units and replace with a dual cool unit as indicated on the project drawings. The replacement units are to be 22-ton and 30-ton dual cool units unless indicated otherwise on attachment A. Attachment A will show the approximate location of the CRAC units and the final location shall be determined by the Government. Building automation controls shall be compatible with existing Honeywell system. Building Automation to control operation of the unit, start/stop, humidity, temperature, and alarm points will be incorporated to be reported for remote monitoring. New CRAC units shall communicate with existing CRAC units via factory provided electronics and control cooling load with factory provided electronics between similar CRAC units. Minimum specifications shown on Attachment B – Basis of Design. Units are located in each of the following rooms:
• Computer Room 1:
A/C #2 – Model No. DE267W-AA0I, Serial No. 547515-001
• Replace with a new 22-ton CRAC A/C #5 – Model No. DE267W-AA0I2644, Serial No. C08H7F0033
• Replace with a new 30-ton CRAC A/C-8 – New 30-ton CRAC
• Computer Room 2:
CR2 AC-1 – Model No. FH529C-AAM, Serial No. 364077-002
• Replace with a new 22-ton CRAC CR2-AC-3 – Model No. CW084DCVA3S406, Serial No. N12K140017
CR2-AC-8 – new 30-ton CRAC
• Computer Room 3:
LIEBERT #2 CR-3 – Model No. FH529C-AA0G, Serial No. 531292-001
1. Furnish, install, and start-up SEVEN (7) dual cool CRAC units. Attached drawings will show the approximate locations of CRAC units. Final location shall be determined by the Government. Minimum specifications shown on Attachment B – Basis of Design.
2. Design/Install chilled water piping to connect CRAC units to the building chilled water loop and condenser water loops (Victaulic or equivalent) without shutting down water flow to the facility. Water control valves to be placed at both the branch connections and in the plenum to service the units in an emergency if they do not exist. Water supply and return lines line to have a drain valve for service. Insulation to be provided shall be a minimum of 2” wall thickness or minimum required by the manufacturer.
3. The contractor shall analyze existing CRAC unit electrical distribution and install new electrical distribution components from specified motor control center per manufacturers requirements should the requirements of the new unit be different from the existing unit.
4. Furnish and install all piping, insulation, wiring, controls and other accoutrements as needed for fully functional operation.
5. Temporary valves and alternative control operation will need to be reviewed by the Government with the Contractor and the onsite O&M maintenance contractor.
Work shall be phased. The ‘new’ CRAC unit in each room shall be installed and connected to chilled water and condenser water prior to the removal and installation of the next CRAC unit to maintain operation of each respective computer room.
6. Warranty Period of 1 year for parts, and 2nd through 5th year for compressor warranty (parts only) will be required. Provide cut sheet data on warranty if periods vary or options for warranties.
7. Period of Performance from Notice to Proceed shall be 360 days.
III. PROJECT SPECIFICATIONS
1. Contractor is to field verify all site conditions.
2. Provide submittal data on the CRAC unit, humidifier, base frame, economizer unit, all other electrical, distribution, mechanical, and structural components within the AIA format.
3. Provide submittal data such as cut sheet data as to the controls and verify compatibility with Honeywell Enterprise Buildings Integrator (EBI) controls.
Control graphics will be by owner.
4. Provide plan for dust control to ensure that the room and equipment will not be subjected to construction debris or dust.
5. Staging area will be made available to the contractor and is in the basement area of the Computer Room 3. Packaging debris will be removed by the contractor.
C. Design Scope – Code Compliance: The design shall comply with all current governing specifications including but not limited to: NFPA 101 – Life Safety Code, NFPA 70, Federal , and local building codes.
D. Design Scope – Sustainability: Consult the USGS Sustainability Construction
Checklist (Attachment A) for incorporating sustainability into the design of the project.
E. General Requirements:
1. Recycled Materials: Coordinate the safe disposal of existing materials and metals removed from the EROS worksite.
2. Utility Shutdowns: The USGS has a mandatory requirement to obtain approval for utility shutdowns. Requests for utility shutdowns shall be made at least 48 hours in advance. Consider these shutdowns for planning and phasing purposes. Contractor shall coordinate with the COR.
IV. ADMINISTRATIVE PROCEDURES
A. A site visit will be held at the USGS EROS Science Center, 47914 252nd Street, Sioux Falls SD 57198. The Statement of Work and the existing conditions of the site proposed for the work will be reviewed. At this time the offerors will have the opportunity to review and obtain copies of As-Built Drawings and other USGS materials necessary to prepare a proposal.
B. After award of a contract and issuance of the Notice to Proceed, all site visits shall be coordinated through the Contracting Officer’s Representative (COR). A copy of the COR’s authorized duties and responsibilities will be provided with the Notice-to-Proceed.
C. All Contractor personnel, their sub-contractors and representatives visiting USGS sites will be required to sign in upon arrival. Each visiting individual will be required to enter their name, their company’s name, USGS project title, date, reason for the visit, and the times of arrival and departure. Additionally, all persons must always wear a visitor’s badge which is to be returned prior to leaving daily.
D. Prime contractor is required to provide construction oversight of all sub-contractors during construction. No work shall be done unless the prime contractor is on-site to supervise.
V. MATERIAL TO BE PROVIDED TO THE CONTRACTOR BY THE USGS
A. The USGS shall provide the Contractor with copies of existing EROS record drawings.
VI. DELIVERABLES
A. Meeting Minutes: The contractor shall take minutes of all conferences and other meetings with the USGS (including site visits) and shall provide a copy to the COR for a concurrence signature.
B. Drawings and Specifications: At each design review the Contractor shall present to the COR drawings showing location and extent of work, the design concept, and working drawings used to illustrate methods and proposed constructability of the Work. It is the intent of these presentations to achieve approval for the concept, to address any potential problems, and to make necessary changes before further progress of the design. Completed AutoCAD drawing sets and MS Word specifications making up each design review and final submission shall be organized to American Institute of Architects (AIA) and, Construction Specifications Institute (CSI) conventions. Each drawing sheet shall include the following paragraph: “PROPERTY OF THE UNITED STATES
GOVERNMENT. COPYING, DISSEMINATION, OR DISTRIBUTION OF THESE
DRAWINGS, PLANS, OR SPECIFICATIONS TO UNAUTHORIZED USERS IS
PROHIBITED. Do not remove this notice. Properly destroy documents when no longer needed.”
C. Submittal Log: The contractor shall develop a list of all submittals required by each individual specification. The register should include specification reference, and item to be reviewed and approved.
D. Construction Schedule: The contractor shall provide a preliminary construction schedule indicating the entire length of time estimated for the completion of the construction contract, measured in weeks, and provide a commensurate Gantt chart for the construction activities, including critical path items. This schedule shall include pre-construction activities (such as submittals and mobilization), specific construction activities/events, special phasing requirements and final activation of the new space.
Contractor shall update this schedule as needed or as requested to reflect accurate project timelines.
VII. DESIGN REVIEWS – SCHEDULES AND REQUIREMENTS
The following design submissions will be required:
Final Submission (Final Construction Documents)
1. Provide Review Documents in hard copy and digital in both original (i.e., AutoCAD, MS Word, Excel, etc.) format and PDF format to the COR. Quantities shall be as indicated for each design review submission.
2. Examine the schedules set forth below and recommend to the USGS any improvements in the allocations of time allowed for each phase, the net effect of which would be to either provide more time for phases needing more time or to shorten the entire design schedule.
A. Final Submittal – Final Construction Documents This submission is the final delivery of approved construction documents. This shall be submitted within 60 calendar days after the NTP. Submit to the COR.
1. The contractor shall provide two (2) hard copy sets of Construction Documents
(drawings and bound specification) and digital Construction Documents in both original (i.e., AutoCAD, MS Word) format and PDF format.
2. Fully developed Construction documents, Phasing Requirements and Engineering Calculations which support the documentation set out in this paragraph.
3. A complete construction schedule.
4. A complete submittal log form.
VIII. CONSTRUCTION PERIOD SERVICES
A. General: The Contracting Officer reserves the right to terminate any construction period services, without payment for services not completed, if such services are not needed or are not being adequately completed.
B. Response to RFI’s: The contractor shall provide expeditious responses to all design/conflict questions encountered during the construction term. Within 24 hours of receipt from COR provide in writing the information, clarification or revision material needed to properly answer the RFI and to resolve the issue. Include a cost/credit estimate for RFI’s which result in a change to construction contract cost.
C. Submittal Review: Contractor submittals shall be sent to the Government for review for adherence to contract requirements. Forward recommendations of approval/disapproval to the COR within 7 calendar days. The COR shall take final action of approval/ disapproval on each submittal and shall prepare and send a formal return of submittal to the contractor.
D. Site Visits: Day to day construction administration will be performed by the COR. Site visits shall be at the request of the COR to inspect work installed by the contractor, to resolve issues, review the status of in-progress as-built drawings and for other reasons deemed necessary. At a minimum 2 visits will be required during construction. One, when the contractor mobilizes and has presented plan for dust control and dust control plan is completed and when the final walk through inspection is scheduled.
E. Record drawings: Upon completion of construction, provide (2) sets of stamped
"Architectural E1" (30"x42") as built drawings, as well as in AutoCAD and PDF formats.
They shall be completed within 30 days after receipt of the redlined prints and submitted to the COR.
END OF STATEMENT OF WORK