This is a draft construction contract for the City of New Smyrna Beach, Volusia County, Florida, for the T-Hangar E Renovation project awarded through sealed competitive bid solicitation ITB 11-26-AIR. The scope of work includes complete renovation of a 16,600 square foot hangar structure at the New Smyrna Beach Municipal Airport, encompassing site improvements, taxiway markings, pavement work, drainage provisions, landscaping modifications, sodding, utility modifications with a $20,000 allowance, safety and maintenance of traffic, and mobilization capped at ten percent of total project cost. The project is divided into two work areas with a maximum total contract time of sixty consecutive calendar days from the Notice to Proceed, with work to commence within ten calendar days of that notice and substantial completion required within sixty days, followed by final completion within an additional thirty days. The non-mandatory pre-bid meeting and site visit occurred on March 9, 2026 at 10:30 am at the gate to Hangar E; written questions were due by March 17, 2026 at 5:00 pm; sealed bids were submitted electronically through the City's eProcurement Portal by March 31, 2026 at 5:00 pm with public opening on April 1, 2026 at 10:00 am; and City Commission award recommendation was scheduled for April 28, 2026.

The contract price is to be determined by the accepted bid proposal and negotiated agreed-upon contract price, with payment made in current funds according to the awarded bid proposal. Liquidated damages are assessed at $250 per consecutive calendar day for work not completed within the specified timeframe. Qualified contractors must submit a bid bond equal to no less than ten percent of the bid amount and provide performance and payment bonds equal to one hundred percent of the contract price within fourteen days of bid acceptance. The project is federally funded through a Florida Department of Transportation grant combined with local share, with contract award contingent upon FDOT concurrence. Contractors must demonstrate compliance with prevailing wage provisions under the Davis-Bacon Act, E-Verify employment verification requirements, comprehensive insurance coverage with the City named as additional insured, and various federal and state regulations including Title VI of the Civil Rights Act of 1964, Section 504 of the Rehabilitation Act of 1973, the Americans with Disabilities Act of 1990, and the Airport and Airway Improvement Act of 1982. Disadvantaged business enterprise participation requirements apply to this federally-funded project. Contractors must execute the contract within fifteen calendar days of award notification and provide a Human Trafficking Affidavit.

View the file

Other files for this state and local contract opportunity

Other files attached to T-Hangar E Renovation, newest first.
File Type Posted
T-Hangar_E_Renovation_(Addendum_#4_Revision).pdf PDF
T-Hangar_E_Renovation_(Addendum_#3_Revision).pdf PDF
T-Hangar_E_Renovation_(Addendum_#1_Revision).pdf PDF
DRAWINGS.pdf PDF
DRAWINGS.pdf PDF
DRAWINGS.pdf PDF
City_Forms_.pdf PDF
City_Forms_.pdf PDF
City_Forms_.pdf PDF
Draft_Contract.pdf PDF
Draft_Contract.pdf PDF
SPECIFICATIONS.pdf PDF
SPECIFICATIONS.pdf PDF
SPECIFICATIONS.pdf PDF
Bond_Forms.pdf PDF
Bond_Forms.pdf PDF
Bond_Forms.pdf PDF
Federal_Contract_Provisions.pdf PDF
Federal_Contract_Provisions.pdf PDF
Federal_Contract_Provisions.pdf PDF
Public_Records.pdf PDF
Public_Records.pdf PDF
Public_Records.pdf PDF
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contractor’s Initials: _______

Page | 1 of 4 Construction Contract, Rev. 01/26

CONSTRUCTION CONTRACT

CITY OF NEW SMYRNA BEACH

VOLUSIA COUNTY, FLORIDA

This Agreement, dated this day of _ _ _ _ _ _ , 2026, by and between the CITY OF

NEW SMYRNA BEACH, hereinafter called the OWNER, and

____ __ I n c . (a corporation organized and existing under the laws of the

State of Florida and hereinafter called the CONTRACTOR, is awarded as a result of solicitation

ITB 11-26-AIR, T-Hangar E Renovation.

WITNESSETH: The Owner and the Contractor, for the consideration stated herein, agree as follows:

ARTICLE I: Scope of Work

The Contractor shall perform all required work and shall provide and furnish all labor, materials, necessary tools, expendable equipment, and all utility and transportation services required to complete the construction of and all appurtenant work thereto, described in the following document, hereby fully incorporated into this Contract:

ITB 11-26-AIR, T-Hangar E Renovation

City of New Smyrna Beach, Florida

All work shall be in strict compliance with the drawings and specifications, including any and all

Addenda, and together with all Contract Documents hereinafter enumerated and made a part thereof.

It is understood and agreed that said labor, materials, tools, equipment, and service shall be furnished and said work performed and completed subject to the approval of the Owner.

ARTICLE II: Contract Price

The Owner shall pay the Contractor for performance of the work in accordance with the Contract

Documents in current funds as follows:

Spelled out: _ ___________

Payment will be made in accordance to the awarded bid proposal and the above negotiated agreed upon

Contract Price. Change orders, including additions and deductions, must be approved in writing by the Owner. Any change, where the Contractor has materially deviated from the proposed design shall be borne by the Contractor unless such deviation is agreed to in writing by Owner.

ARTICLE III: Contract Time

The Contractor agrees to commence work within Ten (10) CALENDAR DAYS after the date of the Notice to Proceed letter and shall achieve Substantial Completion within Sixty (60) consecutive

Page | 2 of 4 Construction Contract, Rev. 01/26 calendar days thereafter. The Contractor shall have an additional thirty (30) consecutive calendar days from the date of Substantial Completion to achieve Final Completion.

ARTICLE IV: Inspection by Contractor

The undersigned Contractor agrees that he has carefully inspected all Contract Documents and is familiar with same; the Contractor agrees that he is responsible for having heretofore examined the site, the location and route of all the proposed work and for having satisfied himself as to the character of the route, the location, surface and under-ground obstructions and nature thereof, the nature of the groundwater conditions and other physical characteristics of the work and work area in order that he may include in the prices which he has bid and the prices of the Contract, all costs pertaining to the work and thereby provide for the satisfactory completion thereof and determination of the Contract prices herein agreed upon, and that this Contract price is based upon these inspections and examination.

ARTICLE V: Liquidated Damages

If the work is not completed within the time specified in Article III of this Contract, the Contractor shall pay the Owner, as liquidated damages, the sum of TWO HUNDRED FIFTY DOLLARS

($250) for each consecutive calendar day thereafter until the work is completed, and as outlined in the Supplemental General Conditions.

ARTICLE VI: Right to Require Performance

The failure of the City at any time to require performance by the Contractor of any provision hereof shall in no way affect the right of the City thereafter to enforce same or be considered a waiver of such provision, nor shall a waiver by the City of any breach of any provision hereof be taken or held to be a waiver of any succeeding breach of such provision or as a waiver of any provision itself.

ARTICLE VII: Component Parts of the Contract

This Contract consists of the following Contract Documents, all of which are hereby made a part hereof as if herein set out in full and all of which are familiar to the Contractor:

• City Advertised Bid w Construction Specifications, Drawings and Addendums

• Awarded Bid Proposal w Bid Bond

The Contractor must provide the following documents within fourteen (14) days upon acceptance of the bid by City Commission. All of which are familiar to the Contractor and are component parts of the contract.

• Certificate of Insurance

• Performance/Payment Bond

Upon completion of the project, the Contractor shall provide the Owner with the Warranty of

Title.

ARTICLE VIII: Severability

Should any term, covenant, condition, provision or sentence or part thereof of this Contract, including all Contract Documents which comprise the entire agreement, be held invalid or

Page | 3 of 4 Construction Contract, Rev. 01/26 unenforceable by any court of competent jurisdiction, the remaining terms and provisions shall nevertheless remain in full force and effect.

ARTICLE IX: Force Majeure

No Party shall be liable or responsible to the other party, nor be deemed to have defaulted under or breached this Agreement, for any failure or delay in fulfilling or performing any term of this

Agreement, except for any obligations to make payments to the other party hereunder, when and to the extent such failure or delay is caused by or results from acts beyond the impacted party’s control, including but not limited to, the following force majeure events:

a) Acts of God

b) A natural disaster (fires, explosions, earthquakes, hurricanes, flooding, storms, infestations, epidemic or pandemic)

c) War, invasion, hostilities (regardless if war is declared or not), terrorist threats or acts, riots or other civil unrest

d) Government order or law

e) Actions, embargoes or blockades in effect on or after the date of this Agreement

f) Action by any governmental authority

g) National or regional emergency

h) Strikes, labor stoppages or slowdowns or other industrial disturbance, and

i) Shortage of adequate power or transportation facilities

The Impacted Party shall give notice within two (2) days of the Force Majeure Event to the other party, stating the period of time the occurrence is expected to continue. The impacted party shall use diligent efforts to end the failure or delay and ensure the effects of such Force Majeure Event are minimized. The Impacted Party shall resume the performance of its obligations as soon as reasonably practicable after the removal of the cause. In the event that the Impacted Party’s failure or delay remains uncured for a period of sixty (60) days following Notice given by it, then either party may thereafter terminate this Agreement upon Notice

Notwithstanding the foregoing, any pandemic or epidemic, including but not limited to those related to COVID-19 and its mutations, and related issued executive orders and/or administrative orders by any federal, state, or local government entity related to any pandemic or epidemic, shall

NOT be considered a force majeure and is expressly excluded from that definition herein and said even shall not prevent CONTRACTOR from timely performing its functions under this Agreement

ARTICLE X: Human Trafficking

This Contract is subject to the terms, conditions, provisions and requirements of Section 787.06 of the Florida Statutes and Contractor hereby represents, warrants, and certifies that Contractor does not use coercion for labor or services as defined in Section 787.06, Florida Statutes and that Contractor has provided the Human Trafficking Affidavit.

ARTICLE XI: Construction

The headings and subheadings used throughout the Contract Documents are for convenience only and have no other significance in the interpretation of the body of the Contract Document.

Page | 4 of 4 Construction Contract, Rev. 01/26

IN WITNESS WHEREOF, the parties hereto have made and executed this Agreement on the date written above for execution by the City of New Smyrna Beach.

Attest Vendor Name

Authorized Signature

Authorized Signature

Print Name and Title

Print Name and Title

Address

Address

City, State, Zip

City, State, Zip

Date

Date

ATTEST CITY OF NEW SMYRNA BEACH

Sharon Taylor-Harding, City Clerk Fred E. Cleveland, Mayor

Date:

For the use and reliance of the City of New Smyrna Beach only. Approved as to form and legal sufficiency.

Carrie Avallone, Esq, City Attorney

Date: _______________________________

Approved by the City Commission of the City of New Smyrna Beach at a meeting held on this

___ day of _____________, 2026 under Agenda Item No. .

File details come from the government source that posted it. Updated .