This is a Draft Statement of Work for upgrading the heated and chilled seawater system at the Northeast Fisheries Science Center (NEFSC) Milford Laboratory, located at 212 Rogers Ave, Milford, Connecticut 06460. The National Marine Fisheries Service (NMFS), part of NOAA under the Department of Commerce, is the contracting agency. The project involves installing an Alfa Laval T6-PFG heat exchanger with EPDMP gaskets, isolation ball valves, a temperature control pneumatic valve, temperature transmitter, temperature and pressure indicators on an epoxy-coated steel skid, a 6-inch Thompson replacement impeller on the distribution pump, and upgrading piping to 2-inch sizes on chilled and heated saltwater tanks. Additionally, the contractor must install a GF Signet conductivity probe (Series 2819), Series 2850 electronics, and Series 9900 GF Signet transmitter with field installation and data logger wiring for salinity control. All work must comply with manufacturer specifications and industry best practices.
The contractor must have a minimum of 3 years verifiable experience installing marine seawater systems. Project completion is required within 45 to 60 calendar days of contract award. All equipment, materials, manpower, permits, testing, and fees are the contractor's responsibility. The contractor must obtain NOAA/NMFS NEPA approval in writing before commencing work, maintain quality control, and provide two hours of training and commissioning for two facility personnel. Required submittals include a schedule, material list with manufacturer cut sheets, Safety Data Sheets, and a safety plan, all due within 5 to 10 days after Notice to Proceed. The contractor must comply with OSHA, NEC, NFPA, and EPA requirements; maintain a site superintendent on-site during work; work hours are 7:00 AM to 3:30 PM, Monday through Friday; and provide a one-year warranty on all labor and materials with no dollar limitation. Pre-bid site visits are recommended and should be scheduled at least two working days in advance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Presolicitation Notice SSD_Redacted 143021-26-0122 (1).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAFT
Statement of Work for
Milford Heated & Chilled Seawater System Upgrades at the Northeast Fisheries Science Center Milford, CT Laboratory
212 Rogers Ave Milford, CT 06460
DESCRIPTION
A.The Northeast Fisheries Science Center (NEFSC) Milford Laboratory is located at 212 Rogers Ave Milford, CT 06460.
B.The National Marine Fisheries Service (NMFS), a part of the National Oceanic and Atmospheric Administration (NOAA) of the Department of Commerce (DOC), is a governmental agency charged with the mission of stewardship for living marine resources.
C.The Contractor shall be fully knowledgeable of all requirements of the contract documents and shall make themselves aware of all job site conditions that will affect their work. The contractor shall verify all dimensions prior to submitting a quote.
D.The Contractor shall verify all dimensions and equipment prior to submitting bid quotation.
E. This project involves upgrading the current Milford Laboratory heated and chilled seawater system, installed by Burt Process Equipment in by adding a Alfa Laval T6-PFG heat exchanger, Isolation Ball Valves, Temperature Control Pneumatic valve, Temperature Transmitter, Temperature and Pressure Indicators mounted on an epoxy-coated steel skid. In addition, adding (1) GF Signet Conductivity Probe, Series 2819 probe, Series 2850 electronics, (1) Series 9900 GF Signet Transmitter, Field installation of conductivity probe and Field wiring for data logger for the salinity system.
F. All equipment, equipment rentals, material, manpower, permits, testing, and fees shall be the responsibility of the contractor.
G.The Contractor shall have a minimum 3 years of verifiable experience in installing marine seawater systems.
H. Site and Project Location: 212 Rogers Ave Milford, CT 06460.
PRE-BID SITE VISIT
It is recommended that a site visit be conducted prior to submitting a quote in order to view site conditions, verify locations, verify measurements, and equipment. Please plan to coordinate site visits at least two working days in advance of intended site visit.
SCOPE OF WORK
A. Pre-Work and Permit Application
● The contractor shall be fully knowledgeable of all contract requirements.
● Contractor shall at all times ensure Work is accomplished in accordance with the terms and conditions of the contract in a safe and professional manner. Contractor is responsible for damage to any Government equipment, supplies, or facilities caused by Contractor personnel.
● The contractor shall ensure all required skill sets are obtained and maintained for performance under this contract.
● The contractor shall obtain NOAA, NMFS NEPA approval in writing prior to project commencement.
● Quality Control is the responsibility of the Contractor . The Contractor is responsible for all incidental repairs.
