Draft PWS_VA Fiber Optic Supply Services.pdf
PDF 196 KB Posted
- Solicitation number
- 36C25626Q0559
About this file
This is a Performance Work Statement for fiber optic cable installation at the Michael E. DeBakey VA Medical Center in Houston, Texas. The project requires the contractor to install four separate fiber runs connecting Building B-100 (Main Hospital) to Building 108 (VA Police) with an estimated total cable length of approximately 8,500 feet. Fiber run #1 consists of 12-strand single-mode armor-jacketed cable (2,300 feet) from the 6th floor of Building 100 to the IT closet room in Building 108 for an upgraded radio system. Fiber run #2 uses 12-strand single-mode cable (2,100 feet) from the basement IDF room in Building 100 to Building 108 for license plate reader support. Fiber run #3 and #4 are both approximately 2,100 feet of single-mode and multi-mode OM4 cable respectively, running from Building 100's basement IDF room to Building 108's IT room for Building Automation System (BAS) replacement. All fiber must be installed inside flexible inner duct liner and routed through building basements and existing manholes.
For each fiber run, the contractor must provide wall-mounted racks, 12-port patch panels, fiber enclosures, fan-out kits, adapter panels, connectors, splice connectors, and cable supports, with all fiber terminated, labeled, and tested upon completion. The work must be completed within 60 calendar days from contract award, with the VA preferring the earliest reasonable completion date. The contractor must possess five years of experience in fiber installation and submit a Permit Required Confined Space program for VA approval prior to starting work. A one-year labor and materials warranty is required from the date of project completion. The VA will provide government utilities, a small storage area if available, toilet and washroom facilities, and authorized parking for equipment. The contractor is responsible for daily debris removal, compliance with OSHA and NFPA standards, obtaining short-term VA identification badges for all personnel, and maintaining normal medical center operations throughout the project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25626Q0559_RFI.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAFT
PERFORMANCE WORK STATEMENT
MICHAEL E. DEBAKEY VA MEDICAL CENTER
HOUSTON, TEXAS
Project Title: Install Fiber B-108 VA Police
1. GENERAL:
Contractor shall provide all labor, transportation, materials, tools, and equipment necessary to replace damaged fiber and install new fiber between Building B-100 (Main Hospital) and
Building 108 VA Police at the DeBakey VA Medical Center at 2002 Holcombe, Houston, TX
77030. This is a total of 4 fiber runs required.
2. DESCRIPTION OF SERVICES:
a. Fiber run #1, contractor shall provide all labor, material, equipment and supervision to install new single mode fiber run from Building 100, 6th floor to building 108 IT closet room for upgraded radio system.
1. Fiber to be Armor Jacketed Single Mode 12 Strand Direct Burial Cable
OSP and installed inside flexible inner duct liner. Estimated length is 2300 ft, and the contractor to verify.
2. Provide and install wall mounted rack and shelf to hold switch and fiber rack enclosure.
3. Provide and install 12 port patch panel and rack mounted fiber panel.
4. Provide and install one fiber enclosure in dispatch room.
5. Include all related connections, fan-out-kit for Fiber Ends, adapter panel for
Fiber Bulkheads, Fiber connectors and splice connectors, cable supports.
6. Cable pathway will be from B-108 dispatch through IT room to the basement.
From the basement to connections to manholes that connect to B-100. Once in
B-100 run to mechanical room 6 and then vertical to the 6th floor.
7. All fiber to be terminated, labeled and tested.
b. Fiber run #2, contractor will provide all labor, material, equipment and supervision to install new single mode fiber run from Building 100, basement IDF room to building 108
IT closet room, for VA Police support for license plate reader.
1. Fiber to be Armor Jacketed Single Mode 12 Strand Direct Burial Cable
OSP and installed inside flexible inner duct liner. Estimated length is 2100 ft, and the contractor to verify.
2. Provide and install wall mounted rack and shelf to hold switch and fiber rack enclosure.
3. Provide and install 12 port patch panel and rack mounted fiber panel.
4. Provide and install one fiber enclosure in dispatch room.
5. Include all related connections, fan-out-kit for Fiber Ends, adapter panel for Fiber Bulkheads, Fiber connectors and splice connectors, cable supports.
6. Cable pathway will be from B-108 dispatch through IT room to the basement. From the basement to connections to manholes that connect to
B-100. Once in B-100 run to mechanical room 6 in the basement and then to the adjacent IDF room.
7. All fiber to be terminated, labeled and tested.
c. Fiber run #3, contractor will provide all labor, material, equipment and supervision to install new single mode fiber run from Building 100, basement IDF room to building 108
IT room. This single mode fiber is for the BAS replacement fiber.
1. Fiber to be Armor Jacketed Single Mode 12 Strand Direct Burial Cable
OSP and installed inside flexible inner duct liner. Estimated length is 2100 ft, and the contractor to verify.
2. Provide and install wall mounted rack and shelf to hold switch and fiber rack enclosure.
3. Provide and install 12 port patch panel and rack mounted fiber panel.
4. Provide and install one fiber enclosure in dispatch room.
5. Include all related connections, fan-out-kit for Fiber Ends, adapter panel for Fiber Bulkheads, Fiber connectors and splice connectors, cable supports.
6. Cable pathway will be from B-108 IT room to the basement. From the basement to connections to manholes that connect to B-100. Once in B-
100 run to mechanical room 6 in the basement and then to the adjacent
IDF room.
7. All fiber to be terminated, labeled and tested.
d. Fiber run #4, contractor will provide all labor, material, equipment and supervision to install new multi-mode fiber run from Building 100, basement IDF room to building 108
IT room. This multi-mode fiber is for the BAS replacement fiber.
1. Fiber to be Armor Jacketed Multi Mode 12 Strand Direct Burial Cable
OM4 and installed inside flexible inner duct liner. Estimated length is
2100 ft, and the contractor to verify.
2. Provide and install wall mounted rack and shelf to hold switch and fiber rack enclosure.
3. Provide and install 12 port patch panel and rack mounted fiber panel.
4. Provide and install one fiber enclosure in dispatch room.
5. Include all related connections, fan-out-kit for Fiber Ends, adapter panel for Fiber Bulkheads, Fiber connectors and splice connectors, cable supports.
6. Cable pathway will be from B-108 IT room to the basement. From the basement to connections to manholes that connect to B-100. Once in B-
100 run to mechanical room 6 in the basement and then to the adjacent
IDF room.
7. All fiber to be terminated, labeled and tested.
e. All work shall be accomplished within sixty (60) calendar days from the date designated by the Contracting Officer. The VA would like this work to be accomplished as soon as reasonably possible.
f. Contractor shall provide Permit Required Confined Space program to the VA COR for review prior to starting any work.
g. All new materials and components will be tested (by the contractor at their expense) and be fully functional upon completion of installation.
1. Make all necessary fiber connections.
2. Follow manufacturer’s installation instructions.
3. Damage caused by the contractor during this project to any existing surfaces shall be repaired to the original condition at the Contractors expense.
4. Any changes to this SOW shall be authorized and approved only through written correspondence from the CO.
5. All installed items shall be new. All work shall meet current local, state, and national codes and requirements.
6. Provide manufactures warranty information.
7. Contractor Qualifications: The installation contractor shall have 5 years’ experience in this type of installation.
3.0 ATTACHMENTS
Attachments are supplied for background information only. It may not show the current status of the equipment. Field measurements and observation must be used to gather all necessary information.
Attachment 1: Overall site plan for reverence and routing.
Note that these attachments are the best available data that the VA has. The installed equipment may differ from this information and field verification of actual conditions are necessary.
4.0 SUBMITTALS
Before installing new components, the Contractor shall submit to the MEDVAMC the following:
Permit Required Confined Space program, material submittals
The VA shall check and approve the contractor's material submittals for conformity with the
PWS Documents. All submittals shall be in electronic .pdf format.
5.0 CODE REQUIREMENTS
The VA shall be responsible for obtaining necessary local agency approvals as required.
All work shall comply with all local, state, and federal rules and regulations. In the event of a code discrepancy the stricter of the ordinances shall prevail.
6.0 BIDDING REQUIREMENTS
Please itemize out all bids.
7.0 WARRANTY
A one-year labor and materials warranty is required from the date of project completion (BOD) as formally determined by the government.
8.0 PROPOSED SCHEDULE:
Work shall commence upon contract award from the government and shall be completed within 60 calendar days after award.
Phasing: Normal medical center operations must be maintained.
9. WORK LOCATION:
The work site location is at the Michael E. DeBakey VA Medical Center in Houston, TX, main campus
10. GOVERNMENT FURNISHED PROPERTY AND SERVICES
The Government will provide the following:
• Government Utilities. The Government will furnish electricity and water for the contractor’s use incidental to contract performance at the location being serviced.
• Facilities: The Government will provide a small area for the Contractor to store equipment used to complete the requirements under the contract if space is available.
• Toilet and washrooms for the technicians employed by the Contractor in the performance of this contract.
• Contractor will be allowed to use the VA Canteen Service for breaks and lunches.
Contractor will not use any other location throughout the facility for such purposes.
Parking is rigidly controlled throughout the Medical Center. Contractor parking is only allowed in authorized areas. Contractor shall abide by all police requirements. Parking in designated patient parking areas is strictly prohibited. Parking for equipment necessary to perform the work will be authorized in advance of starting the project. On-site parking will be in the parking lot adjacent to the parking garage. Contractor will be allowed to load and unload at the work site as needed for performance under the contract.
11.0 DEBRIS REMOVAL
The Contractor shall be required to remove waste materials and debris from the campus daily and at the completion of the project. All waste material and debris shall be removed off the site by the contractor and shall be disposed of in accordance with applicable State and Federal regulations. The work area must be maintained in a safe working condition and OSHA and NFPA fire prevention standards must be observed during the duration of the project.
12.0 PROJECT SAFETY:
The contractor shall perform work in a safe manner as required by OSHA Safety and Health
Requirements. Provide a verbal report to the CO as soon as possible of each occurrence of damage to
Government property or an accident resulting in death, injury, occupational disease, or adverse environmental impact. Provide a completed copy of required Accident Investigation Reports to the CO within five calendar days of each occurrence.
Contractor shall comply with the following and keep a copy of any permits on site at all times:
• MEDVAMC ICRA requirements
13. PERFORMANCE ASSESSMENT:
The COR will conduct a 100% surveillance inspection of work requirements and services for subject contract. After the completion and before leaving the site, the Contractor shall contact the
COR for final inspection. The COR will document and sign off inspection results. The inspector will inform the contractor of inspection results and any unacceptable result shall require re-performance at no additional cost to the Government. Any unsatisfactory inspection (defect) result shall be corrected. All work shall be done in a first-class manner according to the best trade practices and to the satisfaction of the Project Manager.
14. SECURITY:
All contractor personnel shall obtain a short-term identification badge issued by the VA. Such badge shall be worn by the individual and prominently displayed at all times while on VA property. No employee of the contractor shall enter the project site without a valid identification badge issued by the VA. In order to obtain a short-term identification badge, contractor personnel shall present to the
Project Manager two valid (non-expired) photo identification issued by a US federal, state or local government agency.
All contractor personnel are subject to inspection of personal effects when entering or leaving the project site.
End of PWS