This is a Statement of Work (SOW) for a TPO roofing system installation project at the Department of Veterans Affairs (VA) Puget Sound – American Lake Campus in Tacoma, Washington. The contractor must furnish all labor, materials, equipment, and supervision to replace an existing failing torchdown roof above laboratory storage rooms in Building 81 with a complete TPO roofing system, including membranes, underlayment, insulation, flashing, sealants, and finish materials. The project includes management of seven air conditioning units that must remain functional and require recovery, removal, and reinstallation over a single weekend to minimize laboratory downtime. The contractor must submit all roofing materials and penetration designs for Contracting Officer's Representative (COR) approval and must coordinate scheduling with the COR to manage AC unit downtime.

Work must be completed within 120 calendar days from notice to proceed and includes removal of existing roofing, inspection of roof decking for damage, installation of the new TPO system in accordance with manufacturer specifications and industry standards, reinstallation of AC units using approved lineset roofjack fixtures, recharging and testing by a licensed technician, and final water testing at seams and penetrations with COR present. Performance monitoring will be conducted by the designated COR with support from Facilities Management Service subject matter experts. Security requirements mandate contractor escort by FMS staff during work. Acceptance criteria include successful water leak testing, aesthetic matching of flashings to original specifications, and full AC unit operability verified by facility maintenance personnel. The project is classified under NAICS Code 238160 (Roofing Contractors) with a small business size standard of $19 million, and the location of performance is 9600 Veterans Drive SW, Building 81, Tacoma, WA 98493.

View the file

Other files

File Type Posted
36C26026Q0790.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

as of 04/07/2026

Contract Number:
(completed by the CO at time of award)
Task Order Number:
(completed by the CO at time of award if a TO)

IFCAP Tracking Number:

1. Contracting Officer’s Technical Representative (COTR).

Name:

Section:
American Lake Facilities Maintenance Service
Address:
9600 Veterans Dr SW, Tacoma WA 98493

Phone Number:

Fax Number:

E-Mail Address:

2. Background.

The small flat roof above the laboratory storage rooms in Building 81 has experienced persistent leaks for several years. Although multiple repairs have been attempted, including large applications of tar, the roof continues to fail. The existing torch‑down roof will be replaced with a TPO roofing system to provide a long‑term solution. The area includes seven AC units that cool the laboratory below and must remain functional nearly year‑round.

3. Scope.

The Contractor shall furnish all labor, materials, equipment, and supervision necessary to provide and install a complete TPO roofing system. The roofing system shall be a fully integrated, weather‑resistant assembly that includes all required roofing membranes, underlayment, insulation, flashing, sealants, and finish roofing materials. The system shall be installed in accordance with applicable manufacturer specifications, industry standards, and governing codes. When completed, the roofing system shall provide continuous, complete, and effective protection of the enclosed space below from all external environmental elements, including precipitation, wind, temperature intrusion, and moisture. The air conditioning down-time shall be limited to a weekend to have negligible effect on laboratory operations.

4. Additional Scope Coordinate scheduling with the COR to reduce downtime associated with AC unit removal and reinstallation. Recovery, removal, reinstallation, and recharging of any AC units will be completed over laboratory weekend downtime to limit effect on laboratory operations.

• Evacuate and recover refrigerant; remove split-unit AC units. Large AC unit may be lifted in order swap roofing underneath without complete removal.

• Remove existing roofing materials entirely.

• Inspect roof decking and underlying materials for damage.

• Install new membranes, insulation, and TPO roofing system (all materials must be submitted for approval).

• Install roof penetrations and reinstall AC units (penetration designs must be COR approved) using lineset roofjack fixtures or comparable COR approved product.

• Charge and test AC units in accordance with manufacturer requirements using a licensed technician.

• Install flashing materials (flashings must be approved by the COR).

• Conduct a final inspection and water test to verify performance.

5. Performance Monitoring

Performance monitoring for this project will be conducted by the designated Contracting Officer’s Representative (COR), who is responsible for Government Quality Assurance, and supported by Facilities Management Service (FMS) subject matter experts, who will provide technical oversight to verify the contractor’s Quality Control measures are properly implemented.

6. Security Requirements

Contractors will be escorted by FMS staff during repairs and when entering the hospital. Badging will not be required due to escort presence.

7. Inspection and Acceptance Criteria

Testing upon completion will consist of the following.

a) Leak-testing with water hose at all seams and penetrations with COR present. HVAC (Heating Ventilation and Air Conditioning) line penetrations will be installed using lineset roofjack fixtures installed using manufacturer's instructions.

b) View of roofing from ground level will match the historic look prior to work starting, to include color and style of flashings.

c) AC units will be inspected for leaks and proper operation by Facility Maintenance Support HVAC employees. The units shall be free of leaks and fully operational. Leak testing will be conducted with refrigerant detection meters as well as soapy water method at all disturbed connections.

The COR is responsible for certifying that the work done under the contract is performed to time and standard. They are also responsible to assure the inspection and acceptance of products provided incidental to services.

8. Risk Control

Demo and installation work will be performed on a weekend to minimize temperature impact on the laboratory staff. No roofing or other material will be thrown or dropped from the rooftop and the area below will be cordoned off. PPE to include tethers for roofers and hardhats for workers on the ground will be used

9. Place of Performance.

9600 Veterans Drive SW, Building 81, Tacoma WA 98493

10. Period of Performance.

120 days from issuance of the notice to proceed.