● All supplies, materials, and equipment for this project will be prior approved by the COR.
B. Heated and Chilled Seawater System Upgrades (all parts and equipment are brand name or equivalent)
● The Contractor shall isolate and lockout/tag out all utilities to ensure a safe working environment.
● The Contractor shall install Alfa Laval T6-PFG with EPDMP heat exchanger for sizing requirement upgrades.
● The Contractor shall Install Isolation Ball Valves, Temperature Control Pneumatic valve, Temperature Transmitter, Temperature and Pressure Indicators all mounted on epoxy-coated carbon steel skid.
● The contractor shall install (1) Finish 6” Thompson Replacement Impeller on the distribution pump to accommodate pressure drop of additional equipment.
● The contractor shall modify Existing Equipment. To include Increase pipe inlet sizes on chilled saltwater tank and heated saltwater tank to 2”to accommodate upsized plumbing, 2” actuated ball valves and manual isolation valves, Additional Baumann Little Scotty 24000 proportional control valve and Include solenoid control and air filter/regulator.
● The contractor shall install and provide the following for salinity control.
(1) GF Signet Conductivity Probe o Series 2819 probe o Series 2850 electronics
• (1) GF Signet Transmitter o Series 9900
• Field installation of conductivity probe
• Field wiring for data logger
● The Contractor shall update the existing control panel programming to accommodate new equipment.
● The Contractor shall insure proper operation of all system components.
● Supply all ancillary equipment, materials not specifically referenced required to complete the work such as support hangers, hardware, signs, and labels.
● The Contractor shall provide two hours of training and commissioning for two facility personnel.
1. Deliverables
● (20) Alfa Laval titanium plates with EPDMP gaskets installed on an existing heat exchanger
● Isolation Ball Valves On heated and salt-water inlets and outlets.
● Baumann Little Scotty 24000 Temperature Control Pneumatic valve.
● Endress + Hauser TH13 Temperature Transmitter.
● Temperature and Pressure Indicators on heated water inlet and outlets.
● (1) 6” Finish Thompson Replacement Impeller on distribution pump to accommodate pressure drop of additional equipment.
● Increase pipe inlet sizes on chilled saltwater tank and heated saltwater tank to 2” to accommodate upsized plumbing
● 2” actuated ball valves and manual isolation valves.
● Additional Baumann Little Scotty 24000 proportional control valve.
● (1) GF Signet Conductivity Probe o Series 2819 probe o Series 2850 electronics
● (1) GF Signet Transmitter o Series 9900
● Includes field installation.
● includes updates to control panel programming to accommodate new equipment.
● 2 hours of training
● All material and supplies documents/specifications sheets.
2. Timeline The project will be completed within 60 days of contract award.
3. Performance Standards
● All work must be performed in accordance with industry best practices and comply with local, state, and federal regulations.
● The final product will enable the seawater system to provide sufficient quantities of heated and chilled seawater for scientific operations.
4. Responsibilities of the Contractor
● Provide all necessary labor, materials, tools, and equipment to complete the project.
● Maintain open communication with the owner throughout the duration of the project, addressing any issues or concerns promptly.
ACCESS TO WORK SITE
A.All persons employed within the boundaries of the property or restricted-access areas therein, and all persons permitted to enter such property and areas shall comply with the security regulations for the NEFSC Milford Laboratory.
B.The Government reserves the right to close down the job site and order Contractor Personnel off the premises in the event of a national emergency or a shutdown, for as long as security problems persist. The Contractor may only return to the site with verbal approval from the COR.
C.The Government reserves the right to exclude or remove from the site or building any employee of the Contractor or a sub-Contractor whom the Government deems incompetent, careless, insubordinate or otherwise objectionable, or whose continued employment on the work is deemed by the Government to be contrary to the public interest.
FINAL ACCEPTANCE AND INSPECTIONS
A.Inspection of work to be performed by the NEFSC Facilities Operations Manager -COR.
Any corrective action required because of the inspection will be accomplished prior to final billing.
B. The Contractor may be notified of deficiencies in performance in writing by the COR.
Oral deficiency notifications will be confirmed in writing. The Contractor shall take prompt corrective action upon notice of deficiency.
C. The Contractor shall advise the Government when all work is completed. The Government will not accept the work until it determines that all work has been satisfactorily completed within the terms of the contract.
EXISTING CONDITIONS
If discrepancies are discovered between the existing conditions and those noted on the SOW/drawings, immediately notify the COR. Upon receipt of Bidding Documents, verify documents are complete. Notify COR if documents are incomplete. Immediately notify COR upon finding discrepancies or omissions in Bidding Documents.
PERIOD OF PERFORMANCE
A.The actual start date shall be coordinated with the COR.
B.Upon notice to proceed, the Contractor shall be required to complete work within 45 calendar days.
SUBMITTALS
The Contractor shall submit the following:
●Schedule (5 days after NTP) ●Material List/Manufactures cut sheets (5 days after NTP).
●Safety Data Sheets (SDS) (10 days after NTP) ●Safety Plan (5 days after NTP)
DELIVERY, STORAGE, HANDLING, AND PROTECTION
A.Deliver materials to the job site in the manufacturer’s original, unopened containers or wrappings with the manufacturer’s name, brand name and installation instructions intact and legible. Deliver in sufficient quantity to permit work to continue without interruption.
B.Comply with the manufacturer’s written instructions for proper material storage.
C. Any damaged materials shall be removed and replaced at the Contractors expense.
D. Care shall be taken to provide protection of surrounding structures, hallways and buildings structures.
QUALITY CONTROL
A.The Contractor shall submit manufacture cut sheets and other specification literature for all materials to be installed for the COR approval.
B.All work described in the Statement of Work shall comply with the manufacturers installation guidelines.
C.The Contractor shall furnish all labor, materials, tools, transportation, services and supplies as stated in this requirement.
D.Work shall be completed in accordance with the construction industry standards and codes.
E. The Contractor shall supply the COR with the onsite supervisor contact information and any other key personnel.
WARRANTY
The Contractor shall provide a written warranty for service including labor and materials for a period of one year from the date of startup with no dollar limitation. Including but not limited to all manufacturers warranties.
USE OF THE PREMISES
Before beginning work, the Contractor shall secure approval from the COR for the following:
A. Contact the COR for parking information and facility access.
B.Access to the site.
C.Areas permitted for storage of materials and debris.
D.Security: Obey the government’s requirements for personnel identification, inspection and other security measures.
E. The NEFSC is a smoke free campus. The Contractor and its employees shall adhere to all applicable rules and regulations regarding maintenance of a smoke free environment on the job site.
F. Use of Government facilities
1. Water and electricity for construction purposes are available at the work site.
2. The Contractor shall provide toilet facilities. Location of temporary facilities shall be coordinated with the owner's representative or the COR.
3. The contractor shall provide storage for tools and materials. The Government is not responsible for providing storage or security of materials, tools, or equipment.
G. The premises will be occupied during the performance of the work. Contractor to coordinate work with the COR to accommodate the work schedule, continuing access and completion date.
H. Working hours shall be 7:00 AM – 3:30 PM (M-F). Contractor shall observe all federal holidays.
WORKMANSHIP
All work shall be of highest quality and in strict accordance with the manufacturer’s published specifications and to the building owner’s satisfaction, most recent codes and standards.
QUALITY ASSURANCE
A.Unless otherwise noted in the contract documents, Contractor shall comply with the manufacturer’s current specifications and details.
B.The Contractor shall provide adequate number of experienced workers regularly engaged in this type of work who are skilled in the application techniques of the materials specified.
C.There shall be a site superintendent on the job site at all times while work is in progress.
The site superintendent must be an employee of the general Contractor and on the site all times during the course of any ongoing work.
D.There shall be no deviations made from this specification or the approved shop drawings (if any) without the prior written approval of the COR. Any deviation from the manufacturer’s installation procedures must be supported by a written certification on the manufacturer’s letterhead and presented to the COR for consideration.
E. All substitution requests for products, equipment, materials and methods described within the contract documents shall be submitted to the COR. Substitution requests are not permitted prior to the Notice to Proceed. Substitute products will be considered when the request is submitted in writing to the COR. The COR will have seven (7) working days to approve/disapprove substitution request. Substitution request shall not result in schedule extensions.
FACILITIES AND CONTROLS
A.The Contractor shall remove and dispose of all debris and trash from the job site in a timely and legally acceptable manner to not detract from the aesthetics or the functions of the building.
B.Contractor shall comply with all applicable Federal, State, and local laws and regulations concerning environmental pollution prevention control and waste disposal.
C.Contractor shall immediately inform the COR of any environmentally hazardous situations that may arise as well as contact required regulatory agencies.
D. Perform daily clean up to collect all wrappings, empty containers, paper, and other debris from the project site. Upon completion, all debris must be disposed of in a legally acceptable manner. The Contractor shall ensure that the project area and areas adjacent to the project area are maintained in a clean and safe condition.
SAFETY
A.The Contractor shall be responsible for all means and methods as they relate to safety and shall comply with all applicable OSHA, NEC, NFPA, and EPA, local, state and federal requirements. Safety shall be the responsibility of the general Contractor. All related personnel shall be instructed daily to be mindful of the full time requirement to maintain a safe environment for the facility’s occupants including staff, visitors, customers and the occurrence of the public on or near the site.
B.The Contractor shall comply with the requirements of 29 CFR, Part 1910: Occupational Safety and Health Administration (OSHA) General Industry and Health Standards, and Health Administration (OSHA) General Industry and Health Standards and 29 CFR, part 1926 Construction Standards. The Contractor shall promptly correct any non-complying work or conditions. Contractor shall be responsible to ensure its work does not affect the safety of the public or employees of the Government. Neither the Government nor its representatives shall bear any responsibility for safety precautions at the project work site.
If, however, in the opinion of the COR a life-threatening condition exists, the COR will orally (to be confirmed in writing) require the Contractor to immediately suspend work in the affected area until the condition is corrected. Whenever Contractor’s operations may create a hazardous condition, it shall at its sole expense, furnish, install and maintain such guards, fences, barricades, railing, light, signs, or other devices necessary to prevent accident, injury or damage to people or equipment.
C.Five days prior to start of work, Contractor shall submit a safety plan. To include but not limited, open flames, welding, debris, cleanup, work place safety methods, and emergency procedures. The Safety Plan must be available on site at all times and must be reviewed with all sub-Contractors working under this contract for the duration of the contract project.
D. It is the Contractor’s responsibility to ensure all employees; sub-Contractors, venders, and other company representative adhere to all safety rules, regulations, policies and practices.
E. Contractor shall observe lock/out tag/out regulations and as required by OSHA.
F. The Contractor shall keep the project site in a neat and orderly condition at all times.
JOB CONDITIONS, CAUTIONS AND WARNINGS
A.Safety Data Sheets (SDS) must be on location at all times during the transportation, storage and application of materials. A separate set shall be given to the COR fifteen (15) days prior to starting of the work.
B.The Contractor shall not cause or permit any hazardous material to be brought upon, kept or used in or about the premises by its agents, employees, or sub-Contractors without the prior consent of the COR. Hazardous materials that are necessary to the performance of this contract shall be used, kept and stored in a manner that complies with all laws regulating any such hazardous material brought upon or used or kept at this site. Contractor shall provide Safety Data Sheets to the COR for any hazardous materials used in the performance of this contract.
C.As used herein, the term “Hazardous Material” means any hazardous or toxic substance, material, or waste, including but not limited to, those substances, materials, and wastes listed in the Department of Transportation Hazardous Material Table (49 CFR 172.101) or by the Environmental Protection Agency as hazardous substances (40CFR Part 68.130) and amendments thereto, petroleum products, or such other substances, material, and wastes that are or become regulated under any applicable local, state, or Federal Law.
PERSONNEL
A.The Contractor shall provide proof that all on-site employees are legal aliens or WE citizens.
B.The Contractor shall not employ personnel with felony convictions, or with a record of narcotics use, for work at any NEFSC property.
APPENDIX 1
PROFESSIONAL AGENCIES, ASSOCIATIONS, CODES, COUNCILS, INSTITUTES,
AND STANDARDS
Air-Condition and Refrigeration Institute ARI Air Movement and Control Association International, Inc. AMCA American Bearing Manufactures Association ABMA American Concrete Institute ACI American Ladder Institute ALI American Institute of Steel Construction AISC American National Standards Institute ANSI American Plywood Association APA American Society of Civil Engineers ASCE American Society for Testing and Materials ASTM American Society of Mechanical Engineers ASME American Welding Society AWS American Wood Preserve Bureau AWPB American Wood Protection Association AWPA Building Officials and Code Administrators BOCA California Roof Rating Council CRRC Clean Air Act CAA Clean Water Act CWA Chain Link Fence Manufacturing Institute CLFMI Code of Federal Regulation CFR Concrete Reinforcing Steel Institute CRSI Construction Specification Institute CSI Department of Environmental Protection DEP Electronic Industries Alliance EIA Environmental Protection Agency EPA Gypsum Association GA International Organization for Standardization ISO Institute of Electrical and Electronic Engineers IEEE Leadership in Energy and Environmental DesignLEED Metal Lath/Steel Framing Association ML/SFA National Asphalt Pavement Association NAPA National Association of Corrosion Engineers NACE National Electric Code NEC National Fire Protection Association NFPA National Institute of Standards and Technology NIST National Sanitation Foundation NSF
National Society of Professional Engineers NSPE Occupational Safety and Health Act OSHA National Electric Manufactures Association NEMA Plastic Pipe Institute PPI Portland Cement Association PCA Precast/Restressed Concrete Institute PCI Resource Conservation and Recovery Act RCRA Steel Door Institute SDI Telecommunication Industry Association TIA Uniform Construction CodeUCC Underwriters Laboratories UL United States Army Corps of Engineers USACE United States Coast Guard USCG United States Green Building Council USGBC Western Wood Products Association WWPA Western Wood Preservation Institute WWPI
APPENDIX 2
ACRONYMS
Air-Condition and Refrigeration Institute ARI Air Movement and Control Association International, Inc. AMCA American Bearing Manufactures Association ABMA American Concrete Institute ACI Asbestos Containing Material ACM American Institute of Steel Construction AISC American National Standards Institute ANSI American Plywood Association APA American Society of Civil Engineers ASCE American Wood Preserve Bureau AWPB American Wood Protection Association AWPA Above ground Storage Tank AST American Society for Testing and Materials ASTM American Society of Mechanical Engineers ASME American Welding Society AWS Best Management Practices BMP Building Officials and Code Administrators BOCA
California Roof Rating Council CRRC Clean Air Act CAA Clean Water Act CWA Chain Link Fence Manufacturing Institute CLFMI Chromatid Copper Arsenate CCA Cubic Feet per Minute CFM Code of Federal Regulation CFR Concrete Masonry Unit CMU Concrete Conc Contracting Officer CO Contracting Officers Representative COR Contracting Officers Technical Representative COTR Demarcation point
DEMARC
Demolition Demo Department of Environmental Protection DEP Drawing Dwg Ethylene Propylene Diene Monomer EPDM Electronic Industries Alliance EIA Elevation Elev Encased Burial EB Environmental Protection Agency EPA Feet Ft Factory Mutual FM Finish Floor FF Fire Rated FR Fiberglass Reinforced Product FRP Gauge Ga General Contractor GC Gallons per Minute GPM Gypsum GYP Gypsum Association GA International Organization for Standardization ISO Inch In Information Technology IT Institute of Electrical and Electronic Engineers IEEE Leadership in Energy and Environmental DesignLEED Linear Feet LF Maximum MAX Metal Lath/Steel Framing Association ML/SFA Mean High Water MHW Mean Low Water MLW
Mile Per Hour MPH Material Safety Data Sheets MSDS National Electric Code NEC National Fire Protection Association NFPA National Institute of Standards and Technology NIST National Sanitation Foundation NSF Notice To Proceed NTP Not To Scale NTS On Center OC Ounce OZ Outside Diameter OD Occupational Safety and Health Act OSHA No Added Urea Formaldehyde NAUF National Electric Manufactures Association NEMA Not To Scale NTS Parts Per Billion PPB Parts Per Million PPM Pounds lbs Pounds per Square Inch PSI Polyvinyl Chloride PVC Professional Engineer PE Programmable Logic Controllers PLC Resource Conservation and Recovery Act RCRA Schedule Sch Steel Door Institute SDI Square Feet SF Statement Of Work SOW Solar Reflectance Index SRI Sound Transmission Class STC Square Sq Telecommunication Industry Association TIA Thick Thk Typical Typ Uniform Construction CodeUCC Underwriters Laboratories UL United States Army Corps of Engineers USACE United States Coast Guard USCG United States Green Building Council USGBC Veneered Faced Panel Products HPVA Underground Storage TankUST Vinyl Asbestos Floor Tile VAT
Volatile Organic Carbon VOC Welded Wire Fabric WWF Western Wood Products Association WWPA
A.
Appendix 1 Existing Equipment
File details come from the government source that posted it. Updated